Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following logic: Unless the Social Work team lives in the village, the Mother and Child Health Programme cannot be started due to ignorance and superstition of the villagers The Analysis of the survey can obviously be done only after the survey is complete. Until rural survey is done, the Rural Credit Programme cannot be started Unless Mother and Child Programme is established, the Immunization of Under Fives cannot be started – Calculate the Earliest and Latest Event Times – Tabulate and Analyze the Activities – Schedule the Project Using a Gantt Char
A Social Project manager is faced with a project with the following activities:
Activity-ID Description Duration
1-2 Social Work Team to live in Village 5 Weeks
1-3 Social Research Team to do survey 12 Weeks
3-4 Analyse results of survey 5 Weeks
2-4 Establish Mother & Child Health Program 14 Weeks
3-5 Establish Rural Credit Programme 15 Weeks
4-5 carry out Immunisation of under Fives 4 Weeks
- Draw the arrow diagram, using the helpful numbering of the activities, which suggests the following logic:
- Unless the Social Work team lives in the village, the Mother and Child Health Programme cannot be started due to ignorance and superstition of the villagers
- The Analysis of the survey can obviously be done only after the survey is complete.
- Until rural survey is done, the Rural Credit Programme cannot be started
- Unless Mother and Child Programme is established, the Immunization of Under Fives cannot be started
- – Calculate the Earliest and Latest Event Times
- – Tabulate and Analyze the Activities
- –
Schedule the Project Using a Gantt Char
Step by step
Solved in 2 steps with 3 images