Task Name Normal time Normal Crash time Crash cost (slope) Predecessor cost 4. 85 3. 10 5. 100 4. 30 30 4. 25 D AB 4. 90 3. 25 B.C 2 05 21 F. D. 4 100 4 G. D.E 90 20 H. E 80 35 F.G.H 85 Based on the above, the first activity that is selected to reduce the project duration is The project duration at the CRASH POINT (the minimum possible duration for the project) is days. The indirect cost with normal times is $300 and there is a savings of $25 per period reduced. The crash cost (cost at the CRASH POINT) is S The optimum cost-time schedule (the schedule with minimum total cost and corresponding time) is periods and $ Note: Enter the values for each item within square brackets.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

please help

Task
Name
Crash
cost
(slope)
Normal
Normal
Crash
time
Predecessor
time
cost
4.
35
3.
10
B.
100
4.
30
30
4
25
D
AB
90
3
25
В.С
2.
95
F
D
4
100
4
G
D.E
2
90
20
4
B0
35
F.G.H
85
Based on the above, the first activity that is selected to reduce the project duration is
The
project duration at the CRASH POINT (the minimum possible duration for the project) is
days. The indirect cost with normal times is $300 and there is a savings of $25 per period reduced The crash cost (cost at
the CRASH POINT) is S
The optimum cost-time schedule (the schedule with minumum
total cost and corresponding time) is
periods and $
Note: Enter the values for each item within square brackets.
Transcribed Image Text:Task Name Crash cost (slope) Normal Normal Crash time Predecessor time cost 4. 35 3. 10 B. 100 4. 30 30 4 25 D AB 90 3 25 В.С 2. 95 F D 4 100 4 G D.E 2 90 20 4 B0 35 F.G.H 85 Based on the above, the first activity that is selected to reduce the project duration is The project duration at the CRASH POINT (the minimum possible duration for the project) is days. The indirect cost with normal times is $300 and there is a savings of $25 per period reduced The crash cost (cost at the CRASH POINT) is S The optimum cost-time schedule (the schedule with minumum total cost and corresponding time) is periods and $ Note: Enter the values for each item within square brackets.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Knowledge Booster
Business reports
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.