a. Draw the precedence diagram. b. What is the probability that the project can be completed in 24 days or less? In 21 days or less? c. Suppose it is now the end of the seventh day and that activities A and B have been completed, while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the proj- ect by day 24 and the probability of finishing by day 21. TIME IN DAYS
a. Draw the precedence diagram. b. What is the probability that the project can be completed in 24 days or less? In 21 days or less? c. Suppose it is now the end of the seventh day and that activities A and B have been completed, while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the proj- ect by day 24 and the probability of finishing by day 21. TIME IN DAYS
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![Preview File Edit
90% O E
Q O
Go Tools Window Help
a Stevenson, W. J. - Operations management. (14th ed.). McGraw-Hill-Mcgraw-Hill (2021).pdf (page 806 of 929)
O a bearch
Rev
How many weeks after the original start time should the project be finished?
7. Three recent college graduates have formed a partnership and have opened an advertising firm.
Their first project consists of activities listed in the following table.
operations
notes
6100
Stevenson,
a. Draw the precedence diagram.
W. J..21).pdf
b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?
c. Suppose it is now the end of the seventh day and that activities A and B have been completed,
while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,
6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the proj-
ect by day 24 and the probability of finishing by day 21.
nd impre
o you w
CExtra
Screen Shot
20228 PM
DOCK
G
resume 2021
TIME IN DAYS
Vaccine and
other info
Immediate
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
Screen Shot
2022-06 PM
A
5
6
7
росх
DOCX
B
8
8.
11
Resume
A
8
11
2/21/22
12
15
Password
E
F
D
6
7
Screen Shot
G
2
3
7
2022-41 PM
XLSX
H
B
4
4
Hw operation o Job
4.xisx
7
8.
Searc...notes
End
E, G, I
d. The partners have decided that shortening the project by two days would be beneficial, as long
as it doesn't cost more than about $20,000. They have estimated the daily crashing costs for each
activity in thousands, as shown in the following table. Which activities should be crashed, and
what further analysis would they probably want to do?
Screen Shot
2022 21 PM
Activity
First Crash
Second Crash
$8
$10
Screen Shot Screen Shot Screen Shot
1 20229 PM 2022-.5 PM 20228 PM
D
10
11
10
F
CALL-DUTY
MW2
G
9
10
H.
7
8
6
8
"Belk Collége
Undergraduate Career
Screen Shot. Screen Shot Call of Duty
2022-.19 PM 2022-..6 PM 2022-.0 PM/20227 PM 2022-..3 PM Mode.rfare 2
Group
Weight
Resources](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F09aea477-ce83-43e0-b5a2-b232364d033a%2F69bb2009-6eff-4932-a134-164f94137781%2Fq9t7yxn_processed.png&w=3840&q=75)
Transcribed Image Text:Preview File Edit
90% O E
Q O
Go Tools Window Help
a Stevenson, W. J. - Operations management. (14th ed.). McGraw-Hill-Mcgraw-Hill (2021).pdf (page 806 of 929)
O a bearch
Rev
How many weeks after the original start time should the project be finished?
7. Three recent college graduates have formed a partnership and have opened an advertising firm.
Their first project consists of activities listed in the following table.
operations
notes
6100
Stevenson,
a. Draw the precedence diagram.
W. J..21).pdf
b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?
c. Suppose it is now the end of the seventh day and that activities A and B have been completed,
while activity D is 50 percent completed. Time estimates for the completion of activity D are 5,
6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the proj-
ect by day 24 and the probability of finishing by day 21.
nd impre
o you w
CExtra
Screen Shot
20228 PM
DOCK
G
resume 2021
TIME IN DAYS
Vaccine and
other info
Immediate
Activity
Predecessor
Optimistic
Most Likely
Pessimistic
Screen Shot
2022-06 PM
A
5
6
7
росх
DOCX
B
8
8.
11
Resume
A
8
11
2/21/22
12
15
Password
E
F
D
6
7
Screen Shot
G
2
3
7
2022-41 PM
XLSX
H
B
4
4
Hw operation o Job
4.xisx
7
8.
Searc...notes
End
E, G, I
d. The partners have decided that shortening the project by two days would be beneficial, as long
as it doesn't cost more than about $20,000. They have estimated the daily crashing costs for each
activity in thousands, as shown in the following table. Which activities should be crashed, and
what further analysis would they probably want to do?
Screen Shot
2022 21 PM
Activity
First Crash
Second Crash
$8
$10
Screen Shot Screen Shot Screen Shot
1 20229 PM 2022-.5 PM 20228 PM
D
10
11
10
F
CALL-DUTY
MW2
G
9
10
H.
7
8
6
8
"Belk Collége
Undergraduate Career
Screen Shot. Screen Shot Call of Duty
2022-.19 PM 2022-..6 PM 2022-.0 PM/20227 PM 2022-..3 PM Mode.rfare 2
Group
Weight
Resources
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Step 1 Introduction
VIEWStep 2 Calculating Te(duration of each activity)
VIEWStep 3 Network diagram
VIEWStep 4 Standard deviation and variance
VIEWStep 5 Critical path
VIEWStep 6 Probability
VIEWStep 7 Durations of activity D changes
VIEWStep 8 Probability with changed duration of activity D
VIEWStep 9 Answers
VIEWStep 10 (NOTE)
VIEWTrending now
This is a popular solution!
Step by step
Solved in 10 steps with 10 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.