c. How many weeks will it take to complete the project? Number of weeks 33 d. How much slack does activity B have? Slack of activity B 7 weeks

Principles of Management
OER 2019th Edition
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax
Chapter17: Organizational Planning And Controlling
Section: Chapter Questions
Problem 2CTQ: China effectively shuts down for two weeks each year and celebrates the lunar new year. How does...
icon
Related questions
Question
es
The following activities are part of a project to be scheduled using CPM:
TIME (WEEKS)
6
ACTIVITY
A
BUDEFG
с
IMMEDIATE PREDECESSOR
-
OA-C-D-F-G
OA-C-D-E-G
O A-B-E-G
A
A
C
B, D
D
E, F
b. What is the critical path?
372437
Transcribed Image Text:es The following activities are part of a project to be scheduled using CPM: TIME (WEEKS) 6 ACTIVITY A BUDEFG с IMMEDIATE PREDECESSOR - OA-C-D-F-G OA-C-D-E-G O A-B-E-G A A C B, D D E, F b. What is the critical path? 372437
es
c. How many weeks will it take to complete the project?
Number of weeks
33
d. How much slack does activity B have?
Slack of activity B
7 weeks
Transcribed Image Text:es c. How many weeks will it take to complete the project? Number of weeks 33 d. How much slack does activity B have? Slack of activity B 7 weeks
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Recommended textbooks for you
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,