a. Draw a network diagram (activity on node), compute the earliest start and finish times of each task using most likely values. b. Compute the latest start and finish times of each task fill the rest of the values in a table format as follows: Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack Is critical? c. If the project is finished within 27 weeks of its start, the project manager will receive a bonus of 500$. Find the probability of getting the bonus.
a. Draw a network diagram (activity on node), compute the earliest start and finish times of each task using most likely values. b. Compute the latest start and finish times of each task fill the rest of the values in a table format as follows: Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack Is critical? c. If the project is finished within 27 weeks of its start, the project manager will receive a bonus of 500$. Find the probability of getting the bonus.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:Activity
A
D
E
H
F
G
B
I
J
4. A construction company planned for a new project and represented the tasks of the project as a
list of immediate predecessors, estimated duration (best, most likely, worst) as follows:
Estimated duration (best-most likely-worst) in weeks
K
с
M
N
O
End
immediate
predecessors
a.
A
D
E
A
FL
B
I
J
C
M
N
H,G,K,O
2-4-6
6-8-10
7-9-12
2-3-5
3-4-8
Earliest
Start
5-7-9
2-2-3
2-3-6
3-4-5
4-5-8
5-8-12
1-1-1
Draw a network diagram (activity on node), compute the earliest start and finish times of each
task using most likely values.
b. Compute the latest start and finish times of each task fill the rest of the values in a table
format as follows:
Activity
6-7-11
8-9-13
Earliest
Finish
Latest
Start
Latest
Finish
Slack
Is critical?
c. If the project is finished within 27 weeks of its start, the project manager will receive a bonus
of 500$. Find the probability of getting the bonus.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 8 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.