a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): Expected Time >) The expected completion time of the critical path = weeks (round your response to two decimal places). The expected completion time of the path other than the critical path = weeks (round your response to two decimal places). :) The variance of the critical path = The variance of the path other than the critical path = weeks (round your response to two decimal places). Activity AB А с D weeks (round your response to two decimal places). Variance
Question content area
Part 1
The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent.
|
Time (weeks) |
|
|
|
|
|
Immediate |
|
Time (weeks) |
|
|
|
|
|
Immediate |
Activity |
a |
|
m |
|
b |
|
Predecessor(s) |
Activity |
a |
|
m |
|
b |
|
Predecessor(s) |
A |
8 |
|
10 |
|
13 |
|
— |
C |
8 |
|
10 |
|
11 |
|
A |
B |
5 |
|
10 |
|
16 |
|
— |
D |
4 |
|
8 |
|
14 |
|
B |
This exercise contains only parts a, b, c, d, and e.
Part 2
a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):
|
|
|
|
|
|
|
|
Part 3
|
|
|
|
Part 4
|
|
|
|
Part 5
|
|
|
|
Part 6
b) The expected completion time of the critical path =
enter your response here
weeks (round your response to two decimal places).
Part 7
The expected completion time of the path other than the critical path =
enter your response here
weeks (round your response to two decimal places).
Part 8
c) The variance of the critical path =
enter your response here
weeks (round your response to two decimal places).
Part 9
The variance of the path other than the critical path =
enter your response here
weeks (round your response to two decimal places).
Part 10
d) If the time to complete the activities on the critical path is
21 weeks or less =
enter your response here
(enter as a probability and round your response to two decimal places).
Part 11
e) If the time to complete the activities on the non critical path is normally distributed, then the probability that the non critical path will be finished in
21 weeks or less =
enter your response here
(enter as a probability and round your response to two decimal places).