1. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. 1 2 3 4 5 6 7 8 9 10 Activity Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and document Install Time (Weeks) 2 3 3 7 6 1 5 4 8 2 Immediate Predecessors - 1 2 2 2 3,4 4,5 6,7 7 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. C. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
1. A project has been defined to contain the following list of activities along with their required times for
completion.
Activity No.
1
2
3
4
5
6
7
8
9
10
Activity
Collect requirements
Analyze processes
Analyze data
Design processes
Design data
Design screens
Design reports
Program
Test and document
Install
Time (Weeks)
2
3
3
7
6
1
5
4
8
2
Immediate Predecessors
1
2
2
2
3,4
4,5
6,7
7
8,9
a. Draw a network diagram for the activities.
b. Calculate the earliest expected completion time.
C.
Show the critical path.
d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
2. Construct a Gantt chart for the project defined in Problem 1.
Transcribed Image Text:1. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. 1 2 3 4 5 6 7 8 9 10 Activity Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and document Install Time (Weeks) 2 3 3 7 6 1 5 4 8 2 Immediate Predecessors 1 2 2 2 3,4 4,5 6,7 7 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. C. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.