. Identify the critical path. . Develop the activity schedule for the project. If your answer is zero, enter "0".

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin:

 

Need answers and explanation. Thanks, appreciate it! :)

Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games,
expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin:
Immediate
Time
Activity
Description
Predecessor
(weeks)
A
Survey building site
4
B
Develop initial design
6
Obtain board approval
А, В
11
D
Select architect
9.
E
Establish budget
Finalize design
D
7
G
Obtain financing
D, E
Hire contractor
F, G
10
a. Which project network is correct?
A
D
F
A
Start
H
Finish
Start
H
Finish
B
G
B
(iii)
(iv)
A
F
A
D
F
Start
H
Finish
Start
H
Finish
B
E
G
B
E
G
b. Identify the critical path.
c. Develop the activity schedule for the project. If your answer is zero, enter "0".
Earliest
Latest
Earliest
Latest
Critical
Activity
Start
Start
Finish
Finish
Slack
Activity
A
B
D
E
F
H
d. Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is
the expected completion time for the project?
Project Completion Time is
weeks.
Transcribed Image Text:Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin: Immediate Time Activity Description Predecessor (weeks) A Survey building site 4 B Develop initial design 6 Obtain board approval А, В 11 D Select architect 9. E Establish budget Finalize design D 7 G Obtain financing D, E Hire contractor F, G 10 a. Which project network is correct? A D F A Start H Finish Start H Finish B G B (iii) (iv) A F A D F Start H Finish Start H Finish B E G B E G b. Identify the critical path. c. Develop the activity schedule for the project. If your answer is zero, enter "0". Earliest Latest Earliest Latest Critical Activity Start Start Finish Finish Slack Activity A B D E F H d. Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project? Project Completion Time is weeks.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.