Chapter 06-01: Production Master Data
PREREQUISITES
1.
You should be familiar with navigation in SAP HANA
2.
Completed Exercises Chs. 02-01 through 05-02
MOTIVATION
In this exercise, you will do the following for Production Master Data:
1.
Create Materials
2.
View Inventory Balance
3.
View Material Inventory
4.
Display Requirements List
5.
Create Bills of Materials
6.
Create Product Routings
7.
Create Initial Inventory Balances PRODUCT
SAP S/4 HANA 1709
REVISED
04/06/2020
FOCUS
Production
Master Data
AUTHORS
Simha R. Magal
Jeff Word
VERSION
1.3 MCC
TESTED
Date: 04/06/2020
System: MGL
ACKNOWLEDGEMENT
These are the GBI exercises developed by Simha R. Magal and Jeff Word. These exercises include concepts discussed in the book,
Integrated Business Processes with ERP Systems
(Epistemy Press, 2012).
© 2020 Epistemy Press, LLC.
Screenshots © 2020, SAP SE
Chapter 06: Production Master Data
Page 2 of 45
© 2020 Epistemy Press, LLC.
Part 1 - Table of Contents
Table of Contents
Section 1.1: Create Materials
......................................................................................................................
3
Section 1.2: View Inventory Balance
...........................................................................................................
9
Section 1.3: View Material Inventory
........................................................................................................
10
Section 1.4: Display Requirements List
......................................................................................................
11
Section 1.5: Create Bills of Materials
.........................................................................................................
13
Section 1.6: Create Product Routings
........................................................................................................
16
Section 1.7: Create Production Versions
...................................................................................................
19
Section 1.8: Create Initial Inventory Balance
.............................................................................................
23
Chapter 06: Production Master Data
Page 3 of 45
© 2020 Epistemy Press, LLC.
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
In this section, you will be creating your own version of all the below raw materials, semi-finished goods,
and finished goods necessary for the production process within the material master. The following table consists of five columns: the original material description, the original material number, your material number, the material type, and your storage location where it is.
Description
Number
Your Number
Type
Your S.L.
Raw Materials
Brake Kit
BRKT1000
BRKT10##
Raw
RM##
Chain
CHAN1000
CHAN10##
Raw
RM##
Derailleur Gear Assembly
DGAM1000
DGAM10##
Raw
RM##
Hex Nut 5 mm
HXNT1000
HXNT10##
Raw
RM##
Lock Washer 5 mm
LWSH1000
LWSH10##
Raw
RM##
Packaging
PCKG1000
PCKG10##
Raw
RM##
Pedal Assembly
PEDL1000
PEDL10##
Raw
RM##
Socket Head Bolt 5x20mm
BOLT1000
BOLT10##
Raw
RM##
Touring Aluminum Wheel
TRWH1000
TRWH10##
Raw
RM##
Chapter 06: Production Master Data
Page 4 of 45
© 2020 Epistemy Press, LLC.
Section 1.1: Create Materials
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Touring Frame-Red
TRFR3000
TRFR30##
Raw
RM##
Touring Handle Bar
TRHB1000
TRHB10##
Raw
RM##
Touring Seat Kit
TRSK1000
TRSK10##
Raw
RM##
Touring Tire
TRTR1000
TRTR10##
Raw
RM##
Touring Tube
TRTB1000
TRTB10##
Raw
RM##
Warranty Document
WDOC1000
WDOC10##
Raw
RM##
Semi-Finished Materials
Touring Aluminum Wheel Assembly
TRWA1000
TRWA10##
Semi.
SF##
Finished Materials
Deluxe Touring Bike (red)
DXTR3000
DXTR30##
Fin.
FG##
Chapter 06: Production Master Data
Page 5 of 45
© 2020 Epistemy Press, LLC.
Raw Materials
Step: 1.1.1: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Materials Management
Material Master
Material
Create (General)
Immediately
1: What is the Transaction Code to create a general material immediately?
MM01
2: What is the Transaction Code to change a material immediately?
MM02
3: What is the Transaction Code to display a current material?
MM03
Step: 1.1.2: In the “Create Material (Initial Screen)”
screen, enter the following information:
Attribute
Description
Data Value
Material
Key uniquely identifying the material
Your Brake Kit
Industry Sector
Specifies the branch of industry to which the material is assigned
Mechanical Engineering
Material Type
Assigns the material to a group of materials Raw Materials
Copy from…Material
Data you want the system to copy as default values
Original Brake Kit
Step: 1.1.3: Click Continue
.
Step: 1.1.4: In the “Select View(s)”
pop-up, click Deselect All
.
Chapter 06: Production Master Data
Page 6 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.5: Highlight the “Basic Data 1”
row.
Step: 1.1.6: Highlight the “Purchasing”
row.
Step: 1.1.7: Highlight the “MRP 1”
row.
Step: 1.1.8: Highlight the “General Plant Data / Storage 1”
row.
Step: 1.1.9: Highlight the “Accounting 1”
row.
Step: 1.1.10: Highlight the “Costing 1”
row.
Step: 1.1.11: Click Save as Default Values .
Step: 1.1.12: Click Org. Levels .
Chapter 06: Production Master Data
Page 7 of 45
© 2020 Epistemy Press, LLC.
Step: 1.1.13: In the “Organizational Levels”
pop-up, enter the following information:
Attribute
Description
Data Value
Plant
Key uniquely identifying a plant
Your Dallas Plant
Stor. Location
Location where materials are stored
Your Raw Materials
Copy from Plant
Plant of reference Original Dallas Plant
Copy from Stor. Location
Storage location of reference
Original Raw Materials
Step: 1.1.14: Click Save As Default Values and then click continue(Enter) You will receive a message that says, “The material already exists and will extend”.
Step: 1.1.15: In the “Create Material BRKT10## (Raw materials)”
screen, enter the following information:
Attribute
Description
Data Value
Material Description
Describes the material in more detail
## Brake Kit
Purchasing Group
A buyer or group of buyers
Your GBI Buyer
Step: 1.1.16: Press Enter, until the “Last data screen reached”
pop-up opens, click Yes You will receive a message that says “Material BRKT10## created”.
Step: 1.1.17: Refer to the beginning of this section and create the rest of your RAW materials.
Chapter 06: Production Master Data
Page 8 of 45
© 2020 Epistemy Press, LLC.
Semi-Finished Goods
Step: 1.1.18: In the “Create Material (Initial Screen)”
screen, enter the following information:
Attribute
Description
Data Value
Material
Key uniquely identifying the material
TRWA10##
Industry Sector
Branch of industry to which the material is assigned.
Mechanical Engineering
Material Type
Assigns the material to a group of materials Semi-finished Product
Copy from…
Material
Material whose data you want the system to copy as default values
Original Touring Aluminum Wheel Assembly
Step: 1.1.19: Click Continue .
Step: 1.1.20: In the “Select View(s)”
pop-up, click Deselect All .
Step: 1.1.21: Highlight “Basic Data 1”
Step: 1.1.22: Highlight “Purchasing”
Step: 1.1.23: Highlight “MRP 1”
Step: 1.1.24: Highlight “Work Scheduling”
Step: 1.1.25: Highlight “General Plant Data/Storage 1”
Step: 1.1.26: Highlight “Accounting 1”
Step: 1.1.27: Highlight “Costing 1”
Step: 1.1.28: Click Save As Default Values .
Chapter 06: Production Master Data
Page 9 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.29: Click Org. Levels .
Step: 1.1.30: In the “Organizational Levels”
pop-up, enter the following information:
Attribute
Description
Data Value
Plant
Key uniquely identifying a plant
Your Dallas Plant
Stor. Location
Location at which materials are stored Your Semi-Fin. Goods
Copy from Plant
Plant of reference Original Dallas Plant
Copy from Stor. Location
Storage location of reference material
Original Semi-Fin. Goods
Step: 1.1.31: Click Save As Default Values and then click continue(Enter) .
You will receive a message that says, “The materials already exists and will be extended”.
Step: 1.1.32: In the “Create Material TRWA10## (Semi-Finished Product)”
screen, enter the following information:
Attribute
Description
Data Value
Material Description
Describes the material in more detail
## Touring Aluminum Wheel Assembly
MRP Type
Determines whether and how the material is planned.
MRP
Step: 1.1.33: Press Enter, until the “Last data screen reached”
pop-up opens, click on the
icon. You will receive a message that says “Material TRWA10## created”.
Chapter 06: Production Master Data
Page 10 of 45
© 2020 Epistemy Press, LLC.
Finished Goods
Step: 1.1.34: In the “Create Material (Initial Screen)”
screen, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
DXTR30##
Industry Sector
Specifies the branch of industry to which the material
is assigned.
Mechanical Engineering Material Type
Assigns the material to a group of materials Finished Product
Copy from…
Material
Material whose data you want the system to copy as default values
Original Deluxe Touring Bike (red)
Step: 1.1.35: Click Continue .
Step: 1.1.36: In the “Select View(s)”
pop-up, click Deselect All .
Step: 1.1.37: Highlight “Basic Data 1”
Step: 1.1.38: Highlight “MRP 1”
Step: 1.1.39: Highlight “Work Scheduling”
Step: 1.1.40: Highlight “General Plant Data/Storage 1”
Step: 1.1.41: Highlight “Accounting 1”
Step: 1.1.42: Highlight “Costing 1”
Step: 1.1.43: Click Save As Default Values .
Step: 1.1.44: In the “Select View(s)”
pop-up, click Org. Levels .
Chapter 06: Production Master Data
Page 11 of 45
© 2020 Epistemy Press, LLC.
Step: 1.1.45: In the “Organizational Levels”
pop-up, enter the following information:
Attribute
Description
Data Value
Plant
Key uniquely identifying a plant
Your Dallas Plant
Stor. Location
Location at which materials are stored Your Finished Goods
Copy from Plant
Plant of reference Original Dallas Plant
Copy from Stor. Location
Storage location of reference material
Original Finished Goods
Step: 1.1.46: Click Save As Default Values and then click continue(Enter) .
You will receive a message that says, “The material already exists and will be extended”.
Step: 1.1.47: In the “Create Material DXTR30## (Finished Product)”
screen, enter the following information:
Attribute
Description
Data Value
Material Description
Describes the material in more detail.
## Deluxe Touring Bike (red)
MRP Type
Determines whether and how the material is planned
MRP
Step: 1.1.48: Press Enter, until the “Last data screen reached”
pop-up opens, click .
You will receive a message that says “Material DXTR30## created”.
Chapter 06: Production Master Data
Page 12 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
In this section, you look at the inventory balance of a raw material located within Dallas.
Step: 1.1.49: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Materials Management
Physical Inventory
Environment
Stock Overview
4: What is the Transaction Code to display a material’s inventory level?
MMBE
Step: 1.1.50: In the “Stock Overview: Company Code/Plant/Storage Location/Batch.”
screen, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
Your Touring Frame-Red
Plant
Key uniquely identifying a plant
Your Dallas Plant
Chapter 06: Production Master Data
Page 13 of 45
© 2020 Epistemy Press, LLC.
Section 1.2: View Inventory Balance
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Storage Location
Location at which the material is stored
Your Raw Materials
Click Execute .
5: How many Touring Frames-Red are in unrestricted use?
0.000
6: How many Touring Frames-Red are in reserved stock?
0.000
7: How many Touring Frames-Red are in on-order stock?
0.000
Chapter 06: Production Master Data
Page 14 of 45
© 2020 Epistemy Press, LLC.
In this section, you view your material inventory of all your materials maintained in Dallas.
Step: 1.1.51: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Materials Management
Inventory Management
Environment
Stock
Warehouse Stock
8: What is the Transaction Code to display a material’s inventory level?
MB52
Step: 1.1.52: In the “Display Warehouse Stock of Material”
screen, enter the following information:
Attribute
Description
Data Value
Material
Key uniquely identifying the material
*0##
Plant
Key uniquely identifying a plant
DL##
Storage Location
Location at which the material is stored
*##
Chapter 06: Production Master Data
Page 15 of 45
© 2020 Epistemy Press, LLC.
Section 1.3: View Material Inventory
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
9: What is the code for Your Raw Material Storage Location?
RM23
10: What is the code for Your Semi-Finished Goods Storage Location?
SF23
11: What is the code for Your Finished Goods Storage Location?
FG23
Step: 1.1.53: Click Execute .
12: What is the total United States dollar value of Raw Materials in your inventory?
0.00
13: How many of Your Gear Assemblies are there in inventory?
0
14: What is the material code for Your Warranty Document?
WDOC1023
Chapter 06: Production Master Data
Page 16 of 45
© 2020 Epistemy Press, LLC.
In this section, you look at the stock/requirements list for the touring aluminum wheel assembly.
Step: 1.1.54: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Materials Management
Inventory Management
Environment
Stock
Stock/Requirements List
15: What is the Transaction Code to display a stock/requirements list?
MD04
Step: 1.1.55: In the “Stock/Requirements List: Initial Screen”
screen, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
Your Touring Aluminum Wheel Assembly
MRP Area
Number of the MRP area for which material requirements planning should Your Dallas Plant Chapter 06: Production Master Data
Page 17 of 45
© 2020 Epistemy Press, LLC.
Section 1.4: Display Requirements List
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
be carried out separately.
Plant
Key uniquely identifying a plant
Your Dallas Plant
Step: 1.1.56: Click Continue .
16: What is the material type of the Touring Wheel Assembly?
Semifinished Product
17: What is the code for the Trading Goods material type?
HAWA
“Trading Goods”, NOT “Trading Goods (Planned)”
18: What is the code for the Raw Materials material type?
ROH
19: What is the code for the Finished Product material type?
FERT
In this section, you create a BOM for your wheel assembly and then create a BOM for your bike.
Chapter 06: Production Master Data
Page 18 of 45
© 2020 Epistemy Press, LLC.
Section 1.5: Create Bills of Materials
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.57: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Production
Master Data
Bills of Material
Bill of Material
Material BOM
Create
20: What is the Transaction Code to create a bill of materials?
CS01
21: What is the Transaction Code to display a bill of materials?
CS02
22: What is the Transaction Code to change a bill of materials?
CS03
Semi-Finished Goods
Step: 1.1.58: In the “Create material BOM: Initial Screen”
screen, enter the following information:
Attribute
Description
Data Value
Material
Key uniquely identifying the material
Your Touring Aluminum Wheel Assembly
Plant
Key uniquely identifying a plant
Your Dallas Plant
BOM Usage
Defines an area where a BOM can be used
Production
Step: 1.1.59: Click Copy .
Step: 1.1.60: In the “Copy From…”
pop-up, enter the following information:
Chapter 06: Production Master Data
Page 19 of 45
© 2020 Epistemy Press, LLC.
Attribute
Description
Data Value
Material Key uniquely identifying the material
Original Touring Aluminum Wheel Assembly
Plant
Key uniquely identifying a plant
Original Dallas Plant Step: 1.1.61: Click Continue (Enter) .
Step: 1.1.62: In the “Create material BOM: Copy From”
screen, click Select All .
Step: 1.1.63: Click Copy .
Step: 1.1.64: In the “Create material BOM: Item: General Data”
screen, enter the following information:
Attribute
Description
Data Value
0010
The first component
Your Touring Tire 0020
The second component
Your Touring Tube 0030
The third component
Your Touring Aluminum Wheel 0040
The fourth component
Your Hex Nut 5 mm 0050
The fifth component
Your Lock Washer 5 mm 0060
The sixth component
Your Socket Head Bolt 5x20mm Step: 1.1.65: Press Enter.
Chapter 06: Production Master Data
Page 20 of 45
© 2020 Epistemy Press, LLC.
23: How many components make up the Touring Wheel Assembly?
6
24: What is the material code for Your Touring Tube?
TRTB1023
25: What is the item category for all the components?
Stock Item
26: How many lock washers are needed in a Touring Wheel Assembly?
2
27: What is the item number for The Hex Nut?
0040
Step: 1.1.66: Click Save .
You will receive a message that says “Creating BOM for material”.
Finished Good
Step: 1.1.67: In the “Create material BOM: Initial Screen”
screen, enter the following information:
Attribute
Description
Data Value
Material
Key uniquely identifying the material
Your Deluxe Touring Bike (red)
Plant
Key uniquely identifying a plant
Your Dallas Plant
Usage
Defines an area where a BOM can be used
Production
Step: 1.1.68: Click Copy .
Chapter 06: Production Master Data
Page 21 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.69: In the “Copy From…”
pop-up, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
Original Deluxe Touring Bike (red)
Plant
Key uniquely identifying a plant
Original Dallas Plant
Step: 1.1.70: Click Continue (Enter) .
Step: 1.1.71: In the “Create material BOM: Copy From”
screen, click Select All .
Step: 1.1.72: Click Copy .
In the “Create material BOM: General Item Overview”
screen, enter the following information:
Attribute
Description
Data Value
0010
The first component
Your Touring Aluminum Wheel Assembly 0020
The second component
Your Touring Frame-Red 0030
The third component
Your Derailleur Gear Assembly 0040
The fourth component
Your Touring Seat Kit 0050
The fifth component
Your Touring Handle Bar 0060
The sixth component
Your Pedal Assembly 0070
The seventh component
Your Chain 0080
The eighth component
Your Brake Kit 0090
The ninth component
Your Warranty Document 0100
The tenth component
Your Packaging Chapter 06: Production Master Data
Page 22 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Change the component (Data Value) using their unique identifier ##.
Step: 1.1.73: Press Enter.
Step: 1.1.74: Click Save .
You will receive a message that says “Creating BOM for material”.
Chapter 06: Production Master Data
Page 23 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
In this section, you copy the product routings for your wheel assembly and your touring bike.
Step: 1.1.75: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Production
Master Data
Routings
Routings
Standard Routings
Create
28: What is the Transaction Code to create routings?
CA01
29: What is the Transaction Code to change routings?
CA02
30: What is the Transaction Code to display routings?
CA03
Semi-Finished Good
Chapter 06: Production Master Data
Page 24 of 45
© 2020 Epistemy Press, LLC.
Section 1.6: Create Product Routings
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.76: In the “Create Routing: Initial Screen”
screen, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
Your Touring Aluminum Wheel Assembly
Plant
Key uniquely identifying a plant
Your Dallas Plant
Group
Key identifying a group.
CLEAR OUT (Make sure nothing is in this field)
Ensure the Group Field is Cleared Out
Step: 1.1.77: Click Copy From .
Step: 1.1.78: In the “Select Type”
pop-up, select Routing. Step: 1.1.79: Click Continue (Enter) .
Chapter 06: Production Master Data
Page 25 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.80: In the “Create Using Copy Function: Select Object to be Copied”
pop-up, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
Original Touring Aluminum Wheel Assembly
Plant
Key uniquely identifying a plant
Original Dallas Plant
Step: 1.1.81: Click Continue (Enter) .
Step: 1.1.82: In the “Create Routing: Header Data Check”
screen, enter the following information:
Attribute
Description
Data Value
Description
Routing description
## Touring Aluminum Wheel Assembly
Overall Status Indicates the processing status of a task list
Released (general)
Step: 1.1.83: Press Enter.
Step: 1.1.84: In the “Create Routing: Operation – Check”
screen, Press Enter to dismiss the “Enter Standard Value Setup”
warning message
Step: 1.1.85: Press Enter to dismiss the “Activity type LABOR is not set up for cost center NA## NAPR10## in the current year”
warning message
Step: 1.1.86: Press Enter to dismiss the “
Activity type LABOR is not set up for cost center NA## NAPR10## in the current year”
warning message
Chapter 06: Production Master Data
Page 26 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.87: Continue to Press Enter though the warning messages until you reach the “Create Routing: Operation Overview”
screen.
Step: 1.1.88: In the “Create Routing: Operation Overview”
screen click Save .
You will receive a message that says, “Routing was saved with group”.
Finished Good
Step: 1.1.89: In the “Create Routing: Initial Screen”
screen, enter the following information:
Attribute
Description
Data Value
Material Key uniquely identifying the material
Your Deluxe Touring Bike (red)
Plant
Key uniquely identifying a plant
Your Dallas Plant
Group
Key identifying a group.
CLEAR OUT (Make sure nothing is in this field)
Ensure that the Group Field is cleared out.
Step: 1.1.90: Click Copy From .
Step: 1.1.91: In the “Select Type”
pop-up, select Routing. Step: 1.1.92: Click Continue (Enter)
.
Step: 1.1.93: In the “Create Using Copy Function: Select Object to be Copied”
pop-up, enter the following information:
Chapter 06: Production Master Data
Page 27 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Attribute
Description
Data Value
Material Key uniquely identifying the material
Original Deluxe Touring Bike (red)
Plant
Key uniquely identifying a plant
Original Dallas Plant
Step: 1.1.94: Click Continue (Enter) .
Step: 1.1.95: In the “Create Routing: Header Data Check”
screen, enter the following information:
Attribute
Description
Data Value
Overall Status Indicates the processing status of a task list
Released (general)
Step: 1.1.96: Press Enter.
Step: 1.1.97: In the “Create Routing: Operation – Check”
screen, Press Enter to dismiss the “Enter Standard Value Setup”
warning message
You will receive this message every time you press enter for every material in the BOM.
Step: 1.1.98: Press Enter to dismiss the “Activity type LABOR is not set up for cost center NA## NAPR10## in the current year”
warning message
Step: 1.1.99: Press Enter to dismiss the “Activity type LABOR is not set up for cost center NA## NAPR10## in the current year”
warning message
Step: 1.1.100: Continue to Press Enter though the warning messages until you reach the “Create Routing: Operation Overview”
screen.
Chapter 06: Production Master Data
Page 28 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.101: In the “Create Routing: Operation Overview”
screen, click Save .
You will receive a message that says, “Routing was saved with group”.
31: What is the importance of routings?
give the steps/process on how to produce goods and a defined sequence of activities performed at the work center. calculates production cost, machine time, labor.
Chapter 06: Production Master Data
Page 29 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
In this section, you will create Production Versions for your Touring Wheel Assembly (TRWA10##) and your Deluxe Touring Bike (red) (DXTR30##). Manufacturing BOM determination is only possible with the creation of Production Version master data. You will need to reference your material’s routing to find the group and group counter values.
Step: 1.1.102: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Production
Master Data
Routings
Routings
Standard Routings
Display
Step: 1.1.103: In the “Display Routing: Initial Screen”
screen, enter the following information:
Attribute
Description
Data Value
Material
Key identifying your material
Your Touring Wheel Assembly Plant
Key uniquely identifying a plant.
Your Dallas Plant
Group
Groups together several task lists.
CLEARED OUT
Step: 1.1.104: Click Continue .
Step: 1.1.105: In the “Display Routing: Operation Overview”
screen, select Header Data .
Chapter 06: Production Master Data
Page 30 of 45
© 2020 Epistemy Press, LLC.
Section 1.7: Create Production Versions
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
32: What is your Touring Wheel Assembly group? TRWH1023
33: What is your Touring Wheel Assembly group counter? TRWH1023
Step: 1.1.106: In the “Display Routing: Header Details” screen, click back two times.
Step: 1.1.107: In the “Display Routing: Initial Screen” enter the following information:
Attribute
Description
Data Value
Material
Key identifying your material
Your Deluxe Touring Bike (red)
Plant
Key uniquely identifying a plant.
Your Dallas Plant
Group
Groups together several task lists
CLEARED OUT
Step: 1.1.108: Click Continue .
Step: 1.1.109: In the “Display Routing: Operation Overview”
screen, select Header Data .
34: What is your Deluxe Touring Bike (red) group?
DXTR3023
35: What is your Deluxe Touring Bike (red) group counter? DXTR3023
Step: 1.1.110: In the “SAP Easy Access”
screen
, follow the navigation path below:
Navigation
SAP Easy Access Menu
Logistics
Production
Master Data
Production Versions 36: What is the transaction code to create a production version? C223
Step: 1.1.111: In the “Production Version: Mass Processing” screen, enter the following information:
Attribute
Description
Data Value
Chapter 06: Production Master Data
Page 31 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Plant
Key uniquely identifying a plant.
Your Plant Dallas
Material
Key identifying your material
Your Touring Wheel Assembly
Step: 1.1.112: Click Continue .
Step: 1.1.113: In the “Production Version: Mass Processing” screen, in the “
Production Versions”
section
of the screen enter the following information:
Attribute
Description
Data Value
Material
Key identifying your material
Your Touring Wheel Assembly
Production Version
Key identifying your production version
01
Production Version Text
Text describing your Production Version
Touring Wheel Assembly PV
BOM Usage
Key defining the area (such as engineering/design or production) where a BOM can be used
1 Group
Key for task list group found in material routing
Your Touring Wheel Assembly routing group
Group Counter
Helps uniquely identify the task list for the production version of a material
Your Touring Wheel Assembly Group Counter
Type
Key which classifies task lists according to their functionality
Routing
Step: 1.1.114: Click Continue Step: 1.1.115: You will receive a warning message “valid from date is set to current date and valid to date will be set to maximum”
Click Continue .
Step: 1.1.116: Click Continue through the warning message “Check default alternative BOM”
Step: 1.1.117: Click Save .
Chapter 06: Production Master Data
Page 32 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
You will not receive a confirmation message; however, you will now be able to perform the production process for your Touring Wheel Assembly.
Step: 1.1.118: In the “Production Version: Mass Processing” screen, enter the following information:
Attribute
Description
Data Value
Plant
Key uniquely identifying a plant.
Your Plant Dallas
Material
Key identifying your material
Your Deluxe Touring Bike (red)
MRP Controller
MRP Controller responsible for material planning for the material.
Your DL Controller
Step: 1.1.119: Click Continue .
Step: 1.1.120: In the “Production Version: Mass Processing” screen in the “
Production Version”
section of the screen enter the following information:
Attribute
Description
Data Value
Material
Key identifying your material
Your Deluxe Touring Bike (red)
Production Version
Key identifying your production version
01
Production Version Short Text
Text describing your Production Version
Deluxe Touring Bike (red) PV
BOM Usage
Key defining the area (such as engineering/design or production) where a BOM can be used
1 Group
Key for task list group found in material routing
Your Deluxe Touring Bike (red) routing group
Group Counter
Helps uniquely identify the task list for the production
version of a material
Your Deluxe Touring Bike Red group counter
Type
Key which classifies task lists according to their functionality
Routing
Chapter 06: Production Master Data
Page 33 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.121: Click Continue Step: 1.1.122: You will receive a warning message “valid from date is set to current date and valid to date will be set to maximum”
click Continue .
Step: 1.1.123: Click Continue through the warning message “Check default alternative BOM”
.
Step: 1.1.124: Click Save .
You will not receive a confirmation message; however, you will now be able to perform the production process for your Deluxe Touring Bike (red).
Chapter 06: Production Master Data
Page 34 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Normally, the material planning process would create purchase requisitions for the necessary raw materials. You would then execute the procurement process and obtain these materials. For this exercise (and simplicity reasons), we will take a shortcut and create “inventory from heaven”.
Use the table below to calculate how many of the different materials are needed to make ten bikes. The first three columns include the material description, material number, and the quantity needed for one bike. Complete the remaining columns as follows:
Item
Description
Number
Quantity for 1 Bike
Qty. Needed for 10 Bikes
1
Brake Kit
BRKT10##
1
2
Chain
CHAN10##
1
3
Derailleur Gear Assembly
DGAM10##
1
4
Hex Nut 5 mm
HXNT10##
2
5
Lock Washer 5 mm
LWSH10##
4
6
Packaging
PCKG10##
1
7
Pedal Assembly
PEDL10##
1
Chapter 06: Production Master Data
Page 35 of 45
© 2020 Epistemy Press, LLC.
Section 1.8: Create Initial Inventory Balance
Create Materials
(I)
View Inventory Balance
(II)
View Material Inventory
(III)
Display Requirements List
(IV)
Create Bills of Materials
(V)
Create Product Routings
(VI)
Create Initial Inventory Balances
(VII)
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8
Socket Head Bolt 5x20mm
BOLT10##
2
9
Touring Aluminum Wheel
TRWH10##
2
10
Touring Frame-Red
TRFR30##
1
11
Touring Handlebar
TRHB10##
1
12
Touring Seat Kit
TRSK10##
1
13
Touring Tire
TRTR10##
2
14
Touring Tube
TRTB10##
2
15
Warranty Document
WDOC10##
1
Chapter 06: Production Master Data
Page 36 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.125: In the “SAP Easy Access”
screen, follow the navigation path below:
Navigation
SAP Menu
Logistics
Materials Management
Inventory Management
Goods Movement
Goods Movement
37: What is the T-code to create “inventory from heaven”?
MIGO
Step: 1.1.126: In the “Goods Receipt Purchase Order”
screen, enter the following information:
Attribute
Description
Data Value
Trans/Event
Drop-down menu
Goods Receipt
Reference Document
Indicates the document you want to reference when you enter the transaction
Other
Receipt w/o PO (Movement Type )
Specifies a key for the type of goods movement
561
Step: 1.1.127: Press Enter. Step: 1.1.128: In the “Tip” pop-up, click Continue (Enter) .
Chapter 06: Production Master Data
Page 37 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.129: In the “Goods Receipt Other”
screen, enter the following information:
Mat. Short Text
Quantity in UnE
E
SLoc
Plnt
BOLT10##
20
EA
Raw Materials Your Plant Dallas BRKT10##
10
EA
Raw Materials
Your Plant Dallas CHAN10##
10
EA
Raw Materials
Your Plant Dallas DGAM10##
10
EA
Raw Materials
Your Plant Dallas HXNT10##
20
EA
Raw Materials
Your Plant Dallas LWSH10##
40
EA
Raw Materials
Your Plant Dallas PCKG10##
10
EA
Raw Materials
Your Plant Dallas PEDL10##
10
EA
Raw Materials
Your Plant Dallas TRFR30##
10
EA
Raw Materials
Your Plant Dallas TRHB10##
10
EA
Raw Materials
Your Plant Dallas TRSK10##
10
EA
Raw Materials
Your Plant Dallas TRTB10##
20
EA
Raw Materials
Your Plant Dallas TRTR10##
20
EA
Raw Materials
Your Plant Dallas TRWH10##
20
EA
Raw Materials
Your Plant Dallas WDOC10##
10
EA
Raw Materials
Your Plant Dallas Step: 1.1.130: Press Enter.
Step: 1.1.131: Click Post . You will receive a message that says, “Material document 49………… posted”.
Chapter 06: Production Master Data
Page 38 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Step: 1.1.132: Refer to a previous step for instructions on how to view your material inventory. Make
sure you have the correct amount of inventory for each item.
38: How many of Your Touring Frames-Red are in inventory after the movement?
10
39: What is the total United States dollar value of Touring Frames-Red in inventory?
2,000.00
Chapter 06: Production Master Data
Page 39 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Part 2 - Exercise Deliverables
Name:
Jayda Hill
Course and Section:
TRA 4202
Identifier:
GBX-23
Client:
301
Chapter 06: Production Master Data
Page 40 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
1: What is the Transaction Code to create a general material immediately?
MM01
2: What is the Transaction Code to change a material immediately?
MM02
3: What is the Transaction Code to display a current material?
MM03
4: What is the Transaction Code to display a material’s inventory level?
MMBE
5: How many Touring Frames-Red are in unrestricted use?
0.000
6: How many Touring Frames-Red are in reserved stock?
0.000
7: How many Touring Frames-Red are in on-order stock?
0.000
8: What is the Transaction Code to display a material’s inventory level?
MB52
9: What is the code for Your Raw Material Storage Location?
RM23
10: What is the code for Your Semi-Finished Goods Storage Location?
SF23
11: What is the code for Your Finished Goods Storage Location?
FG23
12: What is the total United States dollar value of Raw Materials in your inventory?
0.00
13: How many of Your Gear Assemblies are there in inventory?
0
14: What is the material code for Your Warranty Document?
WDOC1023
Chapter 06: Production Master Data
Page 41 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
15: What is the Transaction Code to display a stock/requirements list?
MD04
16: What is the material type of the Touring Wheel Assembly?
Semifinished Product
17: What is the code for the Trading Goods material type?
HAWA
18: What is the code for the Raw materials material type?
ROH
19: What is the code for the Finished Product material type?
FERT
20: What is the Transaction Code to create a bill of materials?
CS01
21: What is the Transaction Code to display a bill of materials?
CS02
22: What is the Transaction Code to change a bill of materials?
CS03
23: How many components make up the Touring Wheel Assembly?
6
24: What is the material code for Your Touring Tube?
TRTB1023
25: What is the item category for all the components?
Stock Item
26: How many Lock Washers are needed in a Touring Wheel Assembly?
2
27: What is the item number for the Hex Nut?
0040
28: What is the Transaction Code to create routings?
CA01
29: What is the Transaction Code to change routings?
CA02
30: What is the Transaction Code to display routings?
CA03
Chapter 06: Production Master Data
Page 42 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
31: What is the importance of routings?
give the steps/process on how to produce goods and a defined sequence of activities performed at the work center. calculates production cost, machine time, labor.
32: What is your Touring Wheel Assembly group?
TRWH1023
33: What is your Touring Wheel Assembly group counter?
TRWH1023
34: What is your Deluxe Touring Bike (red) group?
DXTR3023
35: What is your Deluxe Touring Bike (red) group counter?
DXTR3023
36: What is the transaction code to create a production version?
C223
37: What is the Transaction Code to create inventory from heaven?
MIGO
38: How many of Your Touring Frames-Red are in inventory after the movement?
10
39: What is the total United States dollar value of Touring Frames-Red in inventory?
2,000.00
Chapter 06: Production Master Data
Page 43 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Description
Number
Your Number
Type
Your S.L.
Brake Kit
BRKT1000
BRKT10##
Raw
RM##
Chain
CHAN1000
CHAN10##
Raw
RM##
Derailleur Gear Assembly
DGAM1000
MM03 DGAM10##
Raw
RM##
Hex Nut 5 mm
HXNT1000
MMBE HXNT10##
Raw
RM##
Lock Washer 5 mm
LWSH1000
0.000 LWSH10##
Raw
RM##
Packaging
PCKG1000
PCKG10##
Raw
RM##
Pedal Assembly
PEDL1000
PEDL10##
Raw
RM##
Socket Head Bolt 5x20mm
BOLT1000
BOLT10##
Raw
RM##
Touring Aluminum Wheel
TRWH1000
TRWH10##
Raw
RM##
Touring Frame-Red
TRFR3000
TRFR30##
Raw
RM##
Touring Handle Bar
TRHB1000
TRHB10##
Raw
RM##
Touring Seat Kit
TRSK1000
TRSK10##
Raw
RM##
Touring Tire
TRTR1000
TRTR10##
Raw
RM##
Touring Tube
TRTB1000
TRTB10##
Raw
RM##
Warranty Document
WDOC1000
WDOC10##
Raw
RM##
Chapter 06: Production Master Data
Page 44 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Touring Aluminum Wheel Assembly
TRWA1000
TRWA10##
Semi.
SF##
Deluxe Touring Bike (red)
DXTR3000
DXTR30##
Fin.
FG##
Chapter 06: Production Master Data
Page 45 of 45
© 2020 Epistemy Press, LLC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Documents
Related Questions
4. Documents business requirements use-case narratives.for only one process
note: please i want Documents like this in pic
arrow_forward
Using signavio or any PBM tools and must Use pool and lane and object.
Model the following business process at a supplier. After a supplier notifies a retailer of the approval of a purchase order, the supplier can receive an order confirmation, an order change, or an order cancelation from the retailer. It may happen that no response is received at all. If no response is received after 48 h, or if an order cancelation is received, the supplier will cancel the order. If an order confirmation is received within 48 h, the supplier will process the order normally. If an order change is received within 48 h, the supplier will update the order and ask again the retailer for confirmation. The retailer is allowed to change an order at most three times. Afterwards, the supplier will automatically cancel the order.
arrow_forward
Can someone please help to solve all of the following problem showing all work and include a load chart. Thank you!
arrow_forward
+ → CO
A student.masteryconnect.com/?iv%3D_n5SY3Pv5S17e01Piby
Gr 8 Sci Bench 1 GradeCam Rutherford TN 2021
AHMAD, ASHNA
D0
3 of 35
A student develops a model of an electric motor using two pins, a wire coil,
coil continues to spin with a certain speed.
wire coil
pins
magnet
tape
battery
How can the student increase the speed of the electric motor?
O by using wider pins
O by using thinner pins
O by using less wire in the clil
O by using more wire in the coil
e Type here to search
近
arrow_forward
Identify the lines
arrow_forward
System Specification
Task 1 is to complete the development of a simple simulated 2-wheel drive mobile robot platform.
You will need to research suitable actuators and platform designs. From review of your research then produce
a specification and model of the platform to hold the proposed processor unit (myRIO), and actuators together
(your chosen motors from selection available) with a battery (Hardware datasheets on BB).
arrow_forward
I want to answer all the questions by handwriting.
arrow_forward
Test 1 .DOCX * A
File Edit View
Tools Help
INDUSTRIAL ENGINEERING PROGRAMME
IMB 411-INDUSTRIAL LOGISTICS
TEST 1- SEPTEMBER 12, 2012
Instructions: Answer all questions. Time allowed is 1.5 hours. Identify your script with your
student number ONLY (Do not write your name).
1. Define the following terms
(i) Logistics management
(ii) Supply chain management
(iii) Vertical integration in a supply chain
(3 Marks)
(3 Marks)
(3 Marks)
2. (a) Using examples of your choice, briefly discuss the following levels of customer
service
(1) Pre-transaction elements
(ii) Transaction elements
(4 Marks)
(4 Marks)
(iii) Post-transaction elements
(4 Marks)
(b) "The challenge facing Dumelang Enterprise (Pty) Ltd is to establish the real
profitability of their customers and to develop service strategies that will improve the
profitability of all customers". As a logistics consultant, briefly discuss how you can
advise Dumelang's customer service management.
3. (a) List the three main forms of inventory in a…
arrow_forward
You are assigned as the head of the engineering team to work on selecting the right-sized blower that will go on your new line of hybrid vehicles.The fan circulates the warm air on the inside of the windshield to stop condensation of water vapor and allow for maximum visibility during wintertime (see images). You have been provided with some info. and are asked to pick from the bottom table, the right model number(s) that will satisfy the requirement. Your car is equipped with a fan blower setting that allow you to choose between speeds 0, 1,2 and 3. Variation of the convection heat transfer coefficient is dependent upon multiple factors, including the size and the blower configuration.You can only use the following parameters:
arrow_forward
Hartley Electronics, Inc., in Nashville, producesshort runs of custom airwave scanners for the defense industry.The owner, Janet Hartley, has asked you to reduce inventory byintroducing a kanban system. After several hours of analysis, youdevelop the following data for scanner connectors used in onework cell. How many kanbans do you need for this connector?Daily demand 1,000 connectorsLead time 2 daysSafety stock 12 dayKanban size 500 connectors
arrow_forward
The Weather Monitor. Your South American expedition splits into two groups: one that stays at home base, and yours that goes off to
set up a sensor that will monitor precipitation, temperature, and sunlight through the upcoming winter. The sensor must link up to a
central communications system at base camp that simultaneously uploads the data from numerous sensors to a satellite. In order to
set up and calibrate the sensor, you will have to communicate with base camp to give them specific location information.
Unfortunately, the group's communication and navigation equipment has dwindled to walkie-talkies and a compass due to a river-raft
mishap, which means your group must not exceed the range of the walkie-talkies (3.0 miles). However, you do have a laser rangefinder
to help you measure distances as you navigate with the compass. After a few hours of hiking, you find the perfect plateau on which to
mount the sensor. You have carefully mapped your path from base camp around lakes and…
arrow_forward
Esker on Demand- Customer X Chat Process Jobs In Hyderaba x
(Messages | Mynaukri
M Chegg Expert Hiring | Complet x
O Zoho Creator - Chegg Expert
experthiring.cheggindia.com/%23Form:Subject test?privateLink=bF53Pq3tqOdXDb6qq0PKbXBKnU6s212F4b2fdONuXXgZX2DTmgJz56EF3A79haQq4A..
Q
S Paused
Apps
State Bank of India...
Welcome to Esker o...
I Feet to Inches conv...
en Watch Super Hit Ful...
IRCTC Next Generat...
A TASHRM
A Time Tracker Time
Prime Video: Good...
Chin Expert Hr
saKANOLA
Subect Test
Determine the Sommerfeld number of a bearing whose clearance ratio is 600 and the
bearing load is 750 lbf . The length and radius of the given bearing is 1.75 in. and 0.75 in.
respectively. The viscosity of the oil inside the bearing is u=6 µreyn. The bearing is
rotating at a speed of 1800 rpm.
a) 0.28
b) 0.58
c) 0.23
d) 0.36
Activate Windows
Go to Settings to activate Windows.
453 PM
ヘ)み
OType here to search
THan-21
oms UP
...
arrow_forward
Directions: modify the standard SolidWorks ANSI B Landscape layout for your own engineering
consulting company. Include a logo, change the legal notice, and make other changes as you see fit.
Be creative! Save this as a SolidWorks drawing layout template and use in subsequent submissions.
Usual DRAWN BY.
Deliverable: screenshot of your personalized layout/template without any drawings on it.
arrow_forward
mylabmastering.pearson.com
Chapter 12 - Lecture Notes.pptx: (MAE 272-01) (SP25) DY...
P Pearson MyLab and Mastering
Scores
arrow_forward
11)
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you

Precision Machining Technology (MindTap Course Li...
Mechanical Engineering
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Cengage Learning
Related Questions
- 4. Documents business requirements use-case narratives.for only one process note: please i want Documents like this in picarrow_forwardUsing signavio or any PBM tools and must Use pool and lane and object. Model the following business process at a supplier. After a supplier notifies a retailer of the approval of a purchase order, the supplier can receive an order confirmation, an order change, or an order cancelation from the retailer. It may happen that no response is received at all. If no response is received after 48 h, or if an order cancelation is received, the supplier will cancel the order. If an order confirmation is received within 48 h, the supplier will process the order normally. If an order change is received within 48 h, the supplier will update the order and ask again the retailer for confirmation. The retailer is allowed to change an order at most three times. Afterwards, the supplier will automatically cancel the order.arrow_forwardCan someone please help to solve all of the following problem showing all work and include a load chart. Thank you!arrow_forward
- + → CO A student.masteryconnect.com/?iv%3D_n5SY3Pv5S17e01Piby Gr 8 Sci Bench 1 GradeCam Rutherford TN 2021 AHMAD, ASHNA D0 3 of 35 A student develops a model of an electric motor using two pins, a wire coil, coil continues to spin with a certain speed. wire coil pins magnet tape battery How can the student increase the speed of the electric motor? O by using wider pins O by using thinner pins O by using less wire in the clil O by using more wire in the coil e Type here to search 近arrow_forwardIdentify the linesarrow_forwardSystem Specification Task 1 is to complete the development of a simple simulated 2-wheel drive mobile robot platform. You will need to research suitable actuators and platform designs. From review of your research then produce a specification and model of the platform to hold the proposed processor unit (myRIO), and actuators together (your chosen motors from selection available) with a battery (Hardware datasheets on BB).arrow_forward
- I want to answer all the questions by handwriting.arrow_forwardTest 1 .DOCX * A File Edit View Tools Help INDUSTRIAL ENGINEERING PROGRAMME IMB 411-INDUSTRIAL LOGISTICS TEST 1- SEPTEMBER 12, 2012 Instructions: Answer all questions. Time allowed is 1.5 hours. Identify your script with your student number ONLY (Do not write your name). 1. Define the following terms (i) Logistics management (ii) Supply chain management (iii) Vertical integration in a supply chain (3 Marks) (3 Marks) (3 Marks) 2. (a) Using examples of your choice, briefly discuss the following levels of customer service (1) Pre-transaction elements (ii) Transaction elements (4 Marks) (4 Marks) (iii) Post-transaction elements (4 Marks) (b) "The challenge facing Dumelang Enterprise (Pty) Ltd is to establish the real profitability of their customers and to develop service strategies that will improve the profitability of all customers". As a logistics consultant, briefly discuss how you can advise Dumelang's customer service management. 3. (a) List the three main forms of inventory in a…arrow_forwardYou are assigned as the head of the engineering team to work on selecting the right-sized blower that will go on your new line of hybrid vehicles.The fan circulates the warm air on the inside of the windshield to stop condensation of water vapor and allow for maximum visibility during wintertime (see images). You have been provided with some info. and are asked to pick from the bottom table, the right model number(s) that will satisfy the requirement. Your car is equipped with a fan blower setting that allow you to choose between speeds 0, 1,2 and 3. Variation of the convection heat transfer coefficient is dependent upon multiple factors, including the size and the blower configuration.You can only use the following parameters:arrow_forward
- Hartley Electronics, Inc., in Nashville, producesshort runs of custom airwave scanners for the defense industry.The owner, Janet Hartley, has asked you to reduce inventory byintroducing a kanban system. After several hours of analysis, youdevelop the following data for scanner connectors used in onework cell. How many kanbans do you need for this connector?Daily demand 1,000 connectorsLead time 2 daysSafety stock 12 dayKanban size 500 connectorsarrow_forwardThe Weather Monitor. Your South American expedition splits into two groups: one that stays at home base, and yours that goes off to set up a sensor that will monitor precipitation, temperature, and sunlight through the upcoming winter. The sensor must link up to a central communications system at base camp that simultaneously uploads the data from numerous sensors to a satellite. In order to set up and calibrate the sensor, you will have to communicate with base camp to give them specific location information. Unfortunately, the group's communication and navigation equipment has dwindled to walkie-talkies and a compass due to a river-raft mishap, which means your group must not exceed the range of the walkie-talkies (3.0 miles). However, you do have a laser rangefinder to help you measure distances as you navigate with the compass. After a few hours of hiking, you find the perfect plateau on which to mount the sensor. You have carefully mapped your path from base camp around lakes and…arrow_forwardEsker on Demand- Customer X Chat Process Jobs In Hyderaba x (Messages | Mynaukri M Chegg Expert Hiring | Complet x O Zoho Creator - Chegg Expert experthiring.cheggindia.com/%23Form:Subject test?privateLink=bF53Pq3tqOdXDb6qq0PKbXBKnU6s212F4b2fdONuXXgZX2DTmgJz56EF3A79haQq4A.. Q S Paused Apps State Bank of India... Welcome to Esker o... I Feet to Inches conv... en Watch Super Hit Ful... IRCTC Next Generat... A TASHRM A Time Tracker Time Prime Video: Good... Chin Expert Hr saKANOLA Subect Test Determine the Sommerfeld number of a bearing whose clearance ratio is 600 and the bearing load is 750 lbf . The length and radius of the given bearing is 1.75 in. and 0.75 in. respectively. The viscosity of the oil inside the bearing is u=6 µreyn. The bearing is rotating at a speed of 1800 rpm. a) 0.28 b) 0.58 c) 0.23 d) 0.36 Activate Windows Go to Settings to activate Windows. 453 PM ヘ)み OType here to search THan-21 oms UP ...arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Precision Machining Technology (MindTap Course Li...Mechanical EngineeringISBN:9781285444543Author:Peter J. Hoffman, Eric S. Hopewell, Brian JanesPublisher:Cengage Learning

Precision Machining Technology (MindTap Course Li...
Mechanical Engineering
ISBN:9781285444543
Author:Peter J. Hoffman, Eric S. Hopewell, Brian Janes
Publisher:Cengage Learning