ASSESSMENT 2
Qualification
BSB50820 Diploma of Project Management
Subject
Project Risk 2
Assessment method
Written Responses
Weighting
50%
Unit of Competency
BSBPMG536 Manage project risk
1.
RISK TREATMENT SCHEDULE
Using the information you completed in Assessment 1 question 8 – the Risk Register, complete the table below for all 5 risks assuming that the risk has
occurred.
You now need to develop possible treatment options, recommend the preferred option, rate the risk before and after the treatment, who you will
assign in the team to be responsible and how this will be monitored.
3.4 Update risk plans and allocate risk responsibilities to project team members
PE - apply risk management techniques, strategies and tools
KE - relevant project risk controls
KE - project risk-management processes and procedures
Compiled by: Ochiroo Tuvshintur
Date:
11/11/2023
Risk
No.
Possible
Treatment
Options
Preferred Options
Risk
Rating
BEFORE
Treatmen
t
Risk
Rating
AFTER
Treatmen
t
Cost/Ben
efit
Analysis
A: Accept
B: Reject
Person
Responsible for
Implementation
Timetab
le
How will it be
monitored
1
Hire an engineer to
approve the
installation prior to the
event
Postpone event if the
weather and wind
speed is above 35
km/p
Prototype testing
Hire an engineer – it will
allow the event to
proceed; it reduces the
safety risk. Hire of
engineer $500.
H
L
A
Onsite event
coordinator
1 day
prior to
event
Coordinator liaises with
engineer, provides
certification to PM
office on 10/5/2020
2
Knowing how to lift
and move big objects
is
essential. In the event
that one of the team
members is injured,
medical expenditure
coverage is provided.
Employ a trainer to
teach your personnel
how to deal with huge
crowds while limiting
the risks that come with
them.
H
L
A
Project Manager
1 month
before
At all times, the project
manager is on top of
everything.
3
Notify your coworkers
that you require
As soon as possible, the
employees should be
H
M
A
Stakeholder Project
Manager
15 days
Maintain communicatio
n with members of the
medical assistance.
Quarantine should be
implemented for all
personnel.
sent to the hospital.
team to stay informed
about his everyday
activities. Once the
quarantine period has
expired, a covid test is
required to determine
that your employee is
unaffected.
4
Determine when the
weather will be
acceptable for work
again by consulting
with the engineer and
project manager.
If you are unable to
return to work,
reschedule the staff's
shift.
For the most up-to-date
information on when it
is safe to return to work,
consult the engineer
and project manager.
H
L
A
Project MANAGER
Engineer
2 days
before
event
Before building begins,
the local climatic
conditions may be
evaluated. A forecast
based on the current
weather conditions.
For the most up-to-date
information on when it
is safe to return to work,
consult the engineer
and project manager.
5
Personal protective
Equipment (PPE) must
be available and in
good working order,
which is the Project
Manager's duty.
No one on your team
should be permitted to
work without suitable
PPE (PPE).
Ensuring that all staff
are
productive is always a
top focus.
H
L
A
Staff Project
Manager
Monthly
Every day, I review all
PPE working
circumstances.
Ascertain that everyone
in the building has
access to and is dressed
in his own clothes
equipment for
protection (PPE).
6
Make sure there are
no
cost overruns before
implementing a
project plan. It is
necessary
to reallocate
resources.
Make sure there are no
hidden charges before
beginning a project.
H
M
A
Financial
Department
Project
Manager Finantial
area
monthly
A project management
tool to your advantage.
Keep a close eye on the
situation for any
changes
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
2.
RISK ACTION PLAN TABLE – Modifying the plan
Select 3 risks from your Risk Treatment Schedule, preferably ones have a high rating.
You
now need to create an action plan for each to manage the risk appropriately.
Complete
one table for each risk.
4.4 Implement agreed risk responses and modify plans
PE - manage project risk on at least two occasions
PE - conduct effective risk management processes for a project of sufficient complexity
PE - apply risk management techniques, strategies and tools
KE - relevant project risk controls
KE - project risk-management processes and procedures
(Example of Risk Action Plan relating to “Marquee Collapse”)
RISK ACTION PLAN
Risk No.
1
Risk Title
Marquee Collapse
Risk Response
Summary
(Recommended
response & impact)
To ensure that the marquee installer completes an inspection checklist, submits
it to the event organiser and to develop a procedure to have the marquee
dismantled in the event of unacceptable wind speed, to ensure that the risk of
collapse is acceptable.
Proposed Actions
(State what the key tasks
are that need to be
undertaken as part of the
risk response)
Contact marquee company and advise that they will need to complete
checklist and submit it to the event organiser once the marquee is
erected.
Develop a procedure for dismantling of the marquee in response
to unacceptable wind speed.
Contract engineer to inspect installation and provide
certification.
Resource Requirements
(What physical and
human resources are
required to implement
risk response?)
Onsite event coordinator
Hire engineer- must have the
right skills and expertise (marquee)
Phone
computer
Costings
(Provide costings of risk
response)
$500 to hire engineer
Responsibilities
(State who will be
responsible and what
parts of the risk response
they are responsible for –
maybe more than 1
person)
Responsibility of
Onsite Event coordinator to contact engineer and liaise for
them to inspect and certify marquee installation on 10/5/2022. Provide the
certification to the PM Office on 10/5/2022.
Timing
(provide due dates for the
key tasks in the risk
response)
Engineer to be sourced by 10/4/2022
Marquee installed by 9/5/2022
Engineer to certify marquee on 10/5/2022
Onsite event coordinator to provide certification document to PM office
10/5/2022
Reporting/Monitoring
(Provide a list of the key
tasks to be
included in
Event coordinator confirms with engineer a week prior to certification that
they are still available
4
the report process, as well
as the person who will be
providing the update)
Event coordinator notifies when engineer is sourced
Event coordinator notifies when marquee installed, engineer has certified
installation
Consulted with
Stakeholders
(You need to say who and
what methods were used
to consult with them)
Discussed with project manager, marquee company and client via phone
RISK ACTION PLAN
Risk No.
1
Risk Title
As a result of handling large things, back injuries might occur.
Risk Response
Summary
(Recommended
response & impact)
To avoid back injuries and other physical harm, we intend to hire a trainer who will
teach our staff how to properly move huge objects and give them with medical
insurance in the event that one of them is injured.
Proposed Actions
(State
the key tasks that
need to be undertaken as
part of the risk response)
Project managers and supervisors must keep a close watch on their staff
in addition to ensuring that they are properly trained and protected from risks.
Resource Requirements
(What physical and
human resources are
required to implement
risk response?)
PPE
Trainer
Costings
(Provide costings of risk
response)
Trainer will cost $1000
Responsibilities
(State who will be
responsible and what
parts of the risk response
they are responsible for –
maybe more than 1
person)
The trainer will be in charge of training the workforce by October 5, 2021.
The Project Manager will be responsible for the crew's performance by October 30,
2021.
Timing
(Provide due dates for the
key tasks in the risk
response)
Health insurance is provided to all workers (as of January 10, 2021).
(05/10/2021) The trainer ensures that suitable training is delivered.
Keep track of employee performance until October 30, 2021.
Reporting/Monitoring
(Provide a list of the key
tasks to be included in the
report process, as well as
the person who will be
providing the update)
A project manager should contact HR before beginning work to check that all
employees are covered by medical insurance.
The trainer must interact with skilled specialists in order to minimise hazards.
The project manager must maintain tabs on the progress of the team.
Consulted with
Stakeholders
(You need to say who and
what methods were used
to consult with them)
It was discussed by the project manager, trainer, and personnel.
5
RISK ACTION PLAN
Risk No.
2
Risk Title
Covid-19 Infection
Risk Response
Summary
(Recommended
response & impact)
Employees who have been exposed to Covid-19 are required to take 15
days off work until they have recovered and passed a negative Covid test
in order to maintain the workplace free of the virus.
Proposed Actions
(State the key tasks that
need to be undertaken as
part of the risk response)
Employees who catch the flu are required to take it. If you see indications of Covid-
19, consult a doctor and be tested. because of the virus Before being returning to
their jobs, the workers must be medicated dwellings, as well as being imprisoned.
Employees who have been confined for 15 days or longer must take the Covid test
to confirm they are virus-free.
Resource Requirements
(What physical and
human resources are
required to implement
risk response?)
Medical Insurance
Costings
(Provide costings of risk
response)
Medical insurance for an individual costs roughly $50 a month.
Responsibilities
(State who will be
responsible and what
parts of the risk response
they are responsible for –
maybe more than 1
person)
Employees must declare any health conditions and get medical assistance
by the deadline of 5/10/2021.
The Project Manager must notify HR of any changes in worker health by
06/10/2021 in order to be in compliance by that date.
Timing
(Provide due dates for the
key tasks in the risk
response)
On October 5, 2021, a staff flu test and a Covid-19 test are scheduled.
Employees infected with Covid-19 must be quarantined before October 10, 2021.
By October 10th, 2021, notify Human Resources (HR) of a staff member's health.
Reporting/Monitoring
(Provide a list of the key
tasks to be included in the
report process, as well as
the person who will be
providing the update)
On October 5, 2021, a staff flu test and a Covid-19 test are scheduled.
Employees infected with Covid-19 must be quarantined before October 10, 2021.
By October 10th, 2021, notify Human Resources (HR) of a staff member's health.
Consulted with
Stakeholders
(You need to say who and
what methods you used
to consult with them)
In addition to the employees, the Project Manager, medical aid, and human
resources were all alerted.
3.
Assess Risk Management Outcomes
a.
Review project outcomes and discuss:
one risk that arose in your project and how it was effectively managed with your risk
management processes and procedures’
one risk that arose in your project where your risk management processes and procedures
did not work and what you had to do to address the risk.
5.1 Review project outcomes for effectiveness of risk-management processes and procedures
6
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
The main outcome was the scope and definitions agreement review with client. So any change was
communicated, budgeted and scheduled, with risk update in the day after the meeting.
The new action pans, if needed, were delivered to the client right after, for agreement as well. The
risk registers were updated in a risk meeting the day after too.
b.
Based on your review of the risk management process and procedures, develop recommended
improvements for future projects.
The risk management follow up was well done, detecting most of the changes in the project risk
factors, environment and client demands too. The initial risk detection and action plans were
effective, since all these risks were correctly avoided or treated as expected.
This allowed the project to end on time and following the previewed budget, with client aditions.
5.2 Develop recommended improvements for application in future projects
c.
Based on your review of the risks that occurred in your project, identify three issues and
recommend what improvements could be made in future projects to avoid these risk issues.
Client availability to participate the meetings.
Delay on the risk management and action plans delivery t the client agreement.
Difficulty building the scope and risk adjustment plan to client agreement
Recommendation:
Set the dates before to schedule alignment
Review of the plans to be delivered in 2 days to the client and more staff in risk management
team
Participation of the risk management staff in the meeting with the client to detect better the
changes discussed
5.3 Identify and document risk management issues and recommended improvements for application
to future projects
END