5-3 Milestone Four_Predictive Schedule Management Plan

docx

School

Southern New Hampshire University *

*We aren’t endorsed by this school

Course

345

Subject

Business

Date

Nov 24, 2024

Type

docx

Pages

5

Uploaded by Telasha1984_1

Report
1 5-3 Milestone Three: Schedule Management Plan Tamika Robinson QSO-345: Project Management for CAPM Certification Jim Cotton December 2, 2023
2 Schedule Management Plan - Predictive Methodology Introduction The schedule management plan outlines how the project will be planned, designed, executed, monitored, and controlled (PMI, 2021). It will outline the project manager and team's approach, methodologies, milestones, and timeline for each activity. This document will be used to measure Project Destiny's performance. We'll define variance thresholds to take corrective action when necessary to ensure we can complete the project on time and within budget. To prevent a project from deviating too far from the planned schedule, earned value metrics can provide insight into a project's current performance and predict future behavior (PMI, 2021). Regarding the schedule, the schedule variance (SV) measures whether a project is behind or ahead of schedule (PMI, 2021). This will aid the project manager in monitoring the project's schedule to ensure no additional finances are incurred. The schedule performance index (SPI) monitors how efficiently the project progresses compared to the plan (PMI, 2021). It helps evaluate the accuracy of a schedule and how well the project team is using its time. The schedule management plan will outline regular intervals to manage the schedule and establish baselines and action plans when variances occur. Schedule management approach First, we'll need to identify all the activities and tasks to be completed for the project. This can be done with working sessions, consulting with team members/SMEs, or assessing previous projects. Then, determine the order of each activity and task. Creating a network diagram can aid in visually indicating the sequential order. Some activities may need to be done sequentially, and some could be done in parallel. Then, we'll need to estimate how long each will take. Analogous and three-point estimating techniques were used for Project Destiny to estimate activity durations. Then, we'll need to develop a schedule by inputting all activities sequentially by their durations. Using this schedule will help with developing a timeline. Lastly, we'll need to review with vital stakeholders. Necessary adjustments will be made before finalizing the schedule. Activity list The activity list outlines all the activities required for Project Destiny. The chart will include the activity name/description predecessor and the estimated work item. The project manager will be responsible for ensuring all items are captured and continuously reviewing the WBS and timeline to ensure all items are being handled timely. WBS WBS Name Predecessor WBS ID Estimated Time (Weeks) 1.1 Legal and Regulatory 1.1.1 Lease Finalization - 4 1.1.2 Obtain Permits 1.1.1 10 1.1.3 Zoning Approvals 1.1.1 8 1.1.4 Select Contractor - - 1.1.5 Certification Completion - - 1.2 Initial build-out 1.2.1 Office construction 1.2.2, 1.2.3 12 1.2.2 Construct pod for quality department 1.1.2, 1.1.3 16 1.2.3 Construct pod for supervisors 1.1.2, 1.1.3
3 WBS WBS Name Predecessor WBS ID Estimated Time (Weeks) 1.3 Plant 1.3.1 Plant construction - - 1.3.2 Build/Construct proving room 1.2.2 4 1.3.3 Construct electrical system 1.1.2, 1.1.3 16 1.3.4 Construct pneumatic system 1.1.2, 1.1.3 1.4 Equipment 1.4.1 Anodizing line installation 1.1.2, 1.1.3 14 1.4.2 Remove machines from current location 1.3.3, 1.4.1 2 1.4.3 Install machines at new location 1.3.3, 1.4.1 2 1.5 Moving 1.5.1 Machine relocation - - 1.5.2 Assembly relocation 1.4.2, 1.4.3 1 1.5.3 Paint line relocation 1.5.2 6 1.5.4 Auxiliary equipment relocation 1.5.3 1 1.5.5 Information technology services 1.2.2, 1.2.3 12 1.5.6 Office move 1.2.1, 1.5.5 1 1.6 Transition 1.6.1 Create inventory of machined parts - - 1.6.2 Create inventory of assembled parts - - 1.6.3 Support customer deliveries - - 1.7 Close 1.7.1 Project End 1.3.2, 1.5.4, 1.5.6 - Table 1, Project Activity List Network diagram The network diagram visually maps the schedule and activity work sequence (PMI, 2021). It can be referred back to aid with tracking progress for each stage. Project Sequencing and Critical Path The table below will cover the project's sequence. The table will include the activity sequence, its corresponding estimated time, and a critical path indicator. Delays can impact Project Destiny, so this will help plan each activity's duration from start to completion. The project manager will ensure the timeline is not negatively impacted. Activity Path Sequence Total Duration Critical Path Y/N 1.1, 1.1.1, 1.1.2, 1.1.3, 1.1.4, 1.1.5 22 weeks Yes 1.2, 1.2.1, 1.2.2, 1.2.3 28 weeks Yes Figure SEQ Figure \* ARABIC 1- Project Network Diagram
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
4 Activity Path Sequence Total Duration Critical Path Y/N 1.3, 1.3.1, 1.3.2, 1.3.3, 1.3.4 20 weeks No 1.4, 1.4.1, 1.4.2, 1.4.3 18 weeks No 1.5, 1.5.1, 1.5.2, 1.5.3, 1.5.4, 1.5.5, 1.5.6 21 weeks Yes Table 2, Project Activity Sequencing and Durations
5 References Project Management Institute. (2021). A Guide to the project management body of knowledge (PMBOK® guide) (7th ed.)