QSO 420 3-2
docx
keyboard_arrow_up
School
Southern New Hampshire University *
*We aren’t endorsed by this school
Course
420
Subject
Accounting
Date
Apr 3, 2024
Type
docx
Pages
5
Uploaded by MegaStarAlpaca3
Southern New Hampshire University
QSO 420:3-2 Final Project Milestone One
Prof. Smith
Soucie, Joseph
3-30-2024
Basic Elements
Here is the introduction to the basic elements of earned value (EV), planned value (PV) actual cost (AC) & budget at completion (BAC) and where they can be found on the project charter. First taking a look at EV, earned value is the percentage of the total budget of the project at the time of completion. Earned value is also known as the budgeted cost of work performed or
BCWP. To calculate EV by multiplying the budget of the project work or activity by the percentage of the progress completed on the project activity or work completed
(Lukas, J. A. 2012)
. Next, Planned Value is the budget for the work that has been scheduled to be completed. This is the portion of the project that the capital that has budgeted to be spent at the given time during the duration of the project. This is also referred to budgeted cost of work schedule or BCWS
(Lukas, J. A. 2012)
. Then, looking at the actual cost of the project, simply the actual cost is the capital or money spent for the work completed on the project. Actual cost is also referred to actual cost of work performed or ACWP
(Lukas, J. A. 2012)
. Finally, the budget at completion
is the total approved budget when the scope of the project is done to completion, barring any project contingencies or project incidents. When examining the project charter the planned value,
earned value, and actual cost are at the top of the charter showing the current capital utilized and the cumulative capital used for the project and the budget at completion subject line is just below
the cumulative of the PV, EV, and AC displaying the project capital spent (
Earned Value Reporting
, n.d.).
Analyze
After reviewing the case study of the Clothes ‘R’ Us project charter, what I found is the project of managing the IT project, ran from through all of 2002 and six months into 2003. What I found interesting is in July of 2002 and September 2002 the project had requirements freeze on the project which is why the project ran into six months of 2003. Also looking over the project charter I also found that during the project the inventory cost grew during the project duration receiving in inventory also training on the new IT setup didn’t start up into four months into the project training new hires to effectively use the new software. At the end of the project, the Software and Hardware purchase and maintenance of the software and hardware didn’t exceed the total amount since there was the freeze in July and September. If the project would have continued, I believe the project would have finished sooner but would have gone over budget.
Earned Value
Discussing some of the methods of how to determine earned value, the first method is the
figuring throughout the project using the percent through percent finish method some of examples of this is the 50/50, 25/75,80/20, and the 0/100 method. Some of the variance of this methods include the percent complete earned value method, weighted milestone method, combining the two with weighted milestones with percent complete earned value method, and finally units completed EV method, this is when you have physical units to measure. The other two methods are apportioned effort earned value method and the level of effort earned value method (Blázquez & Blázquez, 2020). Apportioned effort is the method of planning and measuring the EV for the effort that is related in direct proportion to measure effort (
Apportioned
Effort
, n.d.). The level of Effort method refers to the activities that are the managers overhead of continuing a project that does not produce or manufacture and specific products of a project.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
After reading over the case study, the best method that fits the case study is the Level of Effort method, simply because the case study is producing or manufacturing nothing physical but creating an IT program for Clothes R us to operate more efficiently.
. . References:
Apportioned effort
. (n.d.). Humphreys & Associates. https://www.humphreys-assoc.com/evms/apportioned-effort-ta-a-
97.html#:~:text=Apportioned%20effort%20is%20a%20method%20of%20planning
%20and,is%20the%20most%20typical%20use%20of%20this%20method
.
Blázquez, D., & Blázquez, D. (2020, April 25). Earned Value methods to evaluate work performance. Project 2080
. https://project2080.com/en/earned-value-methods/#:~:text=The%20higher%20the
%20schedule%20risk,use%20to%20determine%20work%20performance
.
Earned value reporting
. (n.d.). https://www.projectengineer.net/tutorials/earned-value-tutorial/earned-value-reporting/
.
Lukas, J. A. (2012). How to make earned value work on your project. Paper presented at PMI® Global Congress 2012—North America, Vancouver, British Columbia, Canada. Newtown Square, PA: Project Management Institute.
https://www.pmi.org/learning/library/make-earned-
value-work-project-6001#:~:text=Earned%20Value%20(EV)%20is%20the,of%20work
%20performed%20(BCWP)
.
Related Documents
Related Questions
Question Help
Use the NPV method to determine whether Smith Products should invest in the following projects:
Project A: Costs $270,000 and offers eight annual net cash inflows of $57,000. Smith Products requires an annual return of 14% on investments of this nature.
Project B: Costs $390,000 and offers 10 annual net cash inflows of $74,000. Smith Products demands an annual return of 12% on investments of this nature.
(Click the icon to view Present Value of $1 table.)
(Click the icon to view Present Value of Ordinary Annuity of $1 table.)
Read the requirements.
Requirement 1. What is the NPV of each project? Assume neither project has a residual value. Round to two decimal places. (Enter any factor amounts to three decimal places, X.XXX. Use parentheses or a minus sign for a negative net
present value.)
Caclulate the NPV (net present value) of each project. Begin by calculating the NPV of Project A.
Project A:
Net Cash
Annuity PV Factor
Present
Years
Inflow
(i=14%, n=8)
Value
1 - 8…
arrow_forward
Answer B pls!!
arrow_forward
ne
NPV, with rankings Botany Bay, Inc., a maker of casual clothing, is considering four projects shown in the following table,
Because of past financial difficulties,
ptions the company has a high cost of capital at 14.4%.
a. Calculate the NPV of each project, using a cost of capital of 14.4%.
b. Rank acceptable projects by NPV.
c. Calculate the IRR of each project and use it to determine the highest cost of capital at which all of the projects would be acceptable.
a. Calculate the NPV of each project, using a cost of capital of 14.4%.
The NPV of project A is $
(Round to the nearest cent.)
Is project A acceptable? (Select the best answer below.)
O A. No
O B. Yes
The NPV of project B is $
(Round to the nearest cent.)
la nreinnt Danontabl-2/0lest the hant an nr hale
Click to select your answer(s).
P Type here to search
arrow_forward
Table 1: Project Data
Project
NPV (M$)
Risk (%)
Capital (M$)
A
19
4
14
B
22
S
10
C
24
6
12
D
27
7
15
E
21
5
13
The budget constraint may be stated as:
*A+c+2%p <= 0
14% +10x12x15xD -13%E43
14% -10%E-12x15xD -13%E43
%B5%E
arrow_forward
Part B please
arrow_forward
Please, this is the next question
arrow_forward
Required information
[The following information applies to the questions displayed below.]
The following capital expenditure projects have been proposed for management's consideration at Scott Inc. for the
upcoming budget year: Use Table 6-4 and Table 6-5. (Use appropriate factor(s) from the tables provided. Round the PV
factors to 4 decimals.)
Project
Year(s)
B
D
$ (25,000)
$(50,000)
16,000
16,000
16,000
16,000
16,000
$ (50,000)
5,000
10,000
15,000
20,000
25,000
Initial investment
$(25,000)
5,000
5,000
5,000
5,000
5,000
5,000
$ 1,081
$(100,000)
30,000
30,000
Amount of net cash return
1
2
3.
10,000
10,000
10,000
6,000
15,000
15,000
15,000
15,000
2,942
4
5
Per year
6-10
NPV (14% discount rate)
2$
$
Present value ratio
1.04
Required:
a. Calculate the net present value of projects
indicated by a minus sign.)
and D, using
as the cost of capital for Scott Inc. (Negative amounts should be
Project
Net Present
Value
B
D
arrow_forward
10/8/2021
Chapter 5 - Homework-sehrish bashir
%3D
4(Click the icon to view the budgeted information.)
Read the requirements.
(Click the icon to view other information.)
Requirement 1. Calculate the cost per unit of cost driver for each indirect-cost pool.
used: "equip." = equipment, "maint." = maintenance.)
%3D
%3D
(2)
Cost driver rate
%3D
Setup
(1)
(3)
%3D
Equip. and Maint.
()
(5)
%3D
Lease rent, etc.
%3D
Requirement 2. What is the budgeted cost of unused capacity?
Select the formula you will use, then calculate the cost of unused capacity.
Cost of unused capacity
(9)
(2)
%3D
Requirement 3. What is the budgeted total cost and the cost per unit of resources used to produce (a) basketballs and (b)
volleyballs? (Enter the cost per unit to the nearest cent.)
Basketballs
Volleyballs
Total
Direct materials
Direct manufacturing labor
Setup
Equipment and maintenance
Lease rent, etc.
Budgeted total costs
Number of units
Budgeted cost per unit
Requirement 4. Why might excess capacity be…
arrow_forward
arning X
+
tps://ng.cengage.com/static/nb/ui/evo/index.html?deploymentid=5933142288413647560152243&eISBN=97813379
CENGAGE | MINDTAP
11: Assignment - The Basics of Capital Budgeting
Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of
$800,000.
Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using
the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because returns in percentage form are
easier to understand and compare to required returns. Blue Llama Mining Company's WACC is 8%, and project Sigma has the same risk
as the firm's average project.
The project is expected to generate the following net cash flows:
Year
Year 1
Year 2
Year 3
Year 4
Cash Flow
$350,000
$475,000
$425,000
$500,000
Which of the following is the correct calculation of project Sigma's IRR?
34.38%
38.20%
42.02%
O 36.29%
arrow_forward
Required information
[The following information applies to the questions displayed below.]
The following capital expenditure projects have been proposed for management's consideration at Scott Inc. for the
upcoming budget year: Use Table 6-4 and Table 6-5. (Use appropriate factor(s) from the tables provided. Round the PV
factors to 4 decimals.)
Project
Year (s)
D
E
$ (25,000)
5,000
5,000
5,000
5,000
5,000
5,000
$ 1,081
$ (25,000)
$ (50,000)
$ (50,000)
5,000
10,000
15,000
20,000
25,000
Initial investment
$(100,000)
30,000
30,000
Amount of net cash return
16,000
16,000
16,000
16,000
16,000
10,000
15,000
10,000
10,000
6,000
15,000
15,000
5
Per year
6-10
15,000
NPV (14% discount rate)
$ 2,942
Present value ratio
1.04
b. Calculate the present value ratio for projects B, C, D, and E. (Round your answers to 2 decimal places.)
Project
Present Value
Ratio
B
D
E
arrow_forward
Use the information for the question(s) below.
Project A
- 10,000
Project B
Time 0
- 10,000
Time 1
5,000
4,000
Time 2
4,000
3,000
Time 3
3,000
10,000
If WiseGuy Inc. uses IRR rule to choose projects, which of the projects (Project A or Project B) will rank highest?
OA. Project A
OB. Project B
OC. Project A and Project B have the same ranking
OD. Cannot calculate a payback period without a discount rate.
arrow_forward
The following information is available on two mutually exclusive projects.
Project Year 0 Year 1 Year 2 Year 3 Year 4
A -$700 $200 $300 $400 $500
B -$700 $600 $300 $200 $100
If the required rate of return is 10%, which project should be selected using the internal rate of return (IRR) method?
Group of answer choices
A
B
arrow_forward
Information for two alternative projects involving machinery investments follows. Project 1 requires an initial investment of $148,000.
Project 2 requires an initial investment of $133,000.
Annual Amounts
Sales of new product
Expenses
Materials, labor, and overhead (except depreciation)
Depreciation-Machinery
Selling, general, and administrative expenses
Project 1
$ 120,000
Project 2
$ 100,000
70,000
25, 000
13,000
$ 12,000
37,000
23,000
25, 000
$ 15,000
Income
(a) Compute each project's annual net cash flow.
(b) Compute payback period for each investment.
Complete this question by entering your answers in the tabs below.
Required A
Required B
Compute each project's annual net cash flow,
Annual Amounts
Project 1
Project 2
Income
Cash Flow
Income
Cash Flow
Sales of new product
120,000
100,000
Expenses
Malerials, labor, and overhead (except depreciation)
70.000
37,000
Depreciation-Machinery
25.000
23.000
Seling, general, and administrative expenses
13,000
25,000
Income
Net cash flow…
arrow_forward
EXERCISE 3: CASH INFLOWS AND CASH OUTFLOWS
With the following capital budgetng elements, identify the cash outflows and cash
inflows that you would use to judge the attractiveness of a project by using the time-
value-of money yardstıcks capital assets ($1.5 million), working capital in year 1
($500,000) and year 2 ($200,000), salaries ($140,000), working capital loan ($190,000).
residual value at the end of the 11th year ($1 million), profit for the years 1 to 10
($300,000), mortgage ($1.1 million), non-cash expense ($50,000), revenue ($300,000),
and sunk costs ($100,000). The project's lifespan is 10 years and the cost of capital is
8%.
arrow_forward
Howard Cooper, the president of Campbell Computer Services, needs your help. He wonders about the potential effects on the firm's
net income if he changes the service rate that the firm charges its customers. The following basic data pertain to fiscal Year 3.
Standard rate and variable costs
Service rate per hour
$
85.00
Labor cost
37.00
Overhead cost
7.10
Selling, general, and administrative cost
Expected fixed costs
Facility maintenance
Selling, general, and administrative
3.80
$522,000
142,000
Required:
a. Prepare the pro forma income statement that would appear in the master budget if the firm expects to provide 45,000 hours of
services in Year 3.
b. A marketing consultant suggests to Mr. Cooper that the service rate may affect the number of service hours that the firm can
achieve. According to the consultant's analysis, if Campbell charges customers $80 per hour, the firm can achieve 50,000 hours of
services. Prepare a flexible budget using the consultant's assumption.
c. The same…
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Related Questions
- Question Help Use the NPV method to determine whether Smith Products should invest in the following projects: Project A: Costs $270,000 and offers eight annual net cash inflows of $57,000. Smith Products requires an annual return of 14% on investments of this nature. Project B: Costs $390,000 and offers 10 annual net cash inflows of $74,000. Smith Products demands an annual return of 12% on investments of this nature. (Click the icon to view Present Value of $1 table.) (Click the icon to view Present Value of Ordinary Annuity of $1 table.) Read the requirements. Requirement 1. What is the NPV of each project? Assume neither project has a residual value. Round to two decimal places. (Enter any factor amounts to three decimal places, X.XXX. Use parentheses or a minus sign for a negative net present value.) Caclulate the NPV (net present value) of each project. Begin by calculating the NPV of Project A. Project A: Net Cash Annuity PV Factor Present Years Inflow (i=14%, n=8) Value 1 - 8…arrow_forwardAnswer B pls!!arrow_forwardne NPV, with rankings Botany Bay, Inc., a maker of casual clothing, is considering four projects shown in the following table, Because of past financial difficulties, ptions the company has a high cost of capital at 14.4%. a. Calculate the NPV of each project, using a cost of capital of 14.4%. b. Rank acceptable projects by NPV. c. Calculate the IRR of each project and use it to determine the highest cost of capital at which all of the projects would be acceptable. a. Calculate the NPV of each project, using a cost of capital of 14.4%. The NPV of project A is $ (Round to the nearest cent.) Is project A acceptable? (Select the best answer below.) O A. No O B. Yes The NPV of project B is $ (Round to the nearest cent.) la nreinnt Danontabl-2/0lest the hant an nr hale Click to select your answer(s). P Type here to searcharrow_forward
- Table 1: Project Data Project NPV (M$) Risk (%) Capital (M$) A 19 4 14 B 22 S 10 C 24 6 12 D 27 7 15 E 21 5 13 The budget constraint may be stated as: *A+c+2%p <= 0 14% +10x12x15xD -13%E43 14% -10%E-12x15xD -13%E43 %B5%Earrow_forwardPart B pleasearrow_forwardPlease, this is the next questionarrow_forward
- Required information [The following information applies to the questions displayed below.] The following capital expenditure projects have been proposed for management's consideration at Scott Inc. for the upcoming budget year: Use Table 6-4 and Table 6-5. (Use appropriate factor(s) from the tables provided. Round the PV factors to 4 decimals.) Project Year(s) B D $ (25,000) $(50,000) 16,000 16,000 16,000 16,000 16,000 $ (50,000) 5,000 10,000 15,000 20,000 25,000 Initial investment $(25,000) 5,000 5,000 5,000 5,000 5,000 5,000 $ 1,081 $(100,000) 30,000 30,000 Amount of net cash return 1 2 3. 10,000 10,000 10,000 6,000 15,000 15,000 15,000 15,000 2,942 4 5 Per year 6-10 NPV (14% discount rate) 2$ $ Present value ratio 1.04 Required: a. Calculate the net present value of projects indicated by a minus sign.) and D, using as the cost of capital for Scott Inc. (Negative amounts should be Project Net Present Value B Darrow_forward10/8/2021 Chapter 5 - Homework-sehrish bashir %3D 4(Click the icon to view the budgeted information.) Read the requirements. (Click the icon to view other information.) Requirement 1. Calculate the cost per unit of cost driver for each indirect-cost pool. used: "equip." = equipment, "maint." = maintenance.) %3D %3D (2) Cost driver rate %3D Setup (1) (3) %3D Equip. and Maint. () (5) %3D Lease rent, etc. %3D Requirement 2. What is the budgeted cost of unused capacity? Select the formula you will use, then calculate the cost of unused capacity. Cost of unused capacity (9) (2) %3D Requirement 3. What is the budgeted total cost and the cost per unit of resources used to produce (a) basketballs and (b) volleyballs? (Enter the cost per unit to the nearest cent.) Basketballs Volleyballs Total Direct materials Direct manufacturing labor Setup Equipment and maintenance Lease rent, etc. Budgeted total costs Number of units Budgeted cost per unit Requirement 4. Why might excess capacity be…arrow_forwardarning X + tps://ng.cengage.com/static/nb/ui/evo/index.html?deploymentid=5933142288413647560152243&eISBN=97813379 CENGAGE | MINDTAP 11: Assignment - The Basics of Capital Budgeting Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to start using the IRR method for capital budgeting decisions. The CFO says that the IRR is a better method because returns in percentage form are easier to understand and compare to required returns. Blue Llama Mining Company's WACC is 8%, and project Sigma has the same risk as the firm's average project. The project is expected to generate the following net cash flows: Year Year 1 Year 2 Year 3 Year 4 Cash Flow $350,000 $475,000 $425,000 $500,000 Which of the following is the correct calculation of project Sigma's IRR? 34.38% 38.20% 42.02% O 36.29%arrow_forward
- Required information [The following information applies to the questions displayed below.] The following capital expenditure projects have been proposed for management's consideration at Scott Inc. for the upcoming budget year: Use Table 6-4 and Table 6-5. (Use appropriate factor(s) from the tables provided. Round the PV factors to 4 decimals.) Project Year (s) D E $ (25,000) 5,000 5,000 5,000 5,000 5,000 5,000 $ 1,081 $ (25,000) $ (50,000) $ (50,000) 5,000 10,000 15,000 20,000 25,000 Initial investment $(100,000) 30,000 30,000 Amount of net cash return 16,000 16,000 16,000 16,000 16,000 10,000 15,000 10,000 10,000 6,000 15,000 15,000 5 Per year 6-10 15,000 NPV (14% discount rate) $ 2,942 Present value ratio 1.04 b. Calculate the present value ratio for projects B, C, D, and E. (Round your answers to 2 decimal places.) Project Present Value Ratio B D Earrow_forwardUse the information for the question(s) below. Project A - 10,000 Project B Time 0 - 10,000 Time 1 5,000 4,000 Time 2 4,000 3,000 Time 3 3,000 10,000 If WiseGuy Inc. uses IRR rule to choose projects, which of the projects (Project A or Project B) will rank highest? OA. Project A OB. Project B OC. Project A and Project B have the same ranking OD. Cannot calculate a payback period without a discount rate.arrow_forwardThe following information is available on two mutually exclusive projects. Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$700 $200 $300 $400 $500 B -$700 $600 $300 $200 $100 If the required rate of return is 10%, which project should be selected using the internal rate of return (IRR) method? Group of answer choices A Barrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education