Calculating ETC, EAC, and VAC in Project Management

.docx

School

Algonquin College *

*We aren’t endorsed by this school

Course

4100

Subject

Accounting

Date

Jun 13, 2024

Type

docx

Pages

7

Uploaded by PrivateHeatWolverine39

Exercise 2 VAC Option Question 1  (1 point)     Project A You are given the following data regarding the Earned Value results of a project.  There are no approved change orders for this project.  Calculate ETC, EAC and VAC. Budget $500,000 Duration 900 days Status 600 days EV $180,000 PV $150,000 AC $178,000 BAC =   Assume that future cost estimates are accurate and do not change.   1) ETC = 2) EAC =  3) VAC =  1) ETC = BAC - EV = $500,000 - $180,000 = $320,000 2) EAC = AC + ETC = $178,000 + $320,000 = $498,000 3) VAC = BAC - EAC = $500,000 - $498,000 = $2,000
Question 2  (1.5 points)   Project A You are given the following data regarding the Earned Value results of a project.  There are no approved change orders for this project.  Calculate ETC, EAC and VAC. Budget $500,000 Duration 900 days Status 600 days EV $180,000 PV $150,000 AC $178,000 BAC =   Assume the spend rate continues for the rest of the project future  1) ETC = 2) EAC =  3) VAC =  ETC = $320,000 existing budget CPI = EV/AC = $180,000/$178,000 = 1.0112 ETC at same spend rate = $320,000 / 1.011236 = $316,444 (round to nearest dollar) ETC = $316,444 (at current spend rate) EAC = AC + ETC = $178,000 + $316,444 = $494,444 VAC = BAC – EAC = $500,000 - $494,444 = $5,556
Question 3  (1 point)   Project B You are given the following data regarding the Earned Value results of a project.  There are no approved change orders for this project.  Calculate ETC, EAC and VAC. Budget $220,000 Duration 350 Status 240 EV $180,000 PV $180,000 AC $192,000 BAC =   Assume that future cost estimates are accurate and do not change.   1) ETC = 2) EAC =  3) VAC =  1) ETC = BAC - EV = $220,000 - $180,000 = $40,000 2) EAC = AC + ETC = $192,000 + $40,000 = $232,000 3) VAC = BAC - EAC = $220,000 - $232,000 = -$12,000 Question 4  (1.5 points)   Project B You are given the following data regarding the Earned Value results of a project.  There are no approved change orders for this project.  Calculate ETC, EAC and VAC.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help