OPERATIONS MANAGEMENT CUSTOM ACCESS
11th Edition
ISBN: 9780135622438
Author: KRAJEWSKI
Publisher: PEARSON EDUCATION (COLLEGE)
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter D, Problem 19P
A
Summary Introduction
Interpretation: The annual production quantity should be determined if the Company will be able to sell all that it can produce.
Concept Introduction: The Company produces different chemicals and solvents, particularly for the use of glue industry.
B
Summary Introduction
Interpretation: The lot size of each product, based on the given data and information should be determined.
Concept Introduction: The Company produces different chemicals and solvents, particularly for the use of glue industry.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Material Handling Systems
Case
Mfa Company operates a centrally located storeroom in their manufacturing complex. Every afternoon, each craft foreman (Tin Shop, Electric Shop, Iron Workers, etc.) writes a requisition for common use items include nuts, bolts, screws, washers, flashlight batteries, and gloves. All specialty items are ordered separately.
During the night shift, the storeroom personnel fill the orders items requested by the craft foreman. Each morning, one or two workers from each department to go the storeroom with a four –wheel platform truck to pick up the filled order.
Question:
Although studies have been performed to determine the amount of time craftsmen spend waiting the supplies, it is the thoughts of the management that idle craft manpower is a problem resulting from this procedure. How can time spent traveling and from the described storeroom be reduced, thus, eliminating or decreasing crafts’ personnel travel time?
) The following data have been prepared for master production scheduling purposes in IKEA Australia:
End product A: Beginning inventory of 60, Period forecast of 10, Lot size of 30, and 30 hours in lot size.
End product B: Beginning inventory of 20, Period forecast of 5, Lot size of 20, and 20 hours in lot size.
End product C: Beginning inventory of 30, Period forecast of 15, Lot size of 50, and 50 hours in lot size.
Capacity: 38 hours/ week
(i) Prepare the master production schedule for these items during the next four periods using the Ethan Allen master production scheduling method.
(ii) Suppose that the master production schedule is frozen for the next three periods. What specific impact would the policy have on the IKEA's performance?
The Ace Manufacturing Company has orders for three similar products.
Product
A
Min
B
C
1
2
Machine
3
Three machines are available for the manufacturing operations. All three machines can produce all the products at the same production rate. However, due to varying defect percentages of each product on each
machine, the unit costs of the products vary depending on the machine used. Machine capacities for the next week and the unit costs are shown below.
A
A
B
B
Ic
C
Product
1
12
3
Orders
(units)
1,900
500
1,100
Capacity
(units)
1,300
1,600
800
1
Machine
2
3
$1.00 $1.30 $1.10
$1.20 $1.40 $1.00
$0.90 $1.20 $1.20
(a) Develop the linear programming formulation of this problem. (Let XA1 be the number of units of product A produced by machine 1, X;; be the number of units of product i produced by machine j, etc.)
Chapter D Solutions
OPERATIONS MANAGEMENT CUSTOM ACCESS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Mr. Omar is a sales manager in Al Noor Company. He decided to drop the production of product A because he found that it is unprofitable. This is an advantage of:arrow_forwardGGG University consists of a number of departments. Each department offers several courses. A number of modules make up each course. Students enroll in a particular course and take modules towards the completion of that course. Each module is taught by a lecturer from the appropriate department, and each lecturer tutors a group of students Specify all needed tables from this case study Determine for each table the requested attributes and the needed primary keyarrow_forwardKala is one of the top manufacturer of ukuleles. The manufacturer produces three different types of ukuleles. Its Concert produce $6 in profit per unit; its Soprano produce $4 in profit per unit; and its Tenor produce $8 in profit per unit. Each type of ukulele passes through three manufacturing stages as a part of the entire production process. The three process centers of modelling, curing and assembly has an available production time per day of 12 hours, 14 hours and 16 hours, respectively. To produce one hundred units of Concert, the time required for the process of modelling, curing and assembly is 2 hours, 3 hours and 2 hours, respectively. To produce one hundred units of Soprano, 2 hours of modelling, 2 hours of curing and 1 hour of assembly is required. Whereas 4 hours of modelling, 2 hours of curing and 2 hours of assembly is required to produce one hundred units of Tenor. Sensitivity report of the problem is given as below where C = unit of Concert to be produced each day, S…arrow_forward
- h4q3barrow_forwardCompany ZWZ manufactures three products in a serial system; Product XA is manufactured in Stage 1, Product XB in Stage 2, and XC in Stage 3. Product XB has a sales potential in the market; hence, some of it can be sold at the end of Stage 2, and the remaining can be moved to Stage 3. The third stage produces Product XC, and then delivers it to customers. Two units of Product XA produced in Stage 1 are required for each unit of Product XB in Stage 2. In addition, four units of Product XB produced in Stage 2 are required for each unit of Product XC in Stage 3. Stage 1 can only use regular time; however, Stage 2 has the options of using regular time and overtime in manufacturing. On the other hand, Stage 3 has only one alternative, which is subcontracting. The pertinent data are provided below: Stage 2 Stage 1 11 No overtime No subcontracting No sales 0.07 Unit regular time cost (TL) Unit overtime cost (TL) Unit subcontracting cost (TL) Unit selling price (TL) Unit processing time (hrs)…arrow_forwardProduction and Materials Purchases Budgets White Corporation’s budget calls for the following sales for next year:Quarter 1 90,000 units Quarter 3 68,000 unitsQuarter 2 76,000 units Quarter 4 96,000 unitsEach unit of the product requires 3 pounds of direct materials. The company’s policy is to begineach quarter with an inventory of product equal to 5% of that quarter’s estimated sales requirementsand an inventory of direct materials equal to 20% of that quarter’s estimated direct materials requirements for production.Required Determine the production and materials purchases budgets for the second quarter.arrow_forward
- 33 White & Becker Tools (W&B) requires 2,000 elec- tric motors next month for its product line of weed trimmers. Each motor is composed of three com- ponents: a coil, a shaft, and housing. W&B has the capability to produce these components or purchase them from an outside vendor. The costs of produc- ing them and purchasing them are shown in the following table. COMPONENT Coil Shaft Housing DEPART- MENT PRODUCTION COST PER UNIT Fabrication 0.5 Molding 0.4 Inspection 0.2 $2.60 $1.80 $1.40 The components that are produced by W&B must pass through three departments: fabrication, molding, and inspection. The number of hours each component requires in each department and the total number of hours available next month in each department are shown in the following table: 0.2 0.7 0.3 PURCHASE COST PER UNIT COIL SHAFT HOUSING AVAILABILITY (HR.) (HR.) (HR.) (HR.) $3.12 $2.16 $1.68 0.6 0.3 0.4 3,000 3,000 1,800 In order to determine the number of components that will be produced and the number…arrow_forwardThe Ace Manufacturing Company has orders for three similar products. Product Min A s.t. B C 1 2 Machine 3 Three machines are available for the manufacturing operations. All three machines can produce all the products at the same production rate. However, due to varying defect percentages of each product on each machine, the unit costs of the products vary depending on the machine used. Machine capacities for the next week and the unit costs are shown below. A A LB B Ic C Product 4 2 3 Orders (units) Machine 1 Capacity Product A Orders Machine 2 Capacity Product B Orders Machine 3 Capacity Product C Orders 1,800 X20 for all i, j. 700 1,100 Capacity (units) 1,400 (a) Develop the linear programming formulation of this problem. (Let x₁ be the number of units of product A produced by XA1 machine 1, x,, be the number of units of product i produced by machine j, etc.) 1,500 1,000 1 Machine $1.00 $1.30 $1.10 2 $1.20 $1.40 $1.00 $0.90 $1.20 $1.20 3 (b) Solve the transportation model for the…arrow_forwardSpikLock makes several lines of metal items. The most recent order has been for 1200 door lock units for an apartment complex developer. The sales and production departments must work together to determine delivery schedules. Each lock unit consists of three components: the knob and faceplate, the actual lock itself, and a set of two keys. Although the processes used in the manufacture of the three components vary, there are three areas where the production manager is concerned about the availability of resources. These three areas, their usage by the three components, and their availability are detailed in the table. Resource Knob and Plate Lock Key (each) Available Brass Alloy 12 5 1 15000 units Machining 18 20 10 36000 minutes Finishing 15 5 1 12000 minutes A quick look at the amounts available confirms that SpikLock does not have the resources to fill this contract. A subcontractor, who can make an unlimited number of each…arrow_forward
- A manufacturer produces three models (I, II, and III) of a certain product using raw materials A and B. The labor time per unit model of I is twice that of Il and three times that of III. The entire labor force of the factory can produce the equivalent of 1500 units of Model I. Market requirements specify the ratios 3:2:5 for the production of the three respective models and minimum demand levels should be satisfied. Requirement Raw Material II Availability A 2 3 5 4000 В 4 2 7 6000 Minimum demand 200 200 150 Price per unit 30 20 50 The objective is to maximize the total revenue. a. Formulate a linear programming model for this problem. b. Discuss your findings in the context of assumptions of linear programming.arrow_forwardUse the following information to answer the question(s) below. Cerebro Manufacturing produces four types of structural support fittings-plugs, rails, rivets, and clips-which are machined on two CNC machining centers. The machining centers have a capacity of 250,000 minutes per year. The gross margin per unit and machining requirements are shown in the spreadsheet below. D E F 11 2 3 A Cerebro Manufacturing Model 6 17 8 Product 14 Gross margin/unit Minutes/unit 15 Gross margin/minute Maximum production Profit B O 125,000 O 250,000 O None of the above C Machine Rivets Clips Capacity (mins./year) Plugs Rails $0.40 $ 1.20 $0.80 $1.10 13 1.5 250,000 Assuming that one half of the machine capacity is used for the production of plugs. What is the maximum possible production of plugs based on this capacity? O 166,666.67 83,333.33arrow_forwardA9)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.