OPERATIONS MANAGEMENT CUSTOM ACCESS
11th Edition
ISBN: 9780135622438
Author: KRAJEWSKI
Publisher: PEARSON EDUCATION (COLLEGE)
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter D, Problem 17P
A
Summary Introduction
Interpretation:The objective functions and constrains should be determined.
Concept Introduction: The Company is the manufacturer of three types of components, processed on three machines.
B
Summary Introduction
Interpretation:Using a computer that has PON for Windows, the problem of the derived linear equations is to be solved.
Concept Introduction: The Company is the manufacturer of three types of components, processed on three machines.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
LENILOVESBATO Co. produces various types of floor rugs with many different designs. They typically produce at least 200 rugs with a single machine setup. A cost incurred each time a new rug design is developed is called a(n)
a. Unit-level cost
b. Batch-level cost
c. Product-level cost
d. Facility-level cost
In a large microelectronics plant, the assembly cell for circuit boards has a demand for 250 units an hour. Two feeder cells supply parts A and B to the assembly cell (one A and one B for each board). Standard containers that look like divided trays are used. A container will hold 24 As or 10 Bs. It takes 10 minutes to fill up a container with As and 24 minutes to fill up a container with Bs. Transit time to the assembly cell is 5 minutes for both A and B. No safety factor is used. Set up a kanban control system for the assembly process.
In order to produce 1000 units of X in a week units X is scheduled weekly for Operation B (due to 5% scrap ratio) units X is scheduled weekly for Operation A (due to 2% scrap ratio)
Based on your answer in part a, find the number of machines required to produce 1000 units of X per week. The total time required to perform Operation B = minutes per week The total time required to perform Operation A = minutes per week H= Available Time in a week = minutes /week Thus FA = . FB = . Since both of the operations A and B are performed on the same machine machines are required
Chapter D Solutions
OPERATIONS MANAGEMENT CUSTOM ACCESS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A manufacturing cell makes three models of a product – AKC1011, BC0001, and AC0102. The daily demand for the three products are as follows: 200 of AKC1011, 500 BC0001, and 300 of AC0102. Develop a balanced mixed-model sequence that should be repeated throughout the day in order to meet demand.arrow_forwardA company manufactures hair dryers. It buys some of the components, but it makes the heating elements, which it can produce at the rate of 800 per day. Hair dryers are assembled daily, 250 days a year, at a rate of 300 per day. Because of the disparity between the production and usage rates, the heating elements are periodically produced in batches of 2,000 units. Approximately how many batches of heating elements are produced annually? If production on a batch begins when there is no inventory of heating elements on hand, how much inventory will be on hand two days later? The same equipment that is used to make the heating elements could also be used to make a component for another of the firm’s products. That job would require four days, including setup. Setup time for making a batch of heating elements is a half day. Is there enough time to do this job between productions of batches of heating elements? Explain.arrow_forwardList the system of inequalities which describe B in the graph below.ECON1003 Mathematics for Social Sciences Unit 3_Version 1 Page 33 6. Anya’s Jeans has production process organized in threedistinct stages: cutting; sewing and finishing. She produces threetypes of jeans, namely peddle-pushers, hipsters and low cuts. Thenumber of minutes each type requires in each production processin shown below.Type Cutting Sewing FinishingPeddle-Pusher 4 6 2Hipster 6 7 4Low Rider 9 3 6On average, there are 6400 minutes of cutting time, 3500 minutes ofsewing time and 2400 minutes of finishing time each day. Given thatthe company makes $10 profit on each peddle-pusher $ 50 on eachhipster and $60 on each low cut and that the company sells all thejeans made. List the system of inequalities for the cutting, sewingand finishing constraints.arrow_forward
- In a large microelectronics plant, the assembly cell for circuit boards has a demand for 300 units an hour. Two feeder cells supply partsA and B to the assembly cell (one A and one B for each board). Standard containers that look like divided trays are used. A container will hold 22 As or 13 Bs. It takes 13 minutes to fill up a container with As and 22 minutes to fill up a container with Bs. Transit time to the assembly cell is 5 minutes for both A and B. No safety factor is used. Kanbans to be circulated Between Process A and Assembly cell? Kanbans to be circulated Between Process B and Assembly cell?arrow_forwardThe Delta company uses three raw materials to make cakes. Delta is trying to reduce warehousing costs and establishes three policies to that end: i) The annual number of orders for all products must be at least 20 per contractual terms with transportation providers. ii) The average inventory in units must be a maximum of 1800. iii) Because the raw material is perishable, there can never be more than 2000 units in inventory of raw material 1. Raw material 2 has a maximum allowed of 1200 units and the raw material 3 can store maximum 400 units. The following table shows the product information: Materia Demanda Costos por unidad Costo por prima (u/año) ordenar ($) 2200 2 300 2 500 4 650 3 3000 10 100 Consider an interest rate of 10% per year. A) Formulate the problem as a mathematical programming model that minimizes the total annual cost. b) Represent the problem in a single equation including the constraints in terms of lambda c) Find the optimized batch sizes for the company's raw…arrow_forwardPlainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 365 units/day Grey: 110 units/day Tan: 210 units/day The injection-molding machine can produce a total of 1,090 parts per day running 24 hours per day. It costs Plainwell $1,040 to set up each color for producition and the daily holding cost for each part is $0.49. What is the length of the lowest cost cyclic schedule (ignoring setup time constraints) in days?arrow_forward
- A company wants to store the following seven SKUs so there is 100% accessibility.Items are stored on pallets that are stored four high.a. How many pallet positions are needed?b. What is the cube utilization? c. If the company bought racking for storing the pallets, how many pallet positionsare needed to give 100% accessibility?arrow_forwardPlease Solve In 20minsarrow_forwardThe seasonal yield of olives in a Piraeus, Greece, vineyard is greatly influenced by a process of branch pruning. If olive trees are pruned every two weeks, output is increased. The pruning process, however, requires considerably more labor than permitting the olives to grow on their own and results in a smaller size olive. It also, though, permits olive trees to be spaced closer together. The yield of 1 barrel of olives by pruning requires 5 hours of labor and 1 acre of land. The production of a barrel of olives by the normal process requires only 2 labor hours but takes 2 acres of land. An olive grower has 250 hours of labor available and a total of 150 acres for growing. Because of the olive size difference, a barrel of olives produced on pruned trees sells for $20, whereas a barrel of regular olives has a market price of $30. The grower has determined that because of uncertain demand, no more than 40 barrels of pruned olives should be produced. Use graphical LP to find (a) the…arrow_forward
- 9Qarrow_forwardCrimson Wheels Bus Company produces buses. In order to produce the seats for the buses, special equipment must be set up. The setup cost per frame is $20. The cost of carrying seats in inventory is $5 per seat per year. The company produces 125,000 buses per year.The number of seats that should be produced per setup in order to minimize the total setup and carrying costs is: a.2,200 seats. b.1,920 seats. c.3,000 seats. d.1,000 seats.arrow_forwardMack’s guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 80 percent are considered good enough to sell. The other 20 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $300. Because some of the production process is automated, each guitar only requires 10 labor hours. Labor is paid at $10/hour, materials cost is $40/guitar, and overhead is $2,000. a) Calculate the labor and multifactor productivities. b) After some study, the operations manager recommends 3 options to improve the company’s multifactor productivity: (1) increase the sales price by 10 percent, (2) improve quality so that only 10 percent are defective, or (3) reduce labor, material, and overhead costs by 10 percent. Which option has the greatest impact on the multifactor productivity measure?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,