Chapter 9, Problem 13P
a)
Summary Introduction
To determine: The values of Cp and Cpk.
Introduction:
Process capability:
Process capability is the measure of repeatability of a process over and over with consistency in the manufacturing, relative to the requirements asked by the customer.
b)
Summary Introduction
To explain: Which of the indices is a better measure of process capability.
c)
Summary Introduction
To explain: By assuming
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A certain process is under statistical control and has a mean value of μ = 130 and a standard deviation of σ = 8. The specifications for this process are USL = 150, LSL = 100.a. Calculate Cp and Cpk.b. Which of these indices is a better measure of process capability? Why?c. Assuming a normal distribution, what percent of the output can be expected to fall outside the specifications?
The specification for a plastic liner for concrete highway projects calls for a thickness of 6.0 mm ± 0.1 mm. The standard deviation of the process is estimated to be 0.02 mm. What are the upper and lower specification limits for this product? The process is known to operate at a mean thickness of 6.03 mm. What is the Cp and Cpk for this process? About what percent of all units of this liner will meet specifications?
Please do not give solution in image formate thanku.
The specification for a plastic liner for concrete highway projects calls for a thickness of 6.0 mm ± 0.1 mm. The standard deviation of the process is estimated to be 0.02 mm. The process is known to operate at a mean thickness of 6.03 mm. What is the Cp and Cpk for this process? Determine whether this process meet 3-sigma requirements, 6-sigma requirements, or doesn’t meet any requirements.
Chapter 9 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Explain every optionarrow_forwardA machine is used to fill cans of motor oil additive. A single sample can is selected every hour and the net weight of the can is obtained. Since the filling process is automated, it has very stable variability, and long experience indicates that s = 0.02 oz. The process target (process mean when in control) is 8.02 oz. A tabular cusum is being used for this process with standardized values h=4.5 and k=0.5. If the values of Cumulative sums at the end of measurement 7 were C," + = 0.030 and C,¯ = 0.0 , and measurement 8 is equal to Xg = 8.071, what will be the Cumulative sum at the end of measurement 8, that is C3 + = ? 0.041 0.071 0.051 0.046 0.061arrow_forwardStudies on a machine that molds plastic water pipe indicate that when it is injecting1-inch diameter pipe, the process standard deviation is 0.05 inches. The one-inchpipe has a specification of 1-inch plus or minus 0.10 inch. What is the processcapability index (Cp) if the long-run process mean is 1 inch?arrow_forward
- A manufacturer is selling pharmaceuticals that have a weight specification 199.8 to 200.2 mg, with a target value of 200 mg. Before sending its next shipment, the company collects a large sample of product and determines the mean weight of the sample is 199.89 mg, with a standard deviation of 0.035 mg. The process capability index for the current process is ____. Round to three decimal places.arrow_forwardAssume the following: A quality manager at a popular restaurant in a New York has accurately measured the Cp & Cpk values associated with the delivery times of the food delivered by her restaurant. He has measured these values over an acceptable time period. The measured values are such that: Cp > 1, and Cpk < 1. Then: a. The process is both cappable and centered between the specification limits. b. The process is neither cappable nor centered between the specification limits. c. The process is cappable but not centered between the specification limits. d. The process is not cappable but centered between the specification limits.arrow_forwardanswer only if you can answer both.arrow_forward
- 2) The specification for a Lindemann’s stainless steel chimney liner requires a thickness of 7.1 mm ± 0.1 mm. The firm’s quality analyst determines that the liner process operates at a mean thickness of 7.13 mm with the standard deviation of the process being 0.02 mm. a) Calculate the upper and the lower limits for the stainless steel chimney liner. b) Calculate the Cpand Cpkfor this process. Hint: Cp = (Upper Specification Limit – Lower Specification Limit)/6sigma Cpk = minimum of [(Upper Specification Limit – Xbar)/3sigma], [(Xbar – Lower Specification Limit)/3sigma]arrow_forwardControl charts for x and R are maintained on a process. After 20 preliminary subgroups each of size 3 are evaluated, you have the following data: 3. 20 20 Ex, = 5,502 ER, = 60 a. Set up the control charts using these data. b. Assume that the process exhibits statistical control. Estimate the process mean and standard deviation. c. Suppose that the quality characteristic is normally distributed with specifications at 275 = 6. Estimate the fraction nonconforming produced by this process.arrow_forwardSpecifications for a part for a 3-D printer state that the part should weigh between 24 and25 ounces. The process that produces the parts has a mean of 24.5 ounces and a standard deviation of .2 ounce. The distribution of output is normal. What percentage of parts will not meet the weight specs? Within what values will 95.44 percent of the sample means of this process fall if samples of n = 16 are taken and the process is in control (random)? Using the control limits from part b, would the following sample means be in control? 24.52, 24.53, 24.44, 24.51, 24.41, 24.39 An automatic filling machine is used to fill 1-liter bottles of cola. The machine’s output is approxi- mately normal with a mean of 1.0 liter and a standard deviation of .01 liter. Output is monitored using means of samples of 25 observations. Determine upper and lower control limits that will include roughly 97 percent of the sample means when the process is in control. Given the following sample means—1.005,…arrow_forward
- Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor that must be controlled. From sample sizes of 10 pistons produced each day, the mean and the range of this diameter have been as follows: a) What is the value of x? x= 156.76 mm (round your response to two decimal places). b) What is the value of R? Day 1 2 3 4 5 Mean x (mm) 158.9 155.2 155.6 157.5 156.6 R = 4.40 mm (round your response to two decimal places). c) What are the UCL and LCL using 3-sigma? Upper Control Limit (UCL) = mm (round your response to two decimal places). Range R (mm) 4.2 4.4 4.3 4.8 4.3 Çarrow_forwardThe specifications for a gasket that installs between two engine parts calls for a thickness of 6.0 mm ± .2 mm. The standard deviation of the process is estimated to be 0.05 mm. The process is known to operate at a mean thickness of 6.1 mm What are the upper and lower specification limits for the gasket? What are the Cp and Cpk values for this process? Is this process capable of producing the desired part?arrow_forwardA process that produces computer chips has a mean of .04 defective chips and a standard deviation of .003 chips. The allowable variation is from .031 to .049 defective. a.Compute the capability index (C,) for the process. (Round your intermediate calculations to 3 decimal places and final answer to 2 decimal places.) Capability indexarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.