Chapter 8, Problem 3E

Compute the early, late, and slack times for the activities in the network that follows, assuming a time-constrained network. Which activities are critical? What is the time-constrained project duration?

Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project.

Assume you have only three resources and you are using a computer that uses software that schedules projects by the parallel method and following heuristics. Schedule only one period at a time!

Minimum slack

Smallest duration

Lowest identification number

Keep a log of each activity change and update you make each period—e.g., period 0-1, 1-2. 2-3, etc. (Use a format similar to the one on page 259.) The log should include any changes or updates in ES and slack times each period, activities scheduled, and activities delayed. (Hint: Remember to maintain the technical dependencies of the network.) Use the resource load chart to assist you in scheduling (see figures 8.4 and 8.5).

List the order in which you scheduled the activities of the project. Which activities of your schedule are now critical?

Recompute your slack for each activity given your new schedule. What is the slack for activity 1? 4? 5?

Chapter 8, Problem 3E, Compute the early, late, and slack times for the activities in the network that follows, assuming a , example  1

Chapter 8, Problem 3E, Compute the early, late, and slack times for the activities in the network that follows, assuming a , example  2

Blurred answer
Students have asked these similar questions
Which of the following circumstances justifies a lack of agenda? orivide correct answer and why The meeting is informal and routine. There wasn’t enough time. Agendas are not part of company culture. The meeting leader is exceptionally busy.
I need help answering the following questions below  What does succession planning entail and what are its essential steps? Are there any disadvantages to using a nine-box grid for succession planning? Would  having any difficulty in categorizing anyone who reports or has reported to you into one of the boxes? If you never managed a team, think about employees you have worked with in the past and how you would categorize them. Do most people frequently move from one box to another or do most people tend to stay in one box for long periods of their careers?
Please original work Background information: You are the chairman of the board for a large technology company. You are seeking a new CEO to replace your recently departed company founder. You are seeking an innovative leader for your organization. What do you think are the most important characteristics for the leader to have? Explain why each is important. How will you determine if an individual has those characteristics? Discuss how executives can ensure a successful fit. Please cite in text references and add weblinks
Knowledge Booster
Background pattern image
Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY