Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 8, Problem 1E
Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this happen in real projects?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now CRITICAL? What is the project duration now?
Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach wish (e.g., trial and error), develop a loading chart for resources Carpenters (C) and Electricians (E). Assume only one carpenter is available and two Electricians are available. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now?
4. Given the network plan that follows, compute
the early, late, and slack times. What is the
project duration? Using any approach you
wish (e.g., trial and error), develop a loading
chart for resource, electrical engineers (EE),
and resource, mechanical engineers (ME).
Assume only one of each resource exists.
Given your resource schedule, compute the
early, late, and slack times for your project.
Which activities are now critical? What is the
project duration now? Could something like
this happen in real projects?
Start
0 1
EE
2
0
02
EE
1
0
4
3
ME
3
I
4
EE
2 3 4 5 6
Fill in the times below for a resource activity schedule.
ID/RES ES LS EF LF SL
1-EE
2-EE
3-ME
4-EE
5-ME
6-ME
7-EE
11
Develop a loading schedule for each resource below. (Figure 8.3)
EE
ME
5
ME
6
6
ME
2
7 8 9
7
EE
4
10
11 12
Legend
ES ID EF
SL
SL
LS DURALF
End
Resource
Schedule
Chapter 8 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 8.1A - Explain how time is wasted in management of...Ch. 8 - How does resource scheduling reduce flexibility in...Ch. 8 - Prob. 5RQCh. 8 - Given the network plan that follows, compute the...Ch. 8 - Compute the early, late, and slack times for the...Ch. 8 - You have prepared the following schedule for a...Ch. 8 - You are one of three carpenters assigned to...Ch. 8 - Jack and Jill Smith have just retired and want to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- You are the project manager of the software installation project in Table. You would like to find the minimum- cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. a. What would be your target completion week? b. How much would you save in total project costs with your schedule?arrow_forwardProblem 1: For the network given below, (a) Draw the bar chart, resource histogram, and cumulative resource distribution for the early schedule. Make comments about potential problems concerning resource utilization in this project. (b) Following your intuition, what can be done to improve the resource utilization? Do not delay the finish date of the project. Support your solution. (c) Assuming that the resource availability is limited not to exceed 8 units at any time of the project, what has to be done to maintain this condition? The project can be delayed only if necessary. Support your solution. A-2 B-3 3 D-8 5 E-0 F-7 4 G-2 H-7 8 ESD J-3 2 LSD Activity-resource duration EED (TF, FF) LFDarrow_forwardBased on the Figure 6.6 What are the benefits and decisions Project managers can take?arrow_forward
- Can you provide a clear drawing and step by step explanation?arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______arrow_forwardFarihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forward
- The director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administra assistant identified the various activities that must be done and their relationships to each other, as shown in the following table: Click the icon to view the activities. Because of the uncertainty in planning the new course, the assistant also has supplied the following time estimates for each acti Click the icon to view the time estimates. The director wants to conduct the seminar 46 working days from now. What is the probability that everything will be ready in time the standard normal table. (Make sure to round all intermediate calculations for t, and variance to two decimal places) The probability that the seminar will be ready in time is 0.8643]. (Enter your response rounded to four decimal places.)arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A (BCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. B A, D с E, F Activity A B CDEFG Slack Time Time (days) 3 GANGG 5 2 10 4 8arrow_forwardConsider the PERT/CPM network below: The activity/task times are given in weeks: Fill in the blank with the correct answer: The estimated time of completion is _________ weeks.arrow_forward
- A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. Description Survey Soils report C Traffic design D Lot layout E Approve design Illumination G Drainage H Landscape I Signage J Bid proposal ID A B The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 13 22 21 a 9 74 20 20 22 17 15 12 days. day(s).arrow_forward"A large Southeast city is requesting federal funding for a park-and-ride project.One of the requirements in the request application is a network plan for the designphase of the project. Sophie Kim, the chief engineer, wants you to develop a proj.ect network plan to meet this requirement. She has gathered the activity time esti-mates and their dependencies shown here. Show your project network with theactivity early, late, and slack times. Mark the critical path.arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEFG с This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. Activity A B C ס ח ד 0 F B A, D C E, F G Slack Time Time (days) 4 6 1 103510arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY