Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 7, Problem 32P

a

Summary Introduction

Interpretation:

Expected completion time of project.

Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

a

Expert Solution
Check Mark

Explanation of Solution

Calculate the estimated task time:

    TaskImmediate predecessorsOptimistic timeMost likely timePessimistic timeEstimated task timeVariance
    ANone12320.11
    BA24640.44
    CNone24640.44
    DB and C12931.78

Calculate the estimated task time for task A:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskA=Optimistic+(4×Mostlikely)+Pessimistic6=1hour+(4×2hours)+3hour6=12hours6=2hours

Hence, the estimated task time for task A is 2 hours.

Calculate the estimated task time for task B:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskB=Optimistic+(4×Mostlikely)+Pessimistic6=2hour+(4×4hours)+6hour6=24hours6=4hours

Hence, the estimated task time for task B is 4 hours.

Calculation of estimated task time for Task C:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskC=Optimistic+(4×Mostlikely)+Pessimistic6=2hour+(4×4hours)+6hour6=24hours6=4 hours

Hence, the estimated task time for Task C is 4 hours.

Calculate the estimated task time for Task D:

It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.

  EstimatedtasktimeofTaskD=Optimistic+(4×Mostlikely)+Pessimistic6=1hour+(4×2hours)+9hours6=18hours6=3hours

Hence, the estimated task time for task D is 3 hours.

Calculate the variance for Task A:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskA=(PessimisticOptimistic6)2

  VarianceofTaskA=(3hour1hour6)2=(2hour6)2=0.11

Calculate the variance for Task B:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskB=(PessimisticOptimistic6)2

  VarianceofTaskD=(6hour2hour6)2=(4hour6)2=0.44

Hence, the variance for task B is 0.44

Calculate the variance for Task C:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskD=(6hour2hour6)2=(4hour6)2=0.44

Hence, the variance for Task C is 0.44

Calculate the variance for Task D:

It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.

  VarianceofTaskD=(PessimisticOptimistic6)2

  VarianceofTaskD=(9hour1hour6)2=(8hour6)2=1.78

Hence, the variance for Task D is 1.78

Project network diagram for given information:

The below image shows the project network with the early start, early finish, late start and late finish:

  Practical Operations Management, Chapter 7, Problem 32P

A

The critical path in the project network:

The paths in the given project network are as follows:

A-B-D

C-D

There are two paths in the project network.

Out of the above-mentioned path, the path has the equal early start and late start at the same time early finish and late finish are the critical path.

Hence, the critical path is A-B-D and the project completion time is 9 days.

b

Summary Introduction

Interpretation:

Time duration in the beginning of reconfiguration.

Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.

b

Expert Solution
Check Mark

Explanation of Solution

The late start time for activity C:

According to the project network, the late start time for activity C is 2 day.

c

Summary Introduction

Interpretation:

Probability that warehouse will finish the project.

Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.

c

Expert Solution
Check Mark

Explanation of Solution

The probability to finish the operation, which started at 1:00 a.m. and finished at 11:00 a.m. on the same day:

The value of Z should be calculated to find the probability to find the operation.

It is calculated by dividing the value attained by subtracting the completion time from the time (time gap from 1:00 a.m. to 11:00 a.m.) with the square root of the variance of critical path (sum of the variance of critical path).

  Z=Time-CompletiontimeVarianceofcriticalpath

  Z=10hour-9hour0.11+0.44+1.78=1hour2.33=0.6551

Hence, the value of Z is 0.6551

For Z= 0.6551, the normal distribution table value is 0.7422. Thus, the probability is 74%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simplex Method  Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup.  1. Determine the optimum number of types of paints to be manufactured. 2.      Determine the optimal utility value.
The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY