Concept explainers
a
Interpretation:
Expected completion time of project.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
a
Explanation of Solution
Calculate the estimated task time:
Task | Immediate predecessors | Optimistic time | Most likely time | Pessimistic time | Estimated task time | Variance |
A | None | 1 | 2 | 3 | 2 | 0.11 |
B | A | 2 | 4 | 6 | 4 | 0.44 |
C | None | 2 | 4 | 6 | 4 | 0.44 |
D | B and C | 1 | 2 | 9 | 3 | 1.78 |
Calculate the estimated task time for task A:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task A is 2 hours.
Calculate the estimated task time for task B:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task B is 4 hours.
Calculation of estimated task time for Task C:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for Task C is 4 hours.
Calculate the estimated task time for Task D:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task D is 3 hours.
Calculate the variance for Task A:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Calculate the variance for Task B:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for task B is 0.44
Calculate the variance for Task C:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for Task C is 0.44
Calculate the variance for Task D:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for Task D is 1.78
Project network diagram for given information:
The below image shows the project network with the early start, early finish, late start and late finish:
A
The critical path in the project network:
The paths in the given project network are as follows:
A-B-D
C-D
There are two paths in the project network.
Out of the above-mentioned path, the path has the equal early start and late start at the same time early finish and late finish are the critical path.
Hence, the critical path is A-B-D and the project completion time is 9 days.
b
Interpretation:
Time duration in the beginning of reconfiguration.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
b
Explanation of Solution
The late start time for activity C:
According to the project network, the late start time for activity C is 2 day.
c
Interpretation:
Probability that warehouse will finish the project.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
c
Explanation of Solution
The probability to finish the operation, which started at 1:00 a.m. and finished at 11:00 a.m. on the same day:
The value of Z should be calculated to find the probability to find the operation.
It is calculated by dividing the value attained by subtracting the completion time from the time (time gap from 1:00 a.m. to 11:00 a.m.) with the square root of the variance of critical path (sum of the variance of critical path).
Hence, the value of Z is 0.6551
For Z= 0.6551, the
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- i). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.arrow_forwardIn the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why. ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.arrow_forwardi). Complete the table for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible. You should support your answer with numerical data derived from Table 3. In comparing the costs, state any other assumptions made.arrow_forward
- i). Complete for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible.arrow_forwardComplete the table for a Chase production plan.arrow_forwardHow much can the garden centre expect to sell during each quarter of next year (Year 3) accounting for seasonality? Your forecast must make use of seasonal indices. All workings must be shown in full. (NOTE: Please round your calculations to three decimal places).arrow_forward
- PS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forwardTisjTzktxyduduarrow_forwardNot use ai pleasearrow_forward
- Not use ai pleasearrow_forwardWhat is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impactarrow_forward419 X .com/courses/1546/assignments/49499?module_item_id=111573 Unlimited Attempts Allowed ✓ Details Directions: Record a video of yourself giving a business presentation. Imagine you are tasked with researching a professional development topic on business communication for 40 coworkers. You are then expected to give a 4 - 5 minute presentation on the topic. Choose any topic related to business communication, such as intercultural communication, effective leadership, professional writing, etc. Research the topic and prepare a 4 - 5 minute presentation that could be given over video conference call (such as Zoom). You may use visual aids if you choose. Upload a video file of your presentation. Provide all needed citations. Requirements: 4-5 minutes long Contains visual and audio Create your own work; do not plagiarize Cite your sources using APA citations Choose a submission type Tarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,