
Concept explainers
a
Interpretation:
Expected completion time of project.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
a

Explanation of Solution
Calculate the estimated task time:
Task | Immediate predecessors | Optimistic time | Most likely time | Pessimistic time | Estimated task time | Variance |
A | None | 1 | 2 | 3 | 2 | 0.11 |
B | A | 2 | 4 | 6 | 4 | 0.44 |
C | None | 2 | 4 | 6 | 4 | 0.44 |
D | B and C | 1 | 2 | 9 | 3 | 1.78 |
Calculate the estimated task time for task A:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task A is 2 hours.
Calculate the estimated task time for task B:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task B is 4 hours.
Calculation of estimated task time for Task C:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for Task C is 4 hours.
Calculate the estimated task time for Task D:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task D is 3 hours.
Calculate the variance for Task A:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Calculate the variance for Task B:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for task B is 0.44
Calculate the variance for Task C:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for Task C is 0.44
Calculate the variance for Task D:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for Task D is 1.78
Project network diagram for given information:
The below image shows the project network with the early start, early finish, late start and late finish:
A
The critical path in the project network:
The paths in the given project network are as follows:
A-B-D
C-D
There are two paths in the project network.
Out of the above-mentioned path, the path has the equal early start and late start at the same time early finish and late finish are the critical path.
Hence, the critical path is A-B-D and the project completion time is 9 days.
b
Interpretation:
Time duration in the beginning of reconfiguration.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
b

Explanation of Solution
The late start time for activity C:
According to the project network, the late start time for activity C is 2 day.
c
Interpretation:
Probability that warehouse will finish the project.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
c

Explanation of Solution
The probability to finish the operation, which started at 1:00 a.m. and finished at 11:00 a.m. on the same day:
The value of Z should be calculated to find the probability to find the operation.
It is calculated by dividing the value attained by subtracting the completion time from the time (time gap from 1:00 a.m. to 11:00 a.m.) with the square root of the variance of critical path (sum of the variance of critical path).
Hence, the value of Z is 0.6551
For Z= 0.6551, the
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- Hyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,600 B C $2,000 $1,100 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardHyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,500 B C $2,100 $1,050 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardThe importance of keeping track of invoices and budgeting in a nursing home kitchen and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forward
- The importance of interviewing potential food service aides and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forwardWhat role does job analysis and job evaluation play in the compensation decision? Give an example of an organization NO AIarrow_forwardI did the first half correct! Please help me with the second half, not quite sure of the naive approach. Thanks in advance!arrow_forward
- Because my tutor and I didnt get it rightarrow_forwardOperations Managementarrow_forwardHow does wellness reflect and impact the past and the future of our health as a workout routine? What are the obstacles during the workout routine, and how do you overcome the obstacles? What are the best solutions to plan and accomplish the wellness?arrow_forward
- My last question! Thank you all for helping me better understand how OM works. If you can assist me for this one I'd be very thankful. Can you explain it step by step?I know now that LS is late start, and ES is early start. - •Activities on the critical path are? •The total project completion time for Rafay Ishfaq's software firm is how many weeks?•Determine the slack time for each of the activities for A-F •What is the total slack for the non critical paths in Rafays project?arrow_forwardThank you so much! I was able to answer C without help! Can you assist me with slack time for A-F? I believe A=0arrow_forwardThere's 8 parts, but I need some help with them. I always get confused on which is most critical of a patharrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
