Interpretation: The expected time and variance in task A is to be calculated.
Concept Introduction:
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.

Explanation of Solution
The estimated task time can be computed by adding optimistic time, mostly likely time multiplied by 4, and pessimistic time. Then, divide the attained value with 6. The optimistic time is 3 days, mostly likely time is 4 days, and pessimistic time is 10 days of task A.
Hence, the estimated time in task A is 4.8 days
Variance in task time:
The variance in task time computed by deducting optimistic time from pessimistic time and divided by six. Then, completely square the attained value. The optimistic time is 3 days, and pessimistic time is 10 days of task A.
Hence, the variance in task A time is 1.36 days.
The project management has two techniques that is critical path method and program Evaluation Review technique. In program evaluation review technique the project’s optimistic time, mostly likely time, and pessimistic time are combined together in to single expected value. This expected value signifies expected time of project’s task.
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- Hyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,600 B C $2,000 $1,100 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardHyundai Motors is considering three sites-A, B, and C-at which to locate a factory to build its new electric car batteries. The goal is to locate at a minimum-cost site, where cost is measured by the annual fixed plus variable costs of production. Hyundai Motors has gathered the following data: Site Annualized Fixed Cost Variable Cost per Battery Produced A $11,000,000 $2,500 B C $2,100 $1,050 $20,000,000 $25,000,000 The firm knows it will produce between 0 and 60,000 batteries at the new plant each year, but, thus far, that is the extent of its knowledge about production plans. a) The value of volume, V, of production above which site C is recommended = batteries (round your response up to the next whole number).arrow_forwardThe importance of keeping track of invoices and budgeting in a nursing home kitchen and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forward
- The importance of interviewing potential food service aides and how can a nutritionist utilize this in their career? Please not just a short explanation.arrow_forwardWhat role does job analysis and job evaluation play in the compensation decision? Give an example of an organization NO AIarrow_forwardI did the first half correct! Please help me with the second half, not quite sure of the naive approach. Thanks in advance!arrow_forward
- Because my tutor and I didnt get it rightarrow_forwardOperations Managementarrow_forwardHow does wellness reflect and impact the past and the future of our health as a workout routine? What are the obstacles during the workout routine, and how do you overcome the obstacles? What are the best solutions to plan and accomplish the wellness?arrow_forward
- My last question! Thank you all for helping me better understand how OM works. If you can assist me for this one I'd be very thankful. Can you explain it step by step?I know now that LS is late start, and ES is early start. - •Activities on the critical path are? •The total project completion time for Rafay Ishfaq's software firm is how many weeks?•Determine the slack time for each of the activities for A-F •What is the total slack for the non critical paths in Rafays project?arrow_forwardThank you so much! I was able to answer C without help! Can you assist me with slack time for A-F? I believe A=0arrow_forwardThere's 8 parts, but I need some help with them. I always get confused on which is most critical of a patharrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,