Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 7, Problem 18P
Summary Introduction

Interpretation: The expected time and variance in task A is to be calculated.

Concept Introduction:

PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.

Expert Solution & Answer
Check Mark

Explanation of Solution

The estimated task time can be computed by adding optimistic time, mostly likely time multiplied by 4, and pessimistic time. Then, divide the attained value with 6. The optimistic time is 3 days, mostly likely time is 4 days, and pessimistic time is 10 days of task A.

  Varianceintasktime=(7days6)2=(1.1667days)2=1.36days

  Estimatedtime=4.8days

  Estimatedtime=3days+16days+10days6

  Estimatedtime=29days6

  Estimatedtime=4.8days

Hence, the estimated time in task A is 4.8 days

Variance in task time:

The variance in task time computed by deducting optimistic time from pessimistic time and divided by six. Then, completely square the attained value. The optimistic time is 3 days, and pessimistic time is 10 days of task A.

  Varianceintasktime=(Pessimistictime-Optimistictime6)2

  Varianceintasktime=(10days-3days6)2

  Varianceintasktime=(7days6)2=(1.1667days)2=1.36days

Hence, the variance in task A time is 1.36 days.

The project management has two techniques that is critical path method and program Evaluation Review technique. In program evaluation review technique the project’s optimistic time, mostly likely time, and pessimistic time are combined together in to single expected value. This expected value signifies expected time of project’s task.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simplex Method  Three types of paints are manufactured in one machine; Interior paint, Exterior paint and Paint for metal structures. The preparation time for each type of paint is 2, 3 and 4 minutes respectively and the processing time is 3, 2 and 1 minute. The profit contributed by each product is 12, 10 and 15 dollars respectively. The machine availability is 100 minutes and 200 minutes for machine setup.  1. Determine the optimum number of types of paints to be manufactured. 2.      Determine the optimal utility value.
The company LED S.A DE C.V. produces 2 devices for lamps, devices 1 and 2 that require metal parts and electrical parts. The manager wants to determine how many units of each product should be manufactured to maximize the profit for each unit, device 1 requires 2 metal parts and 4 electrical parts, device 2 requires 4 metal parts and 2 electrical parts, the company has 24 units of each material available for batch production, device 1 generates $4 profit and device 2 generates $6 profit. a) Formulate PL model. b) Solve by the graphical method and determine what is the resulting maximum profit. Translated with DeepL.com (free version)
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY