Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 7, Problem 31P

a

Summary Introduction

Interpretation:

Critical path of this network.

Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

a

Expert Solution
Check Mark

Explanation of Solution

Project network diagram for given information:

The below image shows the project network with the early start, early finish, late start and late finish:

  Practical Operations Management, Chapter 7, Problem 31P

The critical path in the project network:

The paths in the given project network are as follows:

A-E-J

A-C-F

B-D-G-I-J

B-D-H-I-J

There are four paths in the project network.

Out of the above mentioned path, the path that has the equal early start and late start at the same time early finish and late finish are the critical path.

Here two paths are satisfying the above condition, which are as follows:

A-C-F

B-D-H-I-J

When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.

Hence, the critical path is B-D-H-I-J.

b

Summary Introduction

Interpretation:

Completion time of the project.

Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.

Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.

b

Expert Solution
Check Mark

Explanation of Solution

When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.

A-C-F

B-D-H-I-J

Hence, the critical path is B-D-H-I-J.

As the critical path is determined as B-D-H-I-J, the project completion time is 11 days.

c

Summary Introduction

Interpretation:

The slack of activity A.

Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

c

Expert Solution
Check Mark

Explanation of Solution

The slack of the activity is calculated by subtracting the early start from the late finish.

  Slackoftheactivity=Latefinish-Earlyfinish=1-1=0

Hence, the slack of activity A is 0.

d

Summary Introduction

Interpretation:

Task to be crashed and its cost.

Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.

d

Expert Solution
Check Mark

Explanation of Solution

The cost of crashing.

It is given that the paths should be crashed and the total time of the path should not exceed 8 days. The cost to crash Activity B is $500 per crash, Activity H is $200 per crash, and all eligible activities are $100 per crash.

Use the following steps to crash the activities:

The paths and the total task time to complete the path within 8 days is shown below:

Path A-E-J:

Total task time is calculated by adding the duration of all the activities in the path.

  Totaltasktime=DurationofActivityA+DurationofActivityE+DurationofActivityJ=1day+7days+1day=9days

Hence, the total task time is 9 days. It exceeds 8 days. Thus, the path should be crashed. Activity A and Activity J cannot be crashed as the duration is 1. Activity E should be crashed from 7 days to 6 days.

  Modifiedtotaltasktime=(DurationofactivityA+DurationofactivityE+DurationofactivityJ)

  =1day+2days+1day=4days

Hence, the total task time is 4 days. It does not exceed 8 days. Thus, the path cannot be crashed.

Path B-D-G-I-J:

Total task time is calculated by adding the duration of all activities in the path.

  Totaltasktime=(DurationofactivityB+DurationofactivityD+DurationofactivityG+DurationofactivityI+DurationofactivityJ)

  =4days+2days+2days+1day+1day=10days

Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity D and Activity G can be crashed from 2 days to 1 day.

  ModifiedTotaltasktime=(DurationofactivityB+DurationofactivityD+DurationofactivityG+DurationofactivityI+DurationofactivityJ)

  =4days+1day+1day+1day+1day=8days

The cost for crashing is $200 as the crashing was done for two days in Activity D and Activity G. It is given that the activities except for Activity B and H cost $100 per day.

Path B-D-H-I-J

Total task time is calculated by adding the duration of all the activities in the path.

  Totaltasktime=(DurationofactivityB+DurationofactivityD+DurationofactivityH+DurationofactivityI+DurationofactivityJ)

  =4days+1day+3days+1day+1day=10days

Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. Activity I, Activity D (crashed in the previous step), Activity J cannot be crashed as the duration is 1 day. Activity B can be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity H can be crashed from 3 days to 2 days.

  Modifiedtotaltasktime=(DurationofactivityB+DurationofactivityD+DurationofactivityG+DurationofactivityI+DurationofactivityJ)

  =4days+1day+1day+1day+1day=8days

The cost for crashing is $400 as the crashing was done for two days in Activity H. It is given Activity H costs $100 per day.

Total crashing cost:

Total crashing cost is calculated by adding all the crashing cost done in the previous steps.

  Totalcrashingcost=(CrashingccostofpathAEJ+CrashingcostofpathBDGIJ+CrashingcostofpathBDHIJ)

  =$100+$200+$400=$700

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The global marketplace has undergone a dramatic transformation, demanding that businesses adapt their supply chain management and implement new strategies to ensure the reliable sourcing of materials and goods. Please choose an organisation that you are currently working for or you are familiar with where its procurement operations has been greatly affected. You may pick a commercial or public institution as a choice for your study. You will need to briefly describe the institution and explain its category management structure which support the strategic procurement. You are required to provide an overview and discuss how spend are identified along with the types of categories purchased Briefly describe the organisation that you have chosen. Analyse the criticality of both the category management and strategic sourcing that will impact the business needs of the institution that you have chosen. Laing oxemples from the institution you have selected appraise and recommend CO
The Ideal Spot in the Segment Circles So, where should you try to position your product in the segment circles? As a basic rule, the 'Ideal Spot' will help guide you. The ideal spot represents the position with the highest point of demand for each consumer base – or segment.  The ideal spot is made up by the product’s performance (speed) and size. As the perceptual map drifts down and to the right each year, the ideal spot will change as customers demand sensors with decreased size (smaller) and increased performance (faster). Although it would seem that the Ideal Spot would be in the center of the segment circle, the positioning actually varies due to the customer focus of each segment. For example, in the High End segment, the Ideal Spot is at the leading edge of the segment because those customers want the best possible product. Each segment’s ideal spot is represented by the pink dots on the Perceptual Map.  Ideal Spots offset from segment center Calculating the Ideal Spot To…
In Ecuador, cut roses are one of the country’s leading exports. Prior to advancements in the air transportation industry, this would have been impossible as roses must be sold within three to five days once cut. Today Ecuador is one of the world’s top producers of roses.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY