Concept explainers
a
Interpretation:
Critical path of this network.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
a
Explanation of Solution
Project network diagram for given information:
The below image shows the project network with the early start, early finish, late start and late finish:
The critical path in the project network:
The paths in the given project network are as follows:
A-E-J
A-C-F
B-D-G-I-J
B-D-H-I-J
There are four paths in the project network.
Out of the above mentioned path, the path that has the equal early start and late start at the same time early finish and late finish are the critical path.
Here two paths are satisfying the above condition, which are as follows:
A-C-F
B-D-H-I-J
When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.
Hence, the critical path is B-D-H-I-J.
b
Interpretation:
Completion time of the project.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
b
Explanation of Solution
When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.
A-C-F
B-D-H-I-J
Hence, the critical path is B-D-H-I-J.
As the critical path is determined as B-D-H-I-J, the project completion time is 11 days.
c
Interpretation:
The slack of activity A.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
c
Explanation of Solution
The slack of the activity is calculated by subtracting the early start from the late finish.
Hence, the slack of activity A is 0.
d
Interpretation:
Task to be crashed and its cost.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
d
Explanation of Solution
The cost of crashing.
It is given that the paths should be crashed and the total time of the path should not exceed 8 days. The cost to crash Activity B is $500 per crash, Activity H is $200 per crash, and all eligible activities are $100 per crash.
Use the following steps to crash the activities:
The paths and the total task time to complete the path within 8 days is shown below:
Path A-E-J:
Total task time is calculated by adding the duration of all the activities in the path.
Hence, the total task time is 9 days. It exceeds 8 days. Thus, the path should be crashed. Activity A and Activity J cannot be crashed as the duration is 1. Activity E should be crashed from 7 days to 6 days.
Hence, the total task time is 4 days. It does not exceed 8 days. Thus, the path cannot be crashed.
Path B-D-G-I-J:
Total task time is calculated by adding the duration of all activities in the path.
Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity D and Activity G can be crashed from 2 days to 1 day.
The cost for crashing is $200 as the crashing was done for two days in Activity D and Activity G. It is given that the activities except for Activity B and H cost $100 per day.
Path B-D-H-I-J
Total task time is calculated by adding the duration of all the activities in the path.
Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. Activity I, Activity D (crashed in the previous step), Activity J cannot be crashed as the duration is 1 day. Activity B can be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity H can be crashed from 3 days to 2 days.
The cost for crashing is $400 as the crashing was done for two days in Activity H. It is given Activity H costs $100 per day.
Total crashing cost:
Total crashing cost is calculated by adding all the crashing cost done in the previous steps.
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- The results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value. Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be includedarrow_forwardi). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.arrow_forwardIn the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why. ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.arrow_forward
- i). Complete the table for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible. You should support your answer with numerical data derived from Table 3. In comparing the costs, state any other assumptions made.arrow_forwardi). Complete for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible.arrow_forwardComplete the table for a Chase production plan.arrow_forward
- How much can the garden centre expect to sell during each quarter of next year (Year 3) accounting for seasonality? Your forecast must make use of seasonal indices. All workings must be shown in full. (NOTE: Please round your calculations to three decimal places).arrow_forwardPS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forwardTisjTzktxyduduarrow_forward
- Not use ai pleasearrow_forwardNot use ai pleasearrow_forwardWhat is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impactarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,