Concept explainers
a
Interpretation:
Critical path of this network.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
a
Explanation of Solution
Project network diagram for given information:
The below image shows the project network with the early start, early finish, late start and late finish:
The critical path in the project network:
The paths in the given project network are as follows:
A-E-J
A-C-F
B-D-G-I-J
B-D-H-I-J
There are four paths in the project network.
Out of the above mentioned path, the path that has the equal early start and late start at the same time early finish and late finish are the critical path.
Here two paths are satisfying the above condition, which are as follows:
A-C-F
B-D-H-I-J
When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.
Hence, the critical path is B-D-H-I-J.
b
Interpretation:
Completion time of the project.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
b
Explanation of Solution
When the network has more than one critical path, the path, which has the maximum project completion time, should be selected.
A-C-F
B-D-H-I-J
Hence, the critical path is B-D-H-I-J.
As the critical path is determined as B-D-H-I-J, the project completion time is 11 days.
c
Interpretation:
The slack of activity A.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
c
Explanation of Solution
The slack of the activity is calculated by subtracting the early start from the late finish.
Hence, the slack of activity A is 0.
d
Interpretation:
Task to be crashed and its cost.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
d
Explanation of Solution
The cost of crashing.
It is given that the paths should be crashed and the total time of the path should not exceed 8 days. The cost to crash Activity B is $500 per crash, Activity H is $200 per crash, and all eligible activities are $100 per crash.
Use the following steps to crash the activities:
The paths and the total task time to complete the path within 8 days is shown below:
Path A-E-J:
Total task time is calculated by adding the duration of all the activities in the path.
Hence, the total task time is 9 days. It exceeds 8 days. Thus, the path should be crashed. Activity A and Activity J cannot be crashed as the duration is 1. Activity E should be crashed from 7 days to 6 days.
Hence, the total task time is 4 days. It does not exceed 8 days. Thus, the path cannot be crashed.
Path B-D-G-I-J:
Total task time is calculated by adding the duration of all activities in the path.
Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity D and Activity G can be crashed from 2 days to 1 day.
The cost for crashing is $200 as the crashing was done for two days in Activity D and Activity G. It is given that the activities except for Activity B and H cost $100 per day.
Path B-D-H-I-J
Total task time is calculated by adding the duration of all the activities in the path.
Hence, the total task time is 10 days. It exceeds 8 days. Thus, the path should be crashed. Activity I, Activity D (crashed in the previous step), Activity J cannot be crashed as the duration is 1 day. Activity B can be crashed. However, it costs $500 to crash one day of Activity B. Thus, Activity H can be crashed from 3 days to 2 days.
The cost for crashing is $400 as the crashing was done for two days in Activity H. It is given Activity H costs $100 per day.
Total crashing cost:
Total crashing cost is calculated by adding all the crashing cost done in the previous steps.
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- From the following data, calculate BAC, BCWS, BCWP, ACWP, EV, CV and SV when the Status Checking Date is May 5, 2017. Is the project over or under budget? By what percentage? Is the project behind or ahead of schedule? By what percentage? Project Status Status Checking Date 5/5/2017 Actual Effort Estimated Actual Completion Estimated Work Effort by Status Checking Date Completion Date Tasks Date (mm/dd/yy) (mm/dd/yy) (Person Days) (Person Days) 10 2/5/2017 2/5/2017 15 20 3/15/2017 3/25/2017 20 25 4/25/2017 4. 25 25 5/5/2017 4/1/2017 15 10 5/25/2017 10 5 6/10/2017 7 5 6/15/2017 HTML Editor 2. 3. 5.arrow_forwardI need solve this question in project managerarrow_forwardA project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000arrow_forward
- Using the data provided in the picture added Draw a network for the work package showing the activities, critical path and package duration. Assume the client wishes the package to be completed within 32 weeks. Calculate the most cost effective way of completing the package within this time, giving the cost increase associated with this crash sequence. You should start with the activity with the lowest cost per unit crash time and progress to the activity with the highest cost per unit crash time. Assume liquidated and ascertained damages apply at a rate of GBP 30,000 per week for completion later than the end of week 32. Balancing crash costs against damages costs, calculate the duration that gives the lowest total project cost.arrow_forwardyou can solve it on table and i will copy itarrow_forwardI'm unable to answer the following question? What is the total cost of crashing the project from its current duration down to 13 weeks?arrow_forward
- Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Activity NormalTime(weeks) NormalCost ($) CrashTime(weeks) CrashCost ($) MaximumweeksReduced CrashCost perWeek ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,286 3 162.00 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 0 G 7 1,500 5 1,794 2 147 H 3 500 3 500 0 0 Reduce G by select a number of (1-4) week(s), C by select a number (1-4) of week(s), at a cost of $ __________ enter a dollar amount .arrow_forwardOnly part D is needed to be solved.arrow_forwardPlease solve my Problem as Soon as possible. Thank You!arrow_forward
- We are planning to develop a room reservation system that is estimated to have 400 story points of features. Let’s say our team’s velocity on two-week sprints ranges between 20 and 25 story points. Our project will start on Dec 1, 2021. If our customer wants the project to be in production by end of June 22, how likely will the project be successful? Why? Show your calculations.arrow_forwardManagement & Science University (MSU) have appointed you as a project manager to conduct a Joint Application Design (JAD) session with members from various departments. As a project manager, you are required to develop a specific schedule for the tasks listed below. The estimated task duration for each shown in parentheses. First, you must contact and brief the participants and explain their responsibilities (1 day). Then you must obtain approval from their department managers (3 days). After you have obtained the approval, you can begin the two tasks where you can prepare the agenda for the JAD session (7 days) and arrange the meeting room (2 days) When the agenda is ready, you can start two more concurrent tasks which are preparing the information packets (4 days) and to create visual aids (8 days). When the meeting room is arranged and information packets are ready, you can send out an email to all participants (1 day). Finally, after the e-mail is sent to participants and the…arrow_forwardDo not use chatgptarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.