EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

Question
Book Icon
Chapter 6.S, Problem 7P

a)

Summary Introduction

To determine: The value of x¯¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

a)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of x¯¯ is 155.16mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the value of x¯¯ :

Day Mean (MM)
1 156.9
2 153.2
3 153.6
4 155.5
5 156.6
Total 775.8

Calculate the x¯¯ :

It is calculated by dividing the sum of mean values and the number of days.

x¯¯=Sum of meanNumber of days=156.9+153.2+153.6+155.5+156.65==775.85=155.16

Hence, the value of x¯¯ is 155.16mm.

b)

Summary Introduction

To determine: The value of R¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

b)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of R¯ is 4.48mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the value of R¯ :

Day Range (MM)
1 4.2
2 4.6
3 4.1
4 5
5 4.5
Total 22.4

Calculate the R¯ :

It is calculated by dividing the sum of mean values and the number of days.

R¯=Sum of rangeNumber of days=4.2+4.6+4.1+5.0+4.55=22.45=4.48

Hence, the value of R¯ is 4.48mm.

c)

Summary Introduction

To plot: The UCL and LCL for x¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

c)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 156.54mm and LCL is 153.78mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the UCL and LCL of x¯ :

Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:

UCLx¯=x¯¯+A2×R¯

LCLx¯=x¯¯A2×R¯

Here, the overall mean is x¯¯=155.16mm , the average range is R¯=4.48mm and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 10, the Mean factor A2=0.308 for σ=3 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.

UCLx¯=x¯¯+A2×R¯=155.16+0.308×4.48=156.54mm

Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.

LCLx¯=x¯¯A2×R¯=155.160.308×4.48=153.78mm

Hence, upper control limit is 156.54mm and 153.78mm.

Plot the values:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 6.S, Problem 7P , additional homework tip  1

d)

Summary Introduction

To plot: The UCL and LCL for R¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

d)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 7.96mm and LCL is 0.999mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the UCL and LCL of R¯ :

Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:

UCLR=D4×R¯

LCLR=D3×R¯

Here, the average range is R¯=4.48mm and D3 is the lower range factor and D4 is the upper range factor.

Given the sample size of 10 for σ=3 , the Lower range factor D3=0.223 and the Upper range factor D4=1.777 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by multiplying upper range factor and average range.

UCLR=D4×R¯=1.777×4.48mm=7.96mm

Upper control limit can be calculated by multiplying lower range factor and average range.

LCLR=D3×R¯=0.223×4.48mm=0.999mm

Hence, upper control limit is 7.96mm and 0.999mm.

Plot the values:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 6.S, Problem 7P , additional homework tip  2

e)

Summary Introduction

To determine: The UCL and LCL for x¯ if the true diameter mean is 155mm.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

e)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 156.38mm and LCL is 153.62mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Given the target value of the diameter μ=155mm , calculate the upper control limits UCLx¯ and LCLx¯ using the formula

UCLx¯=μ+A2×R¯

LCLx¯=μA2×R¯

Here,

The target value of the diameter μ=155mm , the average range R¯=4.48mm and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 10, the Mean factor A2=0.308 for σ=3 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.

UCLx¯=μ+A2×R¯=155+0.308×4.48=156.38mm

Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.

LCLx¯=μA2×R¯=1550.308×4.48=153.62mm

Hence, for the x¯ chart, the upper control limit is UCLx¯=156.38mm and the lower control limit is LCLx¯=153.62mm .

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
“Implementing a Performance Management Communication Plan at Accounting, Inc.” Evaluate Accounting Inc.’s communication plan.  Specifically, does it answer all of the questions that a good communication plan should answer? Which questions are left unanswered?  How would you provide answers to the unanswered questions? “Implementing an Appeals Process at Accounting, Inc.”   If you were to design an appeals process to handle these complaints well, what would be the appeal process?  Describe the recommended process and why.
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas

Chapter 6 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.