EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

Question
Book Icon
Chapter 6.S, Problem 7P

a)

Summary Introduction

To determine: The value of x¯¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

a)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of x¯¯ is 155.16mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the value of x¯¯ :

Day Mean (MM)
1 156.9
2 153.2
3 153.6
4 155.5
5 156.6
Total 775.8

Calculate the x¯¯ :

It is calculated by dividing the sum of mean values and the number of days.

x¯¯=Sum of meanNumber of days=156.9+153.2+153.6+155.5+156.65==775.85=155.16

Hence, the value of x¯¯ is 155.16mm.

b)

Summary Introduction

To determine: The value of R¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

b)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of R¯ is 4.48mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the value of R¯ :

Day Range (MM)
1 4.2
2 4.6
3 4.1
4 5
5 4.5
Total 22.4

Calculate the R¯ :

It is calculated by dividing the sum of mean values and the number of days.

R¯=Sum of rangeNumber of days=4.2+4.6+4.1+5.0+4.55=22.45=4.48

Hence, the value of R¯ is 4.48mm.

c)

Summary Introduction

To plot: The UCL and LCL for x¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

c)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 156.54mm and LCL is 153.78mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the UCL and LCL of x¯ :

Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:

UCLx¯=x¯¯+A2×R¯

LCLx¯=x¯¯A2×R¯

Here, the overall mean is x¯¯=155.16mm , the average range is R¯=4.48mm and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 10, the Mean factor A2=0.308 for σ=3 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.

UCLx¯=x¯¯+A2×R¯=155.16+0.308×4.48=156.54mm

Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.

LCLx¯=x¯¯A2×R¯=155.160.308×4.48=153.78mm

Hence, upper control limit is 156.54mm and 153.78mm.

Plot the values:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 6.S, Problem 7P , additional homework tip  1

d)

Summary Introduction

To plot: The UCL and LCL for R¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

d)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 7.96mm and LCL is 0.999mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the UCL and LCL of R¯ :

Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:

UCLR=D4×R¯

LCLR=D3×R¯

Here, the average range is R¯=4.48mm and D3 is the lower range factor and D4 is the upper range factor.

Given the sample size of 10 for σ=3 , the Lower range factor D3=0.223 and the Upper range factor D4=1.777 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by multiplying upper range factor and average range.

UCLR=D4×R¯=1.777×4.48mm=7.96mm

Upper control limit can be calculated by multiplying lower range factor and average range.

LCLR=D3×R¯=0.223×4.48mm=0.999mm

Hence, upper control limit is 7.96mm and 0.999mm.

Plot the values:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 6.S, Problem 7P , additional homework tip  2

e)

Summary Introduction

To determine: The UCL and LCL for x¯ if the true diameter mean is 155mm.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

e)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 156.38mm and LCL is 153.62mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Given the target value of the diameter μ=155mm , calculate the upper control limits UCLx¯ and LCLx¯ using the formula

UCLx¯=μ+A2×R¯

LCLx¯=μA2×R¯

Here,

The target value of the diameter μ=155mm , the average range R¯=4.48mm and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 10, the Mean factor A2=0.308 for σ=3 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.

UCLx¯=μ+A2×R¯=155+0.308×4.48=156.38mm

Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.

LCLx¯=μA2×R¯=1550.308×4.48=153.62mm

Hence, for the x¯ chart, the upper control limit is UCLx¯=156.38mm and the lower control limit is LCLx¯=153.62mm .

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Question 2 MGMT2026 Production and Operations Management Semester II 2024-2025 a. Aman ltd. desires to locate a new facility. Based on preliminary analysis, the choice has been reduced to four locations: A, B, C, and D. These four locations were rated on a scale from 1 (worst) to 10 (best) on each of four criteria. Each criterion was also weighted to indicate its importance (i.e., the higher the weight, the more important). The list of ratings and weights follows in the Table 2 below: Table 2 Factor Score Evaluation by Location Criterion Weights A B с D Wages 25 4 5 3 4 Government Policies 30 8 7 6 5 Unionisation Weather 15 6 4 3 2 30 3 4 6 5 i. Based on weighted scores, where should Acme locate its new facility? [6 marks] b. An operations manager has narrowed down the search for a new factory to three locations. The fixed and variable costs associated with each location is given in the table below. i. Table 3 Location Fixed Cost Variable Cost A $100,000 $10 B $150,000 $7 с $200,000 $5…
The University of the West Indies GLOBAL CAMPUS MGMT 2026 Production and Operations Management - Problem Sheet Assignment Semester II 2024/2025 Note: Although this assignment is being currently assessed out of 100 marks it would be prorated to Contribute a maximum of 40% towards your final course marks. M&H company ltd. sells television sets and has collected monthly sales data (in units) for the past 12 months as shown in table 1below: TABLE 1 Month Sales (Units) 1 120 2 135 3 150 165 5 180 200 7 195 8 210 225 10 240 11 255 12 270 This Assignment is comprised of four (4) Questions - All questions must be attempted Using the data provided, answer the following questions: a. Using a 3-month weighted moving average with weights 0.5, 0.3, and 0.2 (most recent month having the highest weight), calculate the forecast for month 13. [2 marks] Screens 5-7 of 7

Chapter 6 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L