
Concept explainers
a)
To determine: The value of
Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.
a)

Answer to Problem 7P
Hence, the value of
Explanation of Solution
Given information:
The following information is given:
Day | Mean (MM) | Range (MM) |
1 | 156.9 | 4.2 |
2 | 153.2 | 4.6 |
3 | 153.6 | 4.1 |
4 | 155.5 | 5 |
5 | 156.6 | 4.5 |
Determine the value of
Day | Mean (MM) |
1 | 156.9 |
2 | 153.2 |
3 | 153.6 |
4 | 155.5 |
5 | 156.6 |
Total | 775.8 |
Calculate the
It is calculated by dividing the sum of mean values and the number of days.
Hence, the value of
b)
To determine: The value of
Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.
b)

Answer to Problem 7P
Hence, the value of
Explanation of Solution
Given information:
The following information is given:
Day | Mean (MM) | Range (MM) |
1 | 156.9 | 4.2 |
2 | 153.2 | 4.6 |
3 | 153.6 | 4.1 |
4 | 155.5 | 5 |
5 | 156.6 | 4.5 |
Determine the value of
Day | Range (MM) |
1 | 4.2 |
2 | 4.6 |
3 | 4.1 |
4 | 5 |
5 | 4.5 |
Total | 22.4 |
Calculate the
It is calculated by dividing the sum of mean values and the number of days.
Hence, the value of
c)
To plot: The UCL and LCL for
Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.
c)

Answer to Problem 7P
Hence, the value of UCL is 156.54mm and LCL is 153.78mm.
Explanation of Solution
Given information:
The following information is given:
Day | Mean (MM) | Range (MM) |
1 | 156.9 | 4.2 |
2 | 153.2 | 4.6 |
3 | 153.6 | 4.1 |
4 | 155.5 | 5 |
5 | 156.6 | 4.5 |
Determine the UCL and LCL of
Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:
Here, the overall mean is
Given the
Substitute the values in the given formulae:
Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.
Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.
Hence, upper control limit is 156.54mm and 153.78mm.
Plot the values:
d)
To plot: The UCL and LCL for
Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.
d)

Answer to Problem 7P
Hence, the value of UCL is 7.96mm and LCL is 0.999mm.
Explanation of Solution
Given information:
The following information is given:
Day | Mean (MM) | Range (MM) |
1 | 156.9 | 4.2 |
2 | 153.2 | 4.6 |
3 | 153.6 | 4.1 |
4 | 155.5 | 5 |
5 | 156.6 | 4.5 |
Determine the UCL and LCL of
Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:
Here, the average range is
Given the sample size of 10 for
Substitute the values in the given formulae:
Upper control limit can be calculated by multiplying upper range factor and average range.
Upper control limit can be calculated by multiplying lower range factor and average range.
Hence, upper control limit is 7.96mm and 0.999mm.
Plot the values:
e)
To determine: The UCL and LCL for
Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.
e)

Answer to Problem 7P
Hence, the value of UCL is 156.38mm and LCL is 153.62mm.
Explanation of Solution
Given information:
The following information is given:
Day | Mean (MM) | Range (MM) |
1 | 156.9 | 4.2 |
2 | 153.2 | 4.6 |
3 | 153.6 | 4.1 |
4 | 155.5 | 5 |
5 | 156.6 | 4.5 |
Given the target value of the diameter
Here,
The target value of the diameter
Given the sample size of 10, the Mean factor
Substitute the values in the given formulae:
Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.
Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.
Hence, for the
Want to see more full solutions like this?
Chapter 6 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- A small furniture manufacturer produces tables and chairs. Each product must go through three stages of the manufacturing process – assembly, finishing, and inspection. Each table requires 3 hours of assembly, 2 hours of finishing, and 1 hour of inspection. The profit per table is $120 while the profit per chair is $80. Currently, each week there are 200 hours of assembly time available, 180 hours of finishing time, and 40 hours of inspection time. Linear programming is to be used to develop a production schedule. Define the variables as follows: T = number of tables produced each week C= number of chairs produced each week According to the above information, what would the objective function be? (a) Maximize T+C (b) Maximize 120T + 80C (c) Maximize 200T+200C (d) Minimize 6T+5C (e) none of the above According to the information provided in Question 17, which of the following would be a necessary constraint in the problem? (a) T+C ≤ 40 (b) T+C ≤ 200 (c) T+C ≤ 180 (d) 120T+80C ≥ 1000…arrow_forwardAs much detail as possible. Dietary Management- Nursing Home Don't add any fill-in-the-blanksarrow_forwardMenu Planning Instructions Use the following questions and points as a guide to completing this assignment. The report should be typed. Give a copy to the facility preceptor. Submit a copy in your Foodservice System Management weekly submission. 1. Are there any federal regulations and state statutes or rules with which they must comply? Ask preceptor about regulations that could prescribe a certain amount of food that must be kept on hand for emergencies, etc. Is the facility accredited by any agency such as Joint Commission? 2. Describe the kind of menu the facility uses (may include standard select menu, menu specific to station, non-select, select, room service, etc.) 3. What type of foodservice does the facility have? This could be various stations to choose from, self-serve, 4. conventional, cook-chill, assembly-serve, etc. Are there things about the facility or system that place a constraint on the menu to be served? Consider how patients/guests are served (e.g. do they serve…arrow_forward
- Work with the chef and/or production manager to identify a menu item (or potential menu item) for which a standardized recipe is needed. Record the recipe with which you started and expand it to meet the number of servings required by the facility. Develop an evaluation rubric. Conduct an evaluation of the product. There should be three or more people evaluating the product for quality. Write a brief report of this activity • Product chosen and the reason why it was selected When and where the facility could use the product The standardized recipe sheet or card 。 o Use the facility's format or Design one of your own using a form of your choice; be sure to include the required elements • • Recipe title Yield and portion size Cooking time and temperature Ingredients and quantities Specify AP or EP Procedures (direction)arrow_forwardASSIGNMENT: Inventory, Answer the following questions 1. How does the facility survey inventory? 2. Is there a perpetual system in place? 3. How often do they do a physical inventory? 4. Participate in taking inventory. 5. Which type of stock system does the facility use? A. Minimum stock- includes a safety factor for replenishing stock B. Maximum stock- equal to a safety stock plus estimated usage (past usage and forecasts) C. Mini-max-stock allowed to deplete to a safety level before a new order is submitted to bring up inventory up to max again D. Par stock-stock brought up to the par level each time an order is placed regardless of the amount on hand at the time of order E. Other-(describe) Choose an appropriate product and determine how much of an item should be ordered. Remember the formula is: Demand during lead time + safety stock = amount to order Cost out an inventory according to data supplied. Remember that to do this, you will need to take an inventory, and will need to…arrow_forwardHuman Relations, Systems, and Organization Assignments ORGANIZATION: Review the organization chart for the facility • Draw an organization chart for the department. • . Identify and explain the relationships of different units in the organization and their importance to maintain the food service department's mission. Include a copy in your weekly submission. There is a feature in PowerPoint for doing this should you want to use it. JOB ORGANIZATION: ⚫ A job description is a broad, general, and written statement for a specific job, based on the findings of a job analysis. It generally includes duties, purpose, responsibilities, scope, and working conditions of a job along with the job's title, and the name or designation of the person to whom the employee reports. Job description usually forms the basis of job specification. • Work with your preceptor or supervisor to identify a position for which you will write a job description. Include a copy of the job description you write in your…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning


