EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
bartleby

Concept explainers

Question
Book Icon
Chapter 6.S, Problem 7P

a)

Summary Introduction

To determine: The value of x¯¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

a)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of x¯¯ is 155.16mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the value of x¯¯ :

Day Mean (MM)
1 156.9
2 153.2
3 153.6
4 155.5
5 156.6
Total 775.8

Calculate the x¯¯ :

It is calculated by dividing the sum of mean values and the number of days.

x¯¯=Sum of meanNumber of days=156.9+153.2+153.6+155.5+156.65==775.85=155.16

Hence, the value of x¯¯ is 155.16mm.

b)

Summary Introduction

To determine: The value of R¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

b)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of R¯ is 4.48mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the value of R¯ :

Day Range (MM)
1 4.2
2 4.6
3 4.1
4 5
5 4.5
Total 22.4

Calculate the R¯ :

It is calculated by dividing the sum of mean values and the number of days.

R¯=Sum of rangeNumber of days=4.2+4.6+4.1+5.0+4.55=22.45=4.48

Hence, the value of R¯ is 4.48mm.

c)

Summary Introduction

To plot: The UCL and LCL for x¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

c)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 156.54mm and LCL is 153.78mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the UCL and LCL of x¯ :

Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:

UCLx¯=x¯¯+A2×R¯

LCLx¯=x¯¯A2×R¯

Here, the overall mean is x¯¯=155.16mm , the average range is R¯=4.48mm and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 10, the Mean factor A2=0.308 for σ=3 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.

UCLx¯=x¯¯+A2×R¯=155.16+0.308×4.48=156.54mm

Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.

LCLx¯=x¯¯A2×R¯=155.160.308×4.48=153.78mm

Hence, upper control limit is 156.54mm and 153.78mm.

Plot the values:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 6.S, Problem 7P , additional homework tip  1

d)

Summary Introduction

To plot: The UCL and LCL for R¯ .

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

d)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 7.96mm and LCL is 0.999mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Determine the UCL and LCL of R¯ :

Formulae to determine Upper Control Limit and Lower Control Limit are given as follows:

UCLR=D4×R¯

LCLR=D3×R¯

Here, the average range is R¯=4.48mm and D3 is the lower range factor and D4 is the upper range factor.

Given the sample size of 10 for σ=3 , the Lower range factor D3=0.223 and the Upper range factor D4=1.777 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by multiplying upper range factor and average range.

UCLR=D4×R¯=1.777×4.48mm=7.96mm

Upper control limit can be calculated by multiplying lower range factor and average range.

LCLR=D3×R¯=0.223×4.48mm=0.999mm

Hence, upper control limit is 7.96mm and 0.999mm.

Plot the values:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 6.S, Problem 7P , additional homework tip  2

e)

Summary Introduction

To determine: The UCL and LCL for x¯ if the true diameter mean is 155mm.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

e)

Expert Solution
Check Mark

Answer to Problem 7P

Hence, the value of UCL is 156.38mm and LCL is 153.62mm.

Explanation of Solution

Given information:

The following information is given:

Day Mean (MM) Range (MM)
1 156.9 4.2
2 153.2 4.6
3 153.6 4.1
4 155.5 5
5 156.6 4.5

Given the target value of the diameter μ=155mm , calculate the upper control limits UCLx¯ and LCLx¯ using the formula

UCLx¯=μ+A2×R¯

LCLx¯=μA2×R¯

Here,

The target value of the diameter μ=155mm , the average range R¯=4.48mm and A2 is the Mean factor derived from standard tables showing factors for computing control charts.

Given the sample size of 10, the Mean factor A2=0.308 for σ=3 (refer table S6.1).

Substitute the values in the given formulae:

Upper control limit can be calculated by adding the multiple of average range and mean factor with the overall mean.

UCLx¯=μ+A2×R¯=155+0.308×4.48=156.38mm

Lower control limit can be calculated by subtracting the multiple of average range and mean factor from the overall mean.

LCLx¯=μA2×R¯=1550.308×4.48=153.62mm

Hence, for the x¯ chart, the upper control limit is UCLx¯=156.38mm and the lower control limit is LCLx¯=153.62mm .

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this thoroughly Here's the what-if scenario: Assume that the LA warehouse becomes temporarily or even indefinitely disabled since facing a large-scale labor disruption. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis:  Scenario Constraint Scenario vs What-if Scenario Summary The Constraint Scenario exhibits a higher total cost of $7,424,575.45 compared to the What-if Scenario's total cost of $6,611,905.60, signifying a difference of approximately $812,669.85, which indicates a more expensive operation in the Constraint Scenario. The average service time is slightly higher in the Constraint Scenario (0.72 days vs. 0.70 days), suggesting that the What-if Scenario provides a marginally quicker service. Moreover, the average end-to-end service time…
Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this throughly Here's the what-if scenario: Assume that Dallas plant has lost power. It cannot serve the DCs anymore and has to remain locked indefinitely. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis:  Scenario Constraint Scenario vs What-if Scenario Summary In comparing the Constraint Scenario to the What-if Scenario, a few key differences highlight the efficiencies evident in the supply chain. Firstly, the total cost in the Constraint Scenario is lower at $7,424,575.45, while the What-if Scenario incurs a total cost of $7,486,369.12, resulting in a cost delta of $61,793.67. Additionally, although both scenarios exhibit the same average service time of 0.72 days, the What-if Scenario has a more favorable average end-to-end service time of 2.41…
Employee In-Service Training ASSIGNMENT: In-Service Training. The intern is required to plan and implement two in-service training sessions for employees. Each in-service should last at least 10 but not more than 30 minutes and should be given to all employees affected. The preceptor or supervisor/unit manager must approve all in-service topics. 1) One presentation should be related to a policy or procedure of any kind (e.g. proper use of equipment); 2) The second presentation must be related to sanitation or safety. For each in-service presentation, the intern must develop a written class plan and a visual aid (may be a handout, poster, PowerPoint slide presentation, etc.) appropriate to the life experiences, cultural diversity and educational background of the target audience. The intern must also measure behavior change. Note, this cannot be measured by a written pre- and post- test. That would be measuring knowledge. The intern mustactually observe and document that the learners…

Chapter 6 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L