EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175859
Author: Munson
Publisher: VST
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 6.S, Problem 29P
a)
Summary Introduction
To determine: The upper and lower control limit for a 3-sigma mean chart.
b)
Summary Introduction
To determine: The upper and lower control limit for a 3-sigma range chart.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The overall average on a process you are attempting to monitor is
60.0
units. The process population standard deviation is
1.72.
Sample size is given to be
4.
Part 2
a) Determine the 3-sigma
x-chart
control limits.
Upper Control Limit
(UCLx)=enter your response here
units (round your response to two decimal places).
Part 3
Lower Control Limit
(LCLx)=enter your response here
units (round your response to two decimal places).
Part 4
b) Now determine the 2-sigma
x-chart
control limits.
Upper Control Limit
(UCLx)=enter your response here
units (round your response to two decimal places).
Part 5
Lower Control Limit
(LCLx)=enter your response here
units (round your response to two decimal places).
Part 6
How do the control limits change?
A.
The control limits are tighter for the 3-sigma
x-chart
than for the 2-sigma
x-chart.
B.
The control limits for the
2-sigma
x-chart
and for the 3-sigma
x-chart
are the same.
C.
The control limits…
The overall average of a process you are attemptingto monitor at Gihan Edirisinghe Motors is 75 units. The processstandard deviation is 1.95, and the sample size is 11 = 10. Whatwould be the upper and lower control limits for a 3-sigma controlchart?
Our company has recently received a few customer complaints that its candles are not lasting the minimum 50 days previously advertised by the company. As the newly hired quality analyst you are planning to construct control charts that will give you a sense of the current status of the production process. To this end you have collected samples from 20 production batches.
Use Microsoft Excel with answer based on both x̄-chart and R-chart plots
-Is the candle production process in control?
-What is your comment regarding the customer complaints?
-Is there any scope of improvement?
Use Microsoft Excel with answer based on both x̄-chart and R-chart plots
Chapter 6 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 6.S - Prob. 1DQCh. 6.S - Define in statistical control.Ch. 6.S - Prob. 3DQCh. 6.S - Prob. 4DQCh. 6.S - Prob. 5DQCh. 6.S - Prob. 6DQCh. 6.S - Prob. 7DQCh. 6.S - Prob. 8DQCh. 6.S - Prob. 9DQCh. 6.S - Prob. 10DQ
Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1. The overall average on a process you are attempting to monitor is 55.0 units. The process population standard deviation is 1.84. Sample size is given to be 16. a) Determine the 3-sigma x-chart control limits. Upper Control Limit (UCLx)=56.3856.38 units (round your response to two decimal places). Lower Control Limit (LCLx)=53.6253.62 units (round your response to two decimal places). b) Now determine the 2-sigma x-chart control limits. Upper Control Limit (UCLx)=? units (round your response to two decimal places). 2. Sample Size, n Mean Factor, A2 Upper Range, D4 Lower Range, D3 2 1.880 3.268 0 3 1.023 2.574 0 4 0.729 2.282 0 5 0.577 2.115 0 6 0.483 2.004 0 7 0.419 1.924 0.076 8 0.373 1.864 0.136 9 0.337 1.816 0.184 10 0.308 1.777 0.223 12 0.266 1.716 0.284 Thirty-five samples of size 7 each were taken from a…arrow_forwardCartons of Plaster are supposed to weigh exactly 32 ounces. Inspectors want to develop process control charts. They take five samples of six (6) boxes each and weigh them. Sample means (X-bar) are: 33.8, 34.6, 34.7, 34.1, and 34.2 respectively. Also, the corresponding ranges are: 1.1,0.3, 0.4. 0.7, and 0.3, respectively. The lower and upper control limits of the xbar-chart are respectively O a. None is correct O b. 30.11 and 40.15 O c. 34.01 and 34.55 O d. 33.12 and 34.12 O e. 37.01 and 39.23arrow_forwardCan someone please explain how to find upper and lower limits using Excel? I am trying to answer this question: The overall average on a process you are attempting to monitor is 50.0 units. The process population standard deviation is 1.84 Sample size is given to be 4.a) Determine the 3-sigma x-chart control limits. Upper Control Limit (UCL) = ____units (round your response to two decimal places).arrow_forward
- Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor that must be controlled. From sample sizes of 10 pistons produced each day, the mean and the range of this diameter have been as follows: a) What is the value of x? = x= 155.56 mm (round your response to two decimal places). b) What is the value of R? R 4.48 mm (round your response to two decimal places). c) What are the UCL; and LCL; using 3-sigma? Day 1 2 3 4 5 Upper Control Limit (UCL) = 156.94 mm (round your response to two decimal places). Lower Control Limit (LCL-) = 154.18 mm (round your response to two decimal places). d) What are the UCLR and LCLR using 3-sigma? Upper Control Limit (UCL) = 7.96 mm (round your response to two decimal places). Mean x (mm) 154.9 153.2 155.6 155.5 158.6 Range R (mm) 4.0 4.8 3.9 5.0 4.7 Lower Control Limit (LCL) = 1.00 mm (round your response to two decimal places). e) If the true diameter mean should be 155 mm and you want…arrow_forwardCartons of Plaster are supposed to weigh exactly 32 ounces. Inspectors want to develop process control charts. They take five samples of six (5) boxes each and weigh them. Sample means (X-bar) are: 33.8, 34.6, 34.7, 34.1, and 34.2 respectively. Also, the corresponding ranges are: 1.1, 0.3, 0.4, 0.7, and 0.3, respectively. The lower and upper control limits of the R-chart are respectively O a. O and 0.15 O b. 0.01 and 1.13 O c. O and 1.18 O d. None is correct O e. 0.03 and 1.18arrow_forward1. The data shown in Table 1 are x and R values for 20 samples of size n= 5 taken from a process producing bearings. The measurements are made on the inside diameter of the bearing, with only the last three decimals recorded (i.e., 31.6 should be 0.50316). Please show all your work for full credit. (a) Set up x and R charts on this process. Does the process seem to be in statistical control? If necessary, revise the trial control limits. (b) Assume that diameter is normally distributed. Estimate the process standard deviation. Sample R Sample R 1 31.6 4 11 29.8 4 33.0 3 12 34.0 4 35.0 4 13 33.0 10 4 32.2 4 14 34.8 4 5 33.8 38.4 31.6 15 35.6 7 3 16 30.8 7 4 17 33.0 5 8 36.8 10 18 31.6 3 9. 35.0 15 19 28.2 9 10 34.0 6 20 33.8 Table 1: Bearing Diameter Dataarrow_forward
- please answer in 30 mins.arrow_forwardFive data entry operators work at the data process-ing department of the Birmingham Bank. Each day for 30 days, the number of defective records in a sample of 250 records typedby these operators has been noted, as follows: a) Establish 3s upper and lower control limits.b) Why can the lower control limit not be a negative number? c) The industry standards for the upper and lower control lim-its are 0.10 and 0.01, respectively. What does this imply about Birmingham Bank’s own standards?arrow_forwardAn X-bar chart has the following control limits UCL=251.5 and LCL=248.5. The sample size is n=4, the process mean is equal to 250 and the process standard deviation is sigma = 1.0. What is the Cp value ? 0.500 not enough information 0.316 0.408 0.447 0.353arrow_forward
- Factors for Computing Control Chart Limits (3 sigma) Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor that must be controlled. From sample sizes of 10 pistons produced each day, the mean and the range of this diameter have been as follows: Day Mean x (mm) Range R (mm) 1 156.9 4.2 2 153.2 4.6 3 153.6 4.1 4 155.5 5.0 5 156.6 4.5 Part 4 c) What are the (UCLx) and (LCLx) using 3-sigma? (UCLx) = mm (round your response to two decimal places). (LCLx) = mmarrow_forward24 For a 3-sigma x-bar chart where the process standard deviation is known, the upper control limit: Select one: a. is 3σ/ below the mean of sample means for a 3σ control chart. b. cannot be calculated unless the average range is known. c. is 3σ/ above the mean of sample means for a 3σ control chart. d. is 3σ below the mean of sample means for a 3σ control chart. e. is 3σ above the mean of sample means for a 3σ control chart.arrow_forwardAn automatic filling machine is used to fill 1-liter bottles of cola. The machine’s output is approximately normal with a mean of 1.0 liter and standard deviation of .01 liter. Output is monitored using means of samples of 25 observations. Determine upper and lower control limits that will include roughly 97% of the sample means when the process is in control. Using Appendix B, Table A to find the value of Z corresponding to the mean control limits.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.