Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 100 and 3-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

a)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.05145 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 100 and 3-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 3-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=100 and obtain the value of σp

σp=0.015×(0.985)100=0.014775100=0.00014775=0.012155

Hence, the standard deviation of the sampling distribution σp=0.012155

The given values of p¯=1.5% and z=3 and σp=0.012155 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+3×0.01215=0.05145

Hence, the upper control chart limit UCLp=0.05145

The given values of p¯=1.5% and z=3 and σp=0.012155 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0153×0.01215=0.02145=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

b)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 50 and 3-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

b)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.06657 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 50 and 3-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 3-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=50 and obtain the value of σp

σp=0.015×(0.985)50=0.01477550=0.0002955=0.017190

Hence, the standard deviation of the sampling distribution σp=0.017190

The given values of p¯=1.5% and z=3 and σp=0.017190 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+3×0.017190=0.06657

Hence, the upper control chart limit UCLp=0.06657

The given values of p¯=1.5% and z=3 and σp=0.017190 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0153×0.017190=0.03657=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

c)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 100 and 2-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

c)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.0393 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 100 and 2-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 2-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=100 and obtain the value of σp

σp=0.015×(0.985)100=0.014775100=0.00014775=0.012155

Hence, the standard deviation of the sampling distribution σp=0.012155

The given values of p¯=1.5% and z=2 and σp=0.012155 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+2×0.01215=0.0393

Hence, the upper control chart limit UCLp=0.0393

The given values of p¯=1.5% and z=2 and σp=0.012155 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0152×0.01215=0.0093=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

d)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 50 and 2-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

d)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.04938 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 50 and 2-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 2-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=50 and obtain the value of σp

σp=0.015×(0.985)50=0.01477550=0.0002955=0.017190

Hence, the standard deviation of the sampling distribution σp=0.017190

The given values of p¯=1.5% and z=2 and σp=0.017190 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+2×0.017190=0.04938

Hence, the upper control chart limit UCLp=0.04938

The given values of p¯=1.5% and z=2 and σp=0.017190 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0153×0.017190=0.01938=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

e)

Summary Introduction

To determine: What happen to σ^p if the sample size is larger.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

e)

Expert Solution
Check Mark

Explanation of Solution

Determine what happen to σ^p if the sample size is larger:

The standard deviation of the sampling distribution σp . reduces when the sample size increases. However, in the calculation the sample size is in the denominator.

f)

Summary Introduction

To determine: Why LCL cannot be less than 0.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

f)

Expert Solution
Check Mark

Explanation of Solution

Determine why LCL cannot be less than 0:

The lower control limit for defectives cannot be less than zero because it becomes negative. A negative lower control limit is meaningless.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
CASE STUDY 9-1 Was Robert Eaton a Good Performance Management Leader? R obert Eaton was CEO and chairman of Chrys- ler from 1993 to 1998, replacing Lee Iacocca, who retired after serving in this capacity since 1978. Eaton then served as cochairman of the newly merged DaimlerChrysler organization from 1998 to 2000. In fact, Eaton was responsible for the sale of Chrysler Corporation to Daimler-Benz, thereby creating DaimlerChrysler. With 362,100 employees, DaimlerChrysler had achieved revenues of €136.4 billion in 2003. DaimlerChrysler's passenger car brands included Maybach, Mercedes-Benz, Chrysler, Jeep, Dodge, and Smart. Commercial vehicle brands included Mercedes-Benz, Freightliner, Sterling, Western Star, and Setra. From the beginning of his tenure as CEO, Eaton communicated with the people under him. He immediately shared his plans for the future with his top four executives, and upon the advice of his colleague, Bob Lutz, decided to look around the company before making any hasty…
Critically assess Martin’s coaching style.
Compare Robert Eaton’s performance management leadership presented in the case against the performance management leadership principles, functions, and behaviors.  What recommendations can be made about what he might do more effectively?  Explain and defend your answer.

Chapter 6 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.