a)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 100 and 3-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

a)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.05145 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 100 and 3-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 3-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=100 and obtain the value of σp

σp=0.015×(0.985)100=0.014775100=0.00014775=0.012155

Hence, the standard deviation of the sampling distribution σp=0.012155

The given values of p¯=1.5% and z=3 and σp=0.012155 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+3×0.01215=0.05145

Hence, the upper control chart limit UCLp=0.05145

The given values of p¯=1.5% and z=3 and σp=0.012155 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0153×0.01215=0.02145=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

b)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 50 and 3-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

b)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.06657 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 50 and 3-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 3-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=50 and obtain the value of σp

σp=0.015×(0.985)50=0.01477550=0.0002955=0.017190

Hence, the standard deviation of the sampling distribution σp=0.017190

The given values of p¯=1.5% and z=3 and σp=0.017190 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+3×0.017190=0.06657

Hence, the upper control chart limit UCLp=0.06657

The given values of p¯=1.5% and z=3 and σp=0.017190 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0153×0.017190=0.03657=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

c)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 100 and 2-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

c)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.0393 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 100 and 2-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 2-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=100 and obtain the value of σp

σp=0.015×(0.985)100=0.014775100=0.00014775=0.012155

Hence, the standard deviation of the sampling distribution σp=0.012155

The given values of p¯=1.5% and z=2 and σp=0.012155 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+2×0.01215=0.0393

Hence, the upper control chart limit UCLp=0.0393

The given values of p¯=1.5% and z=2 and σp=0.012155 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0152×0.01215=0.0093=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

d)

Summary Introduction

To determine: Determine the UCL and LCL if the sample size is 50 and 2-sigma limits.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

d)

Expert Solution
Check Mark

Answer to Problem 13P

Hence, the UCL is 0.04938 and LCL is 0.

Explanation of Solution

Given information:

Defect rate is given as 1.5%.

Determine the UCL and LCL if the sample size is 50 and 2-sigma limits:

UCLp=p¯+z×σp

LCLp=p¯z×σp

Here,

z refers to the number of standard deviation for setting the limit. Here, it is 2-sigma limit.

σp is the standard deviation of the sampling distribution.

Calculate the value of the standard deviation of the sampling distribution σp :

σp=p¯×(1p¯)n

The given values of p¯=1.5% and the sample size n=50 and obtain the value of σp

σp=0.015×(0.985)50=0.01477550=0.0002955=0.017190

Hence, the standard deviation of the sampling distribution σp=0.017190

The given values of p¯=1.5% and z=2 and σp=0.017190 has been determine. Substitute the values in UCL formula to determine the value of UCL:

UCLp=p¯+z×σp=0.015+2×0.017190=0.04938

Hence, the upper control chart limit UCLp=0.04938

The given values of p¯=1.5% and z=2 and σp=0.017190 has been determine. Substitute the values in LCL formula to determine the value of LCL:

LCLp=p¯z×σp=0.0153×0.017190=0.01938=0

Hence, lower control chart limit cannot be negative therefore LCLp=0

e)

Summary Introduction

To determine: What happen to σ^p if the sample size is larger.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

e)

Expert Solution
Check Mark

Explanation of Solution

Determine what happen to σ^p if the sample size is larger:

The standard deviation of the sampling distribution σp . reduces when the sample size increases. However, in the calculation the sample size is in the denominator.

f)

Summary Introduction

To determine: Why LCL cannot be less than 0.

Introduction: Control charts used to determine whether the process is under control or not. Attributes and variables are the factors under the control charts.

f)

Expert Solution
Check Mark

Explanation of Solution

Determine why LCL cannot be less than 0:

The lower control limit for defectives cannot be less than zero because it becomes negative. A negative lower control limit is meaningless.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
1) View the videos Taco Bell test-drives Live Mas restaurant concept in South Bay (0.32 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=04wRc5Wg8GU , and First-ever Taco Bell Live Mas Café serving exclusive drinks in Chula Vista (1.56 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=fq6jDxJk1LM , and answer the following questions:   a) What is driving Taco Bell to try a beverage-focused format? b) What type of a process strategy does their beverage-focused format represent? c) What operational issues do you think Taco Bell would face from their beverage-focused format? d) What do you think are the main advantages and disadvantages of kiosk ordering?   Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions.   2) Taipei Pharmaceuticals is planning to open a new manufacturing facility as part of its expansion plans. The firm has narrowed down the search to locate its new manufacturing facility…
1) View the videos Taco Bell test-drives Live Mas restaurant concept in South Bay (0.32 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=04wRc5Wg8GU , and First-ever Taco Bell Live Mas Café serving exclusive drinks in Chula Vista (1.56 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=fq6jDxJk1LM , and answer the following questions:   a) What is driving Taco Bell to try a beverage-focused format? b) What type of a process strategy does their beverage-focused format represent? c) What operational issues do you think Taco Bell would face from their beverage-focused format? d) What do you think are the main advantages and disadvantages of kiosk ordering?   Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions.   2) Taipei Pharmaceuticals is planning to open a new manufacturing facility as part of its expansion plans. The firm has narrowed down the search to locate its new manufacturing facility…
The Clothing Shack is an online retailer of men's, women's, and children's clothing. The company has been in business for four years and makes a modest profit from its online sales. However, in an effort to compete successfully against online retailing heavyweights, the Clothing Shack's marketing director, Makaya O'Neil, has determined that the Clothing Shack's marketing information systems need improvement. Ms. O'Neil feels that the Clothing Shack should begin sending out catalogs to its customers, keep better track of its customer's buying habits, perform target marketing, and provide a more personalized shopping experience for its customers. Several months ago, Ms. O'Neil submitted a systems service request (SSR) to the Clothing Shack's steering committee. The committee unanimously approved this project. You were assigned to the project at that time and have since helped your project team successfully complete the project initiation and planning phase. Your team is now ready to move…

Chapter 6 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - Prob. 18DQCh. 6.S - Prob. 19DQCh. 6.S - Prob. 1PCh. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Prob. 5PCh. 6.S - Prob. 6PCh. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 36PCh. 6.S - Prob. 37PCh. 6.S - Prob. 39PCh. 6.S - Prob. 40PCh. 6.S - Prob. 41PCh. 6.S - Prob. 42PCh. 6.S - Prob. 43PCh. 6.S - Prob. 44PCh. 6.S - Prob. 45PCh. 6.S - Prob. 46PCh. 6.S - Prob. 48PCh. 6.S - Prob. 49PCh. 6.S - Prob. 50PCh. 6.S - Prob. 51PCh. 6.S - Prob. 52PCh. 6.S - Prob. 53PCh. 6.S - Prob. 54PCh. 6.S - Prob. 55PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1EDCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - Prob. 18DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 1CSCh. 6 - Prob. 2CSCh. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 3.1VCCh. 6 - Prob. 3.2VCCh. 6 - Prob. 3.3VCCh. 6 - Prob. 3.4VCCh. 6 - Prob. 3.5VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,