Advantage Energy Technology Data Center Migration—Part A
Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider’ world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability Due to the complexity of this project. Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.
Currently, AET’s data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice President of Operations, Dan Whitmore, with the following guidelines:
• From start to finish, it is anticipated the entire project will take three to four months to complete.
• It is essential that AET’s 235 clients suffer no downtime.
Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, “first-cut” timeline, and proposed project team members.
Brian had some preliminary discussions with some of AET’s managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following;
Three to four months is a feasible project timeline and first-cut cost estimate is $80,000—$90,000 (this includes the infrastructure upgrade of the new site).
• Critical to the ‘no-downtime” requirement is the need to completely rely on AET’s remote disaster recovery ‘hot” site for full functionality.
• Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.
Brian’s Executive Committee report was positively received and. after a few modifications and recommendations, he was formally charged with responsibility for the project Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.
Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the network Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires a new ventilation system. The manufacturer’s requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time.
The data center supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.
The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units (“Switchover Approval”). Meetings with each of the functional units will require one week During this tune he can initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day.
Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.
Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data center. Brian will do the move over the weekend—two days—when user traffic is at low point.
2. Develop a WBS for Brian’s project. Include duration (days) and predecessors.
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
- Review the article: Defining the Motivations and Capabilitied of Young Intrapreneurs: Literature Review and Research Opportunities 1. Discuss the differences and similarities of Entrepreneurship and Intrapreneurship. 2. How might your current organization or a former organization that you have been a member of incorporate the elements of Intrapreneurship? 3. Discuss the future of Intrapreneurship List referencesarrow_forwardRoles for Human Resource Departments Analyze HRM functions. Describe and detail each one of these functions. Why are the specific roles associated to HRM important? List referencesarrow_forwardEmployees and Entrepreneurs share many skills, mindsets and values. Even if you are employed by an organization, you may have an entrepreneurial mindset and entrepreneurial traits. How do you envision yourself within an organization, as an employee rather tahan an entrepreneur? Discuss the traits and values that support this?arrow_forward
- Please original work Talk about your need for creating a balanced scorecard in a management consulting firm and the steps you would take to design the balance scorecard. Please cite in text resources and weblinksarrow_forwardThink of a team in which you have participated in a professional setting (the number of individuals should be more than one person and includes you. Also, the team could have been virtual, collocated, or a mixture of virtual and collocated). Think back on how the team formed from the first day until the end of the project or when the work function was completed. Describe what took place. Do you feel your team followed any part of Tuckman's model? Consider what was discussed regarding high-performing teams in the lesson this week in the Team Performance Domain section. It was explained that high-performing project teams are characterized by different factors. Based on the factors listed about high-performance teams, which two factors do you feel your team could have improved upon and why?arrow_forwardPlease original work Background information: Innovation can be simply defined as the introduction of something new or different in the workplace. Creativity on the other hand could be described as the use of the imagination for original ideas. Talk about the difference between innovation and creativity in the workplace and the role that technology plays in fostering both innovation and creativity Please cite in text resources and add weblinksarrow_forward
- In procurement evolution, which statement below should i choose to be themost relevant to ‘limited integration phaseSupply management is often viewed as a lower-level support function.It is the final and most advanced phase of procurement evolution.Supply managers' primary role is to ensure enough supply capacity exists.Supply management is a key part of the organisational structure with a strongexternal customer focus.arrow_forwardWhich of the following stages of P2P process is believed most critical for the spendperformance of procurement?Supplier evaluation and selection stagePayment and settlement stageRecognition of needs stageClarification of needs stagearrow_forwardWhich of the following statements is most accurate in describing ‘preferredsuppliers’?A preferred supplier involves a lower-level risk but still has a significant spend with thebuyer.They will be asked to compete with other suppliers for better price and conditions.They refer the strategic partners of the company.They are the core suppliersarrow_forward
- The primary purpose of this coordination is to establish company-wide agreementsto leverage volumes to obtain lower costs from volume discounts.” Which phase ofprocurement evolution is more relevant to the statement?Phase 1 Basic beginningPhase 2 Moderate developmentPhase 4 Fully integrated supply chainPhase 3 Limited integrationarrow_forwardAmong the phases of procurement evolution, the phase that ‘focuses on supplybaseoptimisation, and more attention is paid to total quality management (TQM) than toother progressive supply management strategies’ is more relevant to ___________.Phase 1 Basic beginningPhase 3 Limited integrationPhase 4 Fully integrated supply chainPhase 2 Moderate developmentarrow_forwardWhich of the following description methods is most suitable if the requirements arewell understood and there is common agreement between supply chain partners aboutwhat certain terms mean?Description by specificationDescription by brandDescription by industry standardDescription by performance characteristicsarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning