Advantage Energy Technology Data Center Migration—Part A
Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider’ world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability Due to the complexity of this project. Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.
Currently, AET’s data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice President of Operations, Dan Whitmore, with the following guidelines:
• From start to finish, it is anticipated the entire project will take three to four months to complete.
• It is essential that AET’s 235 clients suffer no downtime.
Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, “first-cut” timeline, and proposed project team members.
Brian had some preliminary discussions with some of AET’s managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following;
Three to four months is a feasible project timeline and first-cut cost estimate is $80,000—$90,000 (this includes the infrastructure upgrade of the new site).
• Critical to the ‘no-downtime” requirement is the need to completely rely on AET’s remote disaster recovery ‘hot” site for full functionality.
• Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.
Brian’s Executive Committee report was positively received and. after a few modifications and recommendations, he was formally charged with responsibility for the project Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.
Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the network Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires a new ventilation system. The manufacturer’s requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time.
The data center supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.
The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units (“Switchover Approval”). Meetings with each of the functional units will require one week During this tune he can initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day.
Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.
Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data center. Brian will do the move over the weekend—two days—when user traffic is at low point.
1. Generate a priority matrix for AET’s system move.
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
- I participated in a team tasked with developing and implementing a new customer service training program. The team included five members: myself, two training specialists, an HR representative, and a team leader. Our work environment was a mix of virtual and collocated, with weekly in-person meetings and frequent virtual check-ins. Reflecting on our process, it's evident that parts of “Tuckman's model”(Forming, Storming, Norming, Performing, and Adjourning) were present in the development and completion of the project.arrow_forwardProvince/Territory Ontario Quebec British Columbia Alberta Saskatchewan Manitoba Nova Scotia Newfoundland and Labrador Number of Firms 2017 2019 2020 58 54 70 16 19 20 16 17 13 5 6 3 2 1 1 2 2 1 1 1 1 0 0 1 What makes these companies leaders is that they grew rapidly. It does not matter whether they are high-tech or old-economy companies, manufacturing or service companies, they all are exceptional. A remarkable assortment of products and services are offered by these companies. Examples include trucking, car parts, exterior painting services, steeped tea, gaming, sustainable office furniture, business performance consultants, and construction management. Dana 12arrow_forwardelijah wants to start a carpet cleaning business. to do so, he needs to purchase a carpet cleaner and advertise. he estimates the cleaner will cost $400 and advertising will cost $1,600 initially. the cleaning solution is fairly cheap, costing only $5 per room cleaned. he also thinks he will have $3 in gas on average for each client. if he charges $40 per room cleaned and cleans an average of 2 rooms per house, how many houses will he have to clean before breaking even? if taxes are 25% of profits, how many rooms will he have to clean before making $5,000 profit? answer the question by making a cvp worksheet similar to the depreciation sheets. make sure it works well, uses cell references and functions/formulas when appropriate, and looks nice.arrow_forward
- What insights can you gain from working in a laundry business while maintaining a balance in your personal life? What about the joy of doing your work?arrow_forwardHow can you improve your lost and found system in laundry business? Like if there's a customer who has a missing garments and another customer found it accidentally in their clothes?arrow_forwardthe government is about to build a coop housing project in an open land where rich elites are living,suggest some survey questions for the rich elites on citing the coop housing project in their neigbourhood.arrow_forward
- suggest a A PITCH TO CONVINCE CAPE BRETON UNIVERSITY USING THEIR MISSIO STATEMENT ,VISION STATEMENT AND VALUES TO TELL THE SCHOOL WHY THEY SHOULD SUPPORT THE COOP HOUSING PROJECT INITIATIVE WITH RESOURCES OTHER THAN FINANCE.arrow_forwardDRAW UP A PITCH TO CONVINCE CAPE BRETON UNIVERSITY USING THEIR MISSIO STATEMENT ,VISION STATEMENT AND VALUES TO TELL THE SCHOOL WHY THEY SHOULD SUPPORT THE COOP HOUSING PROJECT INITIATIVE WITH RESOURCES OTHER THAN FINANCE.arrow_forwardPlease original work (Please dont add any AI sentences) Background information: LEGO was founded in 1932. The word LEGO is from the Danish words LEg GOdt (play well). Later, it was realized that in Latin the word means “I put together”. The firm initially made wooden toys as well as other wood products stepladders, ironing boards, stools, etc. In 1947, the LEGO Group bought a plastic injection-molding machine for toy production and in 1949 the first LEGO Automatic Binding Brick with four and eight studs appeared. LEGO flourished for many years with its innovative toys. However, in 2004, innovation almost bankrupted the Danish toymaker. LEGO had become concerned about low-cost copies of its plastic building products so it sought to diversify into different activities including: theme parks, Clikits craft sets, action figures (Galidor), and a television show among other efforts. All of these were unprofitable and were eventually discontinued. Today, LEGO is growing in an overall…arrow_forward
- Please original work Talk about your current organization’s greatest needs for creating a balanced scorecard for management consulting firm, and steps you would take to design the balance scorecard. Please cite in text references and add weblinks.arrow_forwardPlease original work How do you think organizations can effectively balance short-term resource constraints with the need for long-term investments in areas like technology and employee development, especially when both are critical to achieving strategic goals? Please cite in text references and add weblinksarrow_forwardImportanc of the process Tuckman's model”(Forming, Storming, Norming, Performing, and Adjourning)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning