Textbook Question
Book Icon
Chapter 6, Problem 6.1.1C

Advantage Energy Technology Data Center Migration—Part A

Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider’ world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability Due to the complexity of this project. Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.

Currently, AET’s data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice President of Operations, Dan Whitmore, with the following guidelines:

• From start to finish, it is anticipated the entire project will take three to four months to complete.

• It is essential that AET’s 235 clients suffer no downtime.

Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, “first-cut” timeline, and proposed project team members.

Brian had some preliminary discussions with some of AET’s managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following;

Three to four months is a feasible project timeline and first-cut cost estimate is $80,000—$90,000 (this includes the infrastructure upgrade of the new site).

• Critical to the ‘no-downtime” requirement is the need to completely rely on AET’s remote disaster recovery ‘hot” site for full functionality.

• Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.

Brian’s Executive Committee report was positively received and. after a few modifications and recommendations, he was formally charged with responsibility for the project Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.

Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the network Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires a new ventilation system. The manufacturer’s requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time.

The data center supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.

The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units (“Switchover Approval”). Meetings with each of the functional units will require one week During this tune he can initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day.

Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.

Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data center. Brian will do the move over the weekend—two days—when user traffic is at low point.

1. Generate a priority matrix for AET’s system move.

Blurred answer
Students have asked these similar questions
Transportation is considered a facilitator of trade as it can either make trade feasible or infeasible. Transportation infrastructure is crucial to the efficiency of transportation and ultimately, international trade. After conducting research on infrastructure investments in Canada, choose one infrastructure investment that has not been chosen already by a fellow candidate and describe the scope of the project and its objectives. Be sure to explain how your project helps facilitate trade with which specific regions and how it contributes to efficient supply chains.
Discuss the advantages and disadvantages of integrating multiple data tracking systems with a CRM. Describe how integration can impact analytics. Describe possible barriers to an organization implementing a CRM.
I participated in a team tasked with developing and implementing a new customer service training program. The team included five members: myself, two training specialists, an HR representative, and a team leader. Our work environment was a mix of virtual and collocated, with weekly in-person meetings and frequent virtual check-ins. Reflecting on our process, it's evident that parts of “Tuckman's model”(Forming, Storming, Norming, Performing, and Adjourning) were present in the development and completion of the project. Do you think only clarifying roles and fostering trust would have resolved the issue you had experienced?

Chapter 6 Solutions

Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)

Knowledge Booster
Background pattern image
Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY