Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the Whistler Ski Resort project. The project workweek will be 5 days (M-F).
Whistler Ski Resort Project
Given the fact that the number of skiing visitors to Whistler, B.C., Canada, has been increasing at an exciting rate, thanks to the 2010 Winter Olympics, the Whistler Ski Association has been considering construction of another ski lodge and ski complex. The results of an economic feasibility study just completed by members of the staff show that a winter resort complex near the base of Whistler Mountain could be a very profitable venture. The area is accessible by car, bus, train, and air. The board of directors has voted to build the 10-million-dollar complex recommended in the study. Unfortunately, due to the short summer season, the complex will have to be built in stages. The first stage (year 1) will contain a day lodge, chair lift, rope tow, generator house (for electricity), and a parking lot designed to accommodate 400 cars and 30 buses. The second and third stages will include a hotel, ice rink, pool, shops, two additional chair lifts, and other attractions. The board has decided that stage one should begin no later than April 1 and be completed by October 1, in time for the next skiing season. You have been assigned the task of project manager, and it is your job to coordinate the ordering of materials and construction activities to ensure the project’s completion by the required date.
After looking into the possible sources of materials, you are confronted with the following time estimates. Materials for the chair lift and rope tow will take 30 days and 12 days, respectively, to arrive once the order is submitted. Lumber for the day lodge, generator hut, and foundations will take 9 days to arrive. The electrical and plumbing materials for the day lodge will take 12 days to arrive. The generator will take 12 days to arrive. Before actual construction can begin on the various facilities, a road to the site must be built; this will take 6 days. As soon as the road is in. clearing can begin concurrently on the sites of the day lodge, generator house, chair lift, and rope tow. It is estimated that the clearing task at each site will take 6 days, 3 days, 36 days, and 6 days, respectively. The clearing of the main ski slopes can begin after the area for the chair lift has been cleared; this will take 84 days.
The foundation for the day lodge will take 12 days to complete. Construction of the main framework will take an additional 18 days. After the framework is completed, electrical wiring and plumbing can be installed concurrently. These should take 24 and 30 days, respectively. Finally, the finishing construction on the day lodge can begin; this will take 36 days.
Installation of the chair lift towers (67 days) can begin once the site is cleared, lumber delivered, and the foundation completed (6 days). Also, when the chair lift site has been cleared, construction of a permanent road to the upper towers can be started; this will take 24 days. While the towers are being installed, the electric motor to drive the chair lift can be installed; the motor can be installed in 24 days. Once the towers are completed and the motor installed, it will take 3 days to install the cable and an additional 12 days to install the chairs.
Installation of the towers for the rope tow can begin once the site is cleared and the foundation is built and poured; it takes 4 days to build the foundation, pour the concrete and let it cure, and 20 days to install the towers for the rope tow. While the towers are being erected, installation of the electric motor to drive the rope tow can begin; this activity will take 24 days. After the towers and motor are installed, the rope tow can be strung in 1 day. The parking lot can be cleared once the rope tow is finished; this task will take 18 days.
The foundation for the generator house can begin at the same time as the foundation for the lodge; this will take 6 days. The main framework for the generator house can begin once the foundation is completed; framing will take 12 days. After the house is framed, the diesel generator can be installed in 18 days. Finishing construction on the generator house can now begin and will take 12 more days.
Assignment:
Identify the critical path on your network.
Can the project be completed by October 1?
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
- build a basic business plan for a supermarket. Make sure to include projected feasibility, market, competitive analysis, and establish your Mission Statement and Core Values.arrow_forwardWhat is an analysis of a supermarkets projected competition. How do you stack up in the marketplace? Do you have a competitive advantage? How will your company break into the market? If there is no competition, when do you expect competitors to enter the marketplace and how will you market against them? Be as specific as possiblearrow_forwardI am currently interning at Lakes Counseling Services it is an autism center. Position is Human Resources intern. However, my major is Health Service Management, so I would like the position description to align more closely with health services and administration. Can you do Roles/responsibilitiesarrow_forward
- Can you guys help me with this? Thank you! Please give some comments about the authentic insight written by my classmate here about the articlearrow_forwardI am currently interning at Lakes Counseling Services it is an autism center. Position is Human Resources intern. However, my major is Health Service Management, so I would like the position description to align more closely with health services and administration. Thank you!arrow_forwardWhich of the following statements could signal a group might be susceptible in groupthink? What data are you using? Why do you believe that to be true? What other options should be considered? Don’t you agree? Which of the following circumstances justifies a lack of agenda?The meeting is informal and routine. There wasn’t enough time. Agendas are not part of company culture. The meeting leader is exceptionally busy. Which is not a strategic consideration listed in the chapter that assists managers in preparation for meetings? whether to meet leadership style physical facilities feedback Question 4 Which is not an advantage of working in a team? it may reduce the chance of communication problems. It provides a welcome break from routine independent tasks. Group members are more likely to be committed to the information presented) A group decision may be of a higher quality than that made by an individual. Flag question: Question 5…arrow_forward
- What sort of scheduling issues might you have for a soup kitchen project besides resources and conflicts and lack of communication?arrow_forwardConsidering contemporary challenges in business, analyze a real-world case where a company successfully navigated a major shift in its marketing strategy to adapt to changing market dynamics. Discussion Question and Prompt: Identify the key factors that contributed to the success of their marketing strategy in the face of contemporary issues. How can businesses draw insights from this case to inform their own marketing strategies amid current business challenges? Introduction and Problem StatementThis report examines ...[Include a statement of the main problem in the case.]Background[Detailed company/case background tying directly to the context of the specific case study.Summarize data from the case scenario that is pertinent to solving the stated problem.]Analysis[Thoroughly analyze the questions asked of you here as well as the main questions suggestedwithin the case study.]Alternatives and Evaluation[This section should list some options available as solutions and discuss the…arrow_forwardWhich of the following circumstances justifies a lack of agenda? orivide correct answer and why The meeting is informal and routine. There wasn’t enough time. Agendas are not part of company culture. The meeting leader is exceptionally busy.arrow_forward
- I need help answering the following questions below What does succession planning entail and what are its essential steps? Are there any disadvantages to using a nine-box grid for succession planning? Would having any difficulty in categorizing anyone who reports or has reported to you into one of the boxes? If you never managed a team, think about employees you have worked with in the past and how you would categorize them. Do most people frequently move from one box to another or do most people tend to stay in one box for long periods of their careers?arrow_forwardPlease original work Background information: You are the chairman of the board for a large technology company. You are seeking a new CEO to replace your recently departed company founder. You are seeking an innovative leader for your organization. What do you think are the most important characteristics for the leader to have? Explain why each is important. How will you determine if an individual has those characteristics? Discuss how executives can ensure a successful fit. Please cite in text references and add weblinksarrow_forwardIn regards to minimum wage, should there be a national standard or should minimum wage be regulated by the state?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,