(a)
Interpretation: Number of days of raw material B’s plant has is to be determined.
Concept Introduction:
The raw material which is important for the B’s plant is the steel sheets.
(b)
Interpretation: Number of days of work-in-process inventory is held between Press and Pierce and form is to be calculated.
Concept Introduction:
The work-in-progress refers to the ongoing process and waiting for completion. It is an important term used in production and
(c)
Interpretation: Number of days of work-in-process inventory is held between Pierce and form and Finish Grind is to be calculated.
Concept Introduction:
The work-in-progress refers to the ongoing process and waiting for completion. It is an important term used in production and supply chain management.
(d)
Interpretation: Number of days of work-in-process inventory is held between Finish Grind and Shipping.
Concept Introduction:
The work-in-progress refers to the ongoing process and waiting for completion. It is an important term used in production and supply chain management.
(e)
Interpretation:
Lead time of new value stream’s production.
Concept Introduction:
Lead time refers to as the latency between beginning and completion of a process.
(f)
Interpretation:
Process time of the new value stream
Concept Introduction:
Processing time is nothing but the sum of each process cycle time.
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
Operations Management: Processes And Supply Chains (12th Global Edition) - Does Not Include Mylab Operations Management
- Carol Cagle bas a repetitive manufacturing plantproducing trailer bitches in Arlington, Texas. The plant has anaverage inventory tu rnover of only 12 times per year. She hastherefore determined that she will reduce her component lotsizes. She has developed the following data for one component,the safety chain clip:Annual demand = 31,200 unitsDaily demand = 120 unitsDaily production (in 8 hours) = 960 unitsDesired lot size (I hour of production) = 120 unitsHolding cost per unit per year = $12Setup labor cost per hour = $20How many minutes of setup time should she have her plant manageraim for regarding this component?arrow_forwardWhich of the following is ‘data’? i. Number of items in inventory in the store were 3,000 ii. Value of items in the store was OMR 5,000 iii. Total items with value OMR 1,500 to OMR 3,000 were 500arrow_forwardWhat happens to availability when the MTTR (mean time between failures) decreases to zero? Is there a way to convey this circumstance correctly?arrow_forward
- Based on available information, lead time demand for PC jump drives averages 48 units (normally distributed), with a standard deviation of 5 drives. Management wants a 98% service level. Refer to the standard normal table for z-values. a) What value of Z should be applied? 2.06 b) How many drives should be carried as safety stock? your response to the nearest whole number). units (roundarrow_forwardDetermine the mix model sequence in the given data: Product Monthly Demand Daily Requirement A 800 30 B 800 30 C 200 5arrow_forwardPlease do not give solution in image format thankuarrow_forward
- c) Even if there is substantial uncertainty in the parameters in the EOQ-model, it is still quite a useful model. Discuss why.arrow_forward"If the demand for a good decreases when a consumer's income rises, the demand for that good must decrease when its price rises". This statement is valid for Nora's demand for cheese. This statement is not valid for Chris' demand for pasta. Q1 a) Using an appropriate model with a diagram, explain in detail Nora's demand for cheese.arrow_forwardA company begins a review of ordering policies for its continuous review system by checking the current policies for a sample of SKUS Following are the characteristics of one tem Demand (D)=85 units/week (Assume 52 weeks per year) Ordening and setup cost (S) $75/order Holding cost (H)-$16/und/year Lead time (L) 5 week(s) Standard deviation of weekly demand 22 units Cycle-service lovel-90 percent >EOQ-207 units Using the above information, develop the best policies for a periodic review system Refer to the standard normal table for z-values a. What value of P gives the same approximate number of orders per year as the EOQ? weeks (Enter your response rounded to the nearest whole number) b. To provide a 98 percent cycle-service level, the average safety stock is To provide a 98 percent cycle-service level, the target inventory level is unts (Enter your response rounded to the nearest whole number) units (Enter your response rounded to the nearest whole number)arrow_forward
- Which one of the following is the most likely example of dependent demand for an MRP controlled item? Demand for spare parts Demand directly from customers Demand from quality control department for destructive testing Demand from MPS Which of the following quantities has no effect on the first period’s ATP calculation? Current on-hand inventory Booked customer orders for the first periods MPS quantity for the first period Forecasted demand for the first periodarrow_forwardYou are completing your audit of LTC Ltd, an importer of cell phones from Taiwan. Total sales this year were $54,000,000. The results of your audit work on inventory are summarized in the following table: Description # of SKU’s $ Value Population 120 $5,200,000 Sample 30 $2,080,000 Errors found 5 $177,000 Required Using the monetary unit method, calculate the projected inventory error, and, assess it against materiality.arrow_forwardThe average weekly demand for ABC Towel Inc.’s sole product is 50 boxes. Its supplier takes 1 week on average and 1.5 weeks maximum to deliver an order. If ABC maintains a safety stock based on the aforementioned data and orders 300 boxes at a time, what is the expected average boxes on hand?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.