A manager is trying to decide whether to purchase a certain part or to have it produced internally. Internal production could use either of two processes. One would entail a variable cost of $17 per unit and an annual fixed cost of $200,000; the other would entail a variable cost of $14 per unit and an annual fixed cost of $240,000. Three vendors are willing to provide the part. Vendor A has a price of $20 per unit for any volune up to 30,000 units. Vendor B has a price of $22 per unit for demand of 1,000 units or less, and $18 per unit for larger quantities. Vendor C offers a price of $21 per unit for the first 1,000 units, and $19 per unit for additional units.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The best alternative from a cost standpoint for an annual volume of 10,000 units and 20,000 units.

Introduction: Decision-making is the process that helps to make decision. It is the process of choosing a best alternative by evaluating many alternatives.

Answer to Problem 8P

The best alternative from a cost standpoint for an annual volume of 10,000 and 20,000 units are purchasing parts from Vendor B.

Explanation of Solution

Given information:

A manager has to decide whether to purchase a product or produce it internally. Internal production consists of two processes. Variable cost and fixed cost of the first process is $17 and $200,000 respectively. Variable cost and fixed cost of the second process is $14 and $240,000 respectively.

There are three vendors available to purchase a product. Vendor A has a price of $20 per unit up to 30,000 units. Vendor B has a price of $22 per unit if the demand is 1,000 units or less and $18 for larger volumes. Vendor C has a price of $21 per unit for first 1,000 units and $19 per unit for additional units.

Determine the best alternative from a cost standpoint for an annual volume of 10,000 units:

Calculate the total cost for the first internal process:

It is calculated by adding the fixed cost with the value attained by multiplying the variable cost and the annual volume. Annual volume is given as 10,000 units. Hence, the total cost for the first internal process is $370,000.

Total cost=Fixed cost+(Variable cost×Annual volume)=$200,000+($17×10,000)=$200,000+170,000=$370,000

Calculate the total cost for the second internal process:

It is calculated by adding the fixed cost with the value attained by multiplying the variable cost and the annual volume. Annual volume is given as 10,000 units. Hence, the total cost for the first internal process is $380,000.

Total cost=Fixed cost+(Variable cost×Annual volume)=$240,000+($14×10,000)=$240,000+140,000=$380,000

Calculate the total cost for the Vendor A:

It is calculated by multiplying the price and the annual volume. Hence, the total cost for Vendor A is $200,000.

Total cost=Price×Annual volume=$20×10,000=$200,000

Calculate the total cost for the Vendor B:

It is calculated by multiplying the price and the annual volume. It is given that the price is $22 if the volume is less than 1,000 and $18 if the volume is larger. As the annual volume is more than 1,000, the price is $18. Hence, the total cost for Vendor B is $180,000.

Total cost=Price×Annual volume=$18×10,000=$180,000

Calculate the total cost for the Vendor C:

It is calculated by multiplying the price and the annual volume. It is given that the price is $21 for the volume up to 1,000 and $19 for the additional volume. Thus, price is $21 for the 1,000 units and $19 for additional 9,000 units. Hence, the total cost for Vendor C is $192,000.

Total cost=(Price×Annual volume)+(Price×Additional volume)=($21×1,000)+($19×9,000)=$21,000+$171,000=$192,000

At the annual volume of 10,000 units, Vendor B has the lowest total cost of ($180,000). Hence, it should be chosen from a cost standpoint.

Determine the best alternative from a cost standpoint for an annual volume of 20,000 units:

Calculate the total cost for the first internal process:

It is calculated by adding the fixed cost with the value attained by multiplying the variable cost and the annual volume. Annual volume is given as 20,000 units. Hence, the total cost for the first internal process is $540,000.

Total cost=Fixed cost+(Variable cost×Annual volume)=$200,000+($17×20,000)=$200,000+340,000=$540,000

Calculate the total cost for the second internal process:

It is calculated by adding the fixed cost with the value attained by multiplying the variable cost and the annual volume. Annual volume is given as 20,000 units. Hence, the total cost for the first internal process is $520,000.

Total cost=Fixed cost+(Variable cost×Annual volume)=$240,000+($14×20,000)=$240,000+280,000=$520,000

Calculate the total cost for the Vendor A:

It is calculated by multiplying the price and the annual volume. Hence, the total cost for Vendor A is $400,000.

Total cost=Price×Annual volume=$20×20,000=$400,000

Calculate the total cost for the Vendor B:

It is calculated by multiplying the price and the annual volume. It is given that the price is $22 if the volume is less than 1,000 and $18 if the volume is larger. As the annual volume is more than 1,000, the price is $18. Hence, the total cost for Vendor B is $360,000.

Total cost=Price×Annual volume=$18×20,000=$360,000

Calculate the total cost for the Vendor C:

It is calculated by multiplying the price and the annual volume. It is given that the price is $21 for the volume up to 1,000 and $19 for the additional volume. Thus, price is $21 for the 1,000 units and $19 for additional 19,000 units. Hence, the total cost for Vendor C is $382,000.

Total cost=(Price×Annual volume)+(Price×Additional volume)=($21×1,000)+($19×19,000)=$21,000+$361,000=$382,000

At the annual volume of 20,000 units, Vendor B has the lowest total cost of ($360,000). Hence, it should be chosen from a cost standpoint.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The range of the best alternative.

Introduction:Decision-making is the process that helps to make decision. It is the process of choosing a best alternative by evaluating many alternatives.

Answer to Problem 8P

The ranges were determined and First internal process and Vendor C are never best.

Explanation of Solution

Given information:

A manager has to decide whether to purchase a product or produce it internally. Internal production consists of two processes. Variable cost and fixed cost of the first process is $17 and $200,000 respectively. Variable cost and fixed cost of the second process is $14 and $240,000 respectively.

There are three vendors available to purchase a product. Vendor A has a price of $20 per unit up to 30,000 units. Vendor B has a price of $22 per unit if the demand is 1,000 units or less and $18 for larger volumes. Vendor C has a price of $21 per unit for first 1,000 units and $19 per unit for additional units.

Cost function for each alternative if the annual volume is 1-1,000 units:

First internal process:

$200,000+$17Q

Second internal process:

$240,000+$14Q

Vendor A:

$20Q

Vendor B:

$22Q

Vendor C:

$21Q

When considering the cost functions, Vendor A would exhibit less cost when compare to Vendor B and Vendor C. Vendor A should be preferred over other alternatives. The graph is as follows:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 5, Problem 8P , additional homework tip  1

Cost function for each alternative if the annual volume is more than 1,000 units:

First internal process:

$200,000+$17Q

Second internal process:

$240,000+$14Q

Vendor A:

$20Q

Vendor B:

$18Q

Vendor C:

$21Q+$19(Q1,000)

When considering the cost functions, Vendor B would dominate Vendor A and Vendor C. Hence, Vendor A and Vendor C should be eliminated. The graph considering two internal processes and Vendor B is as follows:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 5, Problem 8P , additional homework tip  2

Determine the value of Q by equaling two cost equations:

Equal the cost function of second internal process and Vendor B to determine the value of Q.

$18Q=$240,000+$14Q$18Q$14Q=$240,000$4Q=$240,000

Q=$240,000$4=60,000 units

Calculate the total cost of first internal process:

Substitute the value Q in the cost equation of first internal process. Hence, the total cost is $1,220,000.

Total cost=$200,000+$17Q=$200,000+($17×60,000)=$200,000+1,020,000=1,220,000

Calculate the total cost of second internal process:

Substitute the value Q in the cost equation of second internal process. Hence, the total cost is $1,080,000.

Total cost=$240,000+$14Q=$240,000+($14×60,000)=$240,000+840,000=1,080,000

Calculate the total cost of Vendor A:

Substitute the value Q in the cost equation of Vendor A. Hence, the total cost is $1,200,000.

Total cost=$20Q=$20×60,000=1,200,000

Calculate the total cost of Vendor B:

Substitute the value Q in the cost equation of Vendor B. Hence, the total cost is $1,080,000.

Total cost=$18Q=$18×60,000=1,080,000

Calculate the total cost of Vendor C:

Substitute the value Q in the cost equation of Vendor C. Hence, the total cost is $1,142,000.

Total cost=$21Q+$19(Q1,000)=$21,000+($19×59,000)=$21,000+$1,121,000=$1,142,000

Inference:

  • Vendor A should be preferred when the purchasing quantity ranges from 1 to 1,000 units.
  • Vendor B should be preferred when the purchasing quantity ranges from 1,001 to 59,999 units.
  • There would indifferent between Vendor B and second internal process if the quantity is 60,000 units.
  • Second internal process should be preferred if the quantity is more than 60,000 units.

First internal process and Vendor C are never best.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Excel Please. The workload of many areas of banking operations varies considerably based on time of day.  A variable capacity can be achieved effectively by employing part-time personnel.  Because part-timers are not entitled to all the fringe benefits, they are often more economical than full-time employees.  Other considerations, however, may limit the extent to which part-time people can be hired in a given department.  The problem is to find an optimal workforce schedule that would meet personnel requirements at any given time and also be economical.   Some of the factors affecting personnel assignments are listed here:   The bank is open from 9:00am to 7:00pm. Full-time employees work for 8 hours (1 hour for lunch included) per day. They do not necessarily have to start their shift when the bank opens. Part-time employees work for at least 4 hours per day, but less than 8 hours per day and do not get a lunch break. By corporate policy, total part-time personnel hours is limited…
IM.84 An outdoor equipment manufacturer sells a rugged water bottle to complement its product line. They sell this item to a variety of sporting goods stores and other retailers. The manufacturer offers quantity discounts per the following discount schedule: Option Plan Quantity Price A 1 - 2,399 $5.50 B 2,400 - 3,999 $5.20 C 4,000+ $4.50 A large big-box retailer expects to sell 9,700 units this year. This retailer estimates that it incurs an internal administrative cost of $225 each time it places an order with the manufacturer. Holding cost for the retailer is $55 per case per year. (There are 40 units or water bottles per case.) Based on this information, and not taking into account any quantity discount offers, what is the calculated EOQ (in units)? (Display your answer to the nearest whole number.) Number Based on this information, sort each quantity discount plan from left to right by dragging the MOST preferred option plan to the left, and the LEAST preferred…
In less than 150 words, what is an example of what your reflection of core values means to you and your work: Commitment, Perseverance, Community, Service, Pride?

Chapter 5 Solutions

OPERATIONS MANAGEMENT W/ CNCT+

Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
  • Text book image
    Contemporary Marketing
    Marketing
    ISBN:9780357033777
    Author:Louis E. Boone, David L. Kurtz
    Publisher:Cengage Learning
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY