OPERATIONS MANAGEMENT W/ CNCT+
OPERATIONS MANAGEMENT W/ CNCT+
12th Edition
ISBN: 9781259574931
Author: Stevenson
Publisher: MCG CUSTOM
bartleby

Videos

Textbook Question
Book Icon
Chapter 5, Problem 10P

A company must decide which type of machine to buy, and how many units of that type, given the following information:

Chapter 5, Problem 10P, A company must decide which type of machine to buy, and how many units of that type, given the , example  1

Product demand and processing times for the equipment are:

Chapter 5, Problem 10P, A company must decide which type of machine to buy, and how many units of that type, given the , example  2

a. How many machines of each type would be required to handle demand if the machines will operate 8 hours a day, 250 days a year, and what annual capacity cushion in processing time would result for each?

b. With high certainty of annual demand, which type of machine would be chosen if that was an important consideration?

c. If purchasing and operating costs are taken into account, which type of machine would minimize total costs, given your answer for part a? Operating costs are $6/hr for type 1 and $5/hr for type 2.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The number of machines of each type required to handle the demand and its capacity.

Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.

Answer to Problem 10P

The number of machines of type 1 required is 2 machines and the number of machines of type 2 required is 2 machines.

Explanation of Solution

Given information:

A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.

Annual demand and processing unit is given as follows for each product:

ProductAnnual demandProcessing time per minute
Type 1 Type 2
001 12,000 4 6
002 10,000 9 9
003 18,000 5 3

Determine the number of machines of each type required and its capacity:

It is given that the machines will operate 60 minutes per hour, 8 hours per day and 250 days per year.

Determine the minutes available for machine type 1:

It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 1 is 120,000 minutes per year.

Available minutes=Number of days per year×Hours per day×Minutes per hour=250×8×60=120,000 minutes per year

Determine the processing requirement of product 001 using machine type 1:

It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 1. Hence, the processing requirements of product 001 using machine type 1 is 48,000 minutes.

Processing requirement of product 001=Annual demand×Processing time=12,000×4 minutes=48,000 minutes

Determine the processing requirement of product 002 using machine type 1:

It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 1. Hence, the processing requirements of product 002 using machine type 1 is 90,000 minutes.

Processing requirement of product 002=Annual demand×Processing time=10,000×9 minutes=90,000 minutes

Determine the processing requirement of product 003 using machine type 1:

It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 1. Hence, the processing requirements of product 003 using machine type 1 is 90,000 minutes.

Processing requirement of product 003=Annual demand×Processing time=18,000×5 minutes=90,000 minutes

Determine the total processing requirement using machine type 1:

It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.

Total processing requirements=(Processing requirement of product 001+Processing requirement of product 002+Processing requirement of product 003)=48,000+90,000+90,000=228,000 minutes

Determine the needed number of machine type 1:

It is calculated by dividing the total processing requirement and available minutes for machine type 1. Hence, the needed number of machine type 1is 2 machines.

Number of machine type 1 needed=Processing time neededAvailable minutes for machine type 1=228,000120,000=1.92 machines

Determine the capacity of the machines:

It is calculated by multiplying the number of machine type 1 needed and the available minutes for machine type 1. Hence, the capacity of the machine is 240,000 minutes.

Capacity of machines=Number of machines×Available minutes for machine type 1=2×120,000=240,000 minutes

Determine the capacity cushion:

It is calculated by subtracting total processing requirement from capacity of machines.

Capacity cushion=CapacityProcessing requirement=240,000228,000=12,000 minutes

Determine the minutes available for machine type 2:

It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 2 is 120,000 minutes per year.

Available minutes=Number of days per year×Hours per day×Minutes per hour=250×8×60=120,000 minutes per year

Determine the processing requirement of product 001 using machine type 2:

It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 2. Hence, the processing requirements of product 001 using machine type 2 is 72,000 minutes.

Processing requirement of product 001=Annual demand×Processing time=12,000×6 minutes=72,000 minutes

Determine the processing requirement of product 002 using machine type 2:

It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 2. Hence, the processing requirements of product 002 using machine type 2 is 90,000 minutes.

Processing requirement of product 002=Annual demand×Processing time=10,000×9 minutes=90,000 minutes

Determine the processing requirement of product 003 using machine type 2:

It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 2. Hence, the processing requirements of product 003 using machine type 2 is 54,000 minutes.

Processing requirement of product 003=Annual demand×Processing time=18,000×3 minutes=54,000 minutes

Determine the total processing requirement using machine type 2:

It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.

Total processing requirements=(Processing requirement of product 001+Processing requirement of product 002+Processing requirement of product 003)=72,000+90,000+54,000=216,000 minutes

Determine the needed number of machine type 2:

It is calculated by dividing the total processing requirement and available minutes for machine type 2. Hence, the needed number of machine type 2 is 2 machines.

Number of machine type 2 needed=Processing time neededAvailable minutes for machine type 1=216,000120,000=1.82 machines

Determine the capacity of the machines:

It is calculated by multiplying the number of machine type 2 needed and the available minutes for machine type 2. Hence, the capacity of the machine is 240,000 minutes.

Capacity of machines=Number of machines×Available minutes for machine type 2=2×120,000=240,000 minutes

Determine the capacity cushion:

It is calculated by subtracting total processing requirement from capacity of machines.

Capacity cushion=CapacityProcessing requirement=240,000216,000=24,000 minutes

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The machine type that can be chosen for the high and low certainty of demand.

Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.

Answer to Problem 10P

Machine type 2 can be chosen when there is high certainty of annual demand. Machine type 1 can be chosen when there is low certainty of annual demand.

Explanation of Solution

Given information:

A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.

Annual demand and processing unit is given as follows for each product:

ProductAnnual demandProcessing time per minute
Type 1 Type 2
001 12,000 4 6
002 10,000 9 9
003 18,000 5 3

Determine the machine type that can be chosen for the high and low certainty of demand:

The machine with the high capacity cushion should be selected, if the firm faced high certainty of annual demand. hence, machine type 2 should be selected.

The machine with the low capacity cushion should be selected, if the firm faced low certainty of annual demand. hence, machine type 1 should be selected.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The machine type that would minimize the total cost, if purchasing and operating costs are considered.

Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.

Answer to Problem 10P

Machine type 1 would minimize the total cost.

Explanation of Solution

Given information:

A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.

Annual demand and processing unit is given as follows for each product:

ProductAnnual demandProcessing time per minute
Type 1 Type 2
001 12,000 4 6
002 10,000 9 9
003 18,000 5 3

Operating cost is given as $6 per hour for type 1 and $5 per hour for type 2.

Determine the purchase cost for machine type 1:

It is calculated by multiplying the number of machines and cost of type 1 machine. Hence, the purchase cost for machine type 1 is $20,000.

Purchase cost=Number of machines×Machine cost=2 machines×$10,000=$20,000

Determine the total operating time for machine type 1:

Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.

Total processing requirements=(Processing requirement of product 001+Processing requirement of product 002+Processing requirement of product 003)=48,000+90,000+90,000=228,000 minutes3,800 hours

Determine the total operating cost:

Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $22,800.

Total operating cost=Total operating time×Operating cost per hour=3,800 hours×$6 per hour=$22,800

Determine the total cost:

It is calculated by adding the purchasing cost of machine type 1 and total operating cost. Hence, the total cost is $42,800.

Total cost=Total purchase cost+Total operating cost=$20,000+$22,800=$42,800

Determine the purchase cost for machine type 2:

It is calculated by multiplying the number of machines and cost of type 2 machine. Hence, the purchase cost for machine type 2 is $28,000.

Purchase cost=Number of machines×Machine cost=2 machines×$14,000=$28,000

Determine the total processing requirement using machine type 2:

Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.

Total processing requirements=(Processing requirement of product 001+Processing requirement of product 002+Processing requirement of product 003)=72,000+90,000+54,000=216,000 minutes3,600 hours

Determine the total operating cost:

Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $18,000.

Total operating cost=Total operating time×Operating cost per hour=3,600 hours×$5 per hour=$18,000

Determine the total cost:

It is calculated by adding the purchasing cost of machine type 2 and total operating cost. Hence, the total cost is $46,000.

Total cost=Total purchase cost+Total operating cost=$28,000+$18,000=$46,000

Hence, Machine type 1 would minimize the total cost.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
How does capacity analysis behave when a large number of processes are operating concurrently?
Manufacturing Company uses FIFO method of accumulating costs in a two-department process. Materials are introduced at the inception of the process except for a special material which is added in department 2 at 60% completion as to overhead. Inspection is done at the end of the process in both departments. Production data for Department 2 are given below: In process, beginning, (80% labor, 70% overhead)2,000 Transferred in 14,900 In process, ending (40% labor, 20% overhead) 3,000 Normal spoilage 200 Abnormal spoilage (found at 30% completion as to laborand 15% as to overhead due to internal failure) 400 Cost data for the month:In process beginning:Transferred in 15,020 Special materials 1,900 Direct labor 4,388 Overhead 11,044 Current costs:Transferred in 137,080 Special materials 14,030 Direct labor 46,000 Overhead 113,564   The cost of units transferred to finished goods is?The cost of spoilage charged to revenue is?
The owner of Firewood To Go is considering buying a hydraulic wood splitter which sells for $50,000. He figures it will cost an additional $100 per cord to purchase and split wood with this machine, while he can sell each cord of split wood for $125. If, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is anticipated to be 35 cords per day, what would be its utilization? 100 percent 80 percent 75 percent 70 percent 0 percent The owner of Firewood To Go is considering buying a hydraulic wood splitter which sells for $50,000. He figures it will cost an additional $100 per cord to purchase and split wood with this machine, while he can sell each cord of split wood for $125. If, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is expected to be 32 cords per day, what would be its efficiency? 100 percent 80 percent 75 percent 70 percent 0 percent

Chapter 5 Solutions

OPERATIONS MANAGEMENT W/ CNCT+

Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY