Introduction:
Decision tree is one of the methods used in decision-making process. It would graphically represent the available alternatives and states of nature. It would also mention the payoffs and probabilities of the alternatives. It helps to choose the best alternative that would give the best result among the alternatives.
a)
![Check Mark](/static/check-mark.png)
Answer to Problem 4P
Explanation of Solution
Given information:
If small facility is build:
When demand is lower, then
When demand is higher, then two alternatives are as follows:
First alternative: To maintain and NPV is $50,000
Second alternative: To expand and NPV is $450,000
If large facility is build:
Demand is high: NPV is $800,000
Demand is low: NPV is -$10,000
Decision tree diagram:
Explanation:
Here we see that there are (1) two alternative decision small facility to build or to large facility to build. First alternative is to build small facility and there is also two sub parts, first is low demand and second is high demand. In high demand there are (2) two alternative decisions which has also two parts; first has to be maintained and other is expand.
Decision is based on right to left in decisions. We can see that expand have higher NPV that other alternatives.
Calculate the decision alternative payoffs:
It is given that probability of low demand is 40%, and high demand is 60%.
Small facility to build:
If low demand:
Therefore, the payoff of low demand is $160,000.
If high demand:
Therefore, the payoff of high demand is $270,000.
Large facility to build:
If low demand:
If high demand:
Calculate the expected value of each alternative:
Small facility to build:
Large facility to build
Here, we see that highest expected value is for larger facility to build so this alternative need to select and small facility alternative have double slash.
b)
To determine: To calculate expected value of perfect information.
Expected value of perfect information: It is the rate that a person is willing to pay to gain access to get perfect information. A common area which uses expected value of perfect information is the healthcare economy. This value tries to evaluate the expected cost of the uncertainty, which can be interpreted as the expected value of perfect information.
b)
![Check Mark](/static/check-mark.png)
Answer to Problem 4P
Explanation of Solution
Explanation
Calculation of expected value of perfect information:
Step 1: Calculate the expected value with perfection information or Expected payoff under certainty:
Therefore, expected value with perfection information is $640,000.
Step 2: Calculation of the expected value of perfect information:
Hence, the expected value of perfect information is $164,000.
c)
To determine: The range over each alternative that are best in term of the value of P.
Introduction: Decision table to evaluate the range over each alternative. Decision table is formats or visual representations were data is expressed arranged, determined and calculated to make an effective decision making. A decision table is a tabular representation that is used to analyze decision alternatives and states of nature.
c)
![Check Mark](/static/check-mark.png)
Explanation of Solution
Decision table is based on each alternative which are relative to P (low) and graph of low demand and high demand:
Alternative | High Demand | Low Demand |
Build Small | $450,000 | 400,000 |
Build Large | $800,000 | -$10,000.00 |
From the above graph we can obtain that optimal value of P (low) over each alternative are, for low value of P (low) here we decide to build large facilities because we are getting higher expected value. For high value of P (low) we decided to build small facility because we are getting higher expected value.
Calculate the exact value of range:
Equations:
Build Small: 450,000 – 50,000P (slope = 400,000 – 450,000)
Build Large:800,000 – 810,000P (slope = -10,000 – 800,000)
Find the intersection between the two lines:
Optimal ranges:
Build Large: P (Low) = 0 to < .4605
Build Small: P (Low) > .4605 to 1.00
Want to see more full solutions like this?
Chapter 5 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
- Read Himachal Fertilizer Corporation (B) and critique the decision he actually made after reading Part B. Was your recommendation similar to what Neil did...how was it the same or how did it differ? Explain why with details from course materials and the case.arrow_forwardName the key stakeholders in the Himachal Fertilizer Corporation Part A case. Consider the stakeholder map in the image below. Which stakeholders would be the most important under your default lens?arrow_forwardThis crosstab shows product sub-category sales within categories, broken out by sales quarter. The quarterly values for each sub-category increase within each category, with the largest value at the bottom. Using Running Total as the calculation type, which scope and direction option gives this result?arrow_forward
- 6:35 nvas.liberty.edu < 72% i You must post before seeing replies. Edit history will be available to instructors. ☑ Due Feb 13 33 Replies (33) 50 points Discussion Thread: How to Look at the Bible After reading the assigned chapters in Everyday Bible Study (Chapters 1-5), create a learning log that lists 10 quotes from the assigned reading that highlight either a concept that resonated with you or a concept that represents new learning for you. Following each of these quotes, you must provide a 3-5 sentence explanation of how the selected quote represents either what resonated with you or this new learning. For an example of this type of thread, please see the provided example. Pleas ◄ Previous cussion Assignment instructions ✓ and the ||| Next ▸arrow_forwardDo a report to promote an innovative product/service within an organization of your choice. In your assignment, you need to focus on the below: 1. Give a brief introduction of the innovative product/service you are thinking about within an organization of your choice. 2. Analyze how you are going to promote your idea internally to your colleagues (e.g. meetings, presenting and disseminating the information). 3. Explain how you are going to convince them that this product/service is applicable and that it will create a competitive advantage in the market. 4. Refer to a similar product/service that your competitors have and analyze how the competitors’ product can be considered as a threat to your new product/service. 5. Estimate how much will the whole procedure cost to the business. 6. In your conclusions, describe how the new product/service will influence the whole organization’s environment. 3000 words and include and introducion, conclusion and references.arrow_forwardFor my learning and not a assignment question: Tesla, the U.S. electric vehicle manufacturer, has recently proposed to join Indonesia’s initiative to develop an EV battery supply chain within the country. This information was shared by a senior Indonesian government official, who noted that the government received Tesla's proposal on Thursday. Indonesia, known for its rich nickel reserves, is already in discussions with companies like China's Contemporary Amperex Technology (CATL) and South Korea's LG Chem to establish a comprehensive EV battery supply chain that covers everything from raw materials to the final product. Sepian Hari Seto, the deputy for investment and mining at the Coordinating Ministry of Maritime Affairs and Investment, expressed enthusiasm for Tesla's advanced lithium battery technology. He conveyed that the collaboration with Tesla, along with CATL and LG, presents a valuable opportunity for technology transfer and learning. Furthermore, Seto mentioned the…arrow_forward
- Your company is considering investing in a Human Resource Information System (HRIS).Briefly explain the strategies for justifying HRIS investments.arrow_forwardPresent the criteria you would utilize to determine if a right should be extended to an employee or if it would unnecessarily impact a manager’s ability to manage. Additionally, assess how you would balance the need for management rights against the need for employee rights, and how greater employee rights positively and negatively affect the future of the organization.arrow_forwardprovide schoarly research and references as to how internal and exteral audit is a risk management strategy to mitigate risk in a financial institutionarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)