To determine

The diameter of cyclone at various air flow rates.

Expert Solution & Answer
Check Mark

Answer to Problem 5.6P

The diameter of cyclone at different air flow rate is classified into a table below.

    Terminal velocity(m/sec) Diameter of the Cyclone
    5 2153m
    10 748m
    15 411m
    25 199m
    40 105m
    150 21m
    300 10.54m

Explanation of Solution

Calculation:

Write the expression for pressure changes in the cyclone.

  dPdr=ρ×Vt2r   ...... (I)

Here, the change of pressure is dP , the change of rotation radius is dr , the tangential velocity is Vt , the air density is ρ and the rotational radius is r .

Calculate the tangential velocity at radius r .

  Vt=ωr

Here, the rotational velocity is ω .

Write the expression for pressure drop in the cyclone.

  ΔP=ρ×Vt×ln(R)   ...... (II)

Substitute ωr for Vt in Equation (II).

  ΔP=ρ×ωR×ln(R)ω=ΔPρR×ln(R)   ...... (III)

Write the expression for the terminal velocity.

  v=[4( ρ g ρ) ω 2Rd3 C Dρ]12 ..... (IV)

Substitute ΔPρ×ln(R) for ω in Equation (IV).

  v=[ 4( ρ g ρ ) ( ΔP ρ D 2 ×ln( D 2 ) ) 2 Rd 3 C D ρ]12=[ 8( ρ g ρ ) ( ΔP ) 2 Rd 3 C D ρ 3 D ( ln( D 2 ) ) 2 ]12 ..... (V)

Here, the diameter of the cyclone is D .

Convert 1in into metric system.

  1in=0.0254m

Substitute 2700kg/m3 for ρg , 1.2kg/m3 for ρ , 249Pa for ΔP , 0.0254m for d and 2.5 for CD in Equation (V).

  v=[ 8( 2700 kg/ m 3 1.2 kg/ m 3 ) ( 249Pa ) 2 0.0254m 3×2.5× ( 1.2 kg/ m 3 ) 3 ×D ( ln( D 2 ) ) 2 ]12v=( 2623542.5 D ( ln( D 2 ) ) 2 )12   ...... (VI)

Calculate the diameter at an air flow rate of 5m/sec .

Substitute 5m/sec for v in Equation (VI).

  5m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=2153m

Calculate the diameter at an air flow rate of 10m/sec .

Substitute 10m/sec for v in Equation (VI).

  10m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=748m .

Calculate the diameter at an air flow rate of 15m/sec .

Substitute 15m/sec for v in Equation (VI).

  15m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=411m

Calculate the diameter at an air flow rate of 25m/sec .

Substitute 25m/sec for v in Equation (VI).

  25m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=199m

Calculate the diameter at an air flow rate of 40m/sec .

Substitute 40m/sec for v in Equation (VI).

  40m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=105m

Calculate the diameter at an air flow rate of 150m/sec .

Substitute 150m/sec for v in Equation (VI).

  150m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=21m

Calculate the diameter at an air flow rate of 300m/sec .

Substitute 300m/sec for v in Equation (VI).

  300m/sec=( 2623542.5 D ( ln( D 2 ) ) 2 )12

Solve for the value of D .

  D=10.54m

Classify the calculated data.

    Terminal velocity(m/sec) Diameter of the Cyclone
    5 2153m
    10 748m
    15 411m
    25 199m
    40 105m
    150 21m
    300 10.54m

Conclusion:

Thus, the diameter at different air flow rate is classified into a table below.

    Terminal velocity(m/sec) Diameter of the Cyclone
    5 2153m
    10 748m
    15 411m
    25 199m
    40 105m
    150 21m
    300 10.54m

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
2 1d/T₁₂ = 1/2 n First impulse E ("œw / ])÷(1) '7 J-1 -1- -2+ 0 0.5 1 1.5 2
Bars AD and CE (E=105 GPa, a = 20.9×10-6 °C) support a rigid bar ABC carrying a linearly increasing distributed load as shown. The temperature of Bar CE was then raised by 40°C while the temperature of Bar AD remained unchanged. If Bar AD has a cross-sectional area of 200 mm² while CE has 150 mm², determine the following: the normal force in bar AD, the normal force in bar CE, and the vertical displacement at Point A. D 0.4 m -0.8 m A -0.4 m- B -0.8 m- E 0.8 m C 18 kN/m
Draw the updated network. Calculate the new project completion date. Check if there are changes to the completion date and/or to the critical path. Mention the causes for such changes, if any. New network based on the new information received after 15 days (Correct calculations, professionally done). Mention if critical path changes or extended. Write causes for change in critical path or extension in the critical path.
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Understanding Stresses in Beams; Author: The Efficient Engineer;https://www.youtube.com/watch?v=f08Y39UiC-o;License: Standard Youtube License