A paced assembly line has been devised to manufacture calculators, as the following data show:
- What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)
- What cycle time corresponds to this maximum output rate?
- If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?
- What is the line’s efficiency?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A single model manual assembly line produces a product whose work content time = 47.8 min. The line has 24 workstations with a manning level =1.25. Available shift time per day = 8 hr, but downtime during the shift reduces actual production time to 7.6 hr on average. This results in an average daily production of 256 units/day. Repositioning time per worker is 8% of cycle time. Determine (a) line efficiency, (b) balancing efficiency,and (c) repositioning time.
The Avis Company is a car rental company and is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 2 minutes. The average traveling time (a round trip) is 20 minutes.
How many Avis buses are traveling to and from the airport?
The branch manager wants to improve the service and suggests dispatching buses every 0.5 minute. She argues that this will reduce the average traveling time (a round trip) to Avis’s offices to 2.5 minutes. Is she correct? If your answer is negative, then what will the average traveling time be?
A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?
Chapter 5 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 5 - Take a process that you encounter on a daily...Ch. 5 - Prob. 2DQCh. 5 - How could the efficiency of the redesigned process...Ch. 5 - Bill’s Barbershop has two barbers available to...Ch. 5 - Melissa’s Photo Studio offers both individual...Ch. 5 - Figure 5.11 details the process flow for two types...Ch. 5 - Prob. 4PCh. 5 - Super Fun Industries manufactures four top-selling...Ch. 5 - Prob. 6PCh. 5 - Yost-Perry Industries (YPI) manufactures a mix of...
Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - A.J.’s Wildlife Emporium manufactures two unique...Ch. 5 - Cooper River Glass Works (RGW) produces four...Ch. 5 - Quick Stop Pharmacy is a small family-owned,...Ch. 5 - Use the longest work element rule to balance the...Ch. 5 - Johnson Cogs wants to set up a line to serve 60...Ch. 5 - Refer back to Problem 16. Suppose that in addition...Ch. 5 - To meet holiday demand, Penny’s Pie Shop...Ch. 5 - A paced assembly line has been devised to...Ch. 5 - Prob. 20PCh. 5 - Greg Davis, a business major at the University of...Ch. 5 - Prob. 1VCCh. 5 - Which boarding scenario among the different ones...Ch. 5 - How should Southwest evaluate the gate boarding...Ch. 5 - How will Southwest know that the bottleneck had...
Additional Business Textbook Solutions
Find more solutions based on key concepts
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
What is precedent, and how does it affect common law?
Business in Action
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) SEE PICTURE Answer Carrow_forwardThe Pullman Mig, Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 20 minunit Station 1 Machine A Station 1 Machine B 20 min/unit Station 2 6 min/unit Station 3 12 minunit The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3. a) The throughput time of the new work cell is 38 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 10 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 3 is 360 units (enter your response as a whole number). d) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell without the second machine at workstation 3 is units (enter your response…arrow_forwardRideShare offers short-term rentals of vehicles that are kept in small lots in urbanneighborhoods with plenty of potential customers. With one lot, it has eight cars. Theinterarrival time of potential demand for this lot from its base of customers is 40 minutes.The average rental period is five hours. If a customer checks availability of vehicles in thislot online and finds that they are all rented for the desired time, the customer skips rentingand finds alternative arrangements. However, because customers pay a monthly fee tosubscribe to this service, RideShare does not want customers to be disappointed too often.a. What is the offered load?b. What is the implied utilization?c. What is the capacity of the process (rentals per hour)?d. What is the probability that all eight cars are rented at the same time?e. How many customers are served every hour?f. What is the utilization of the cars?g. How many cars should it have in this lot to ensure that it serves at least 90 percent ofdemand?arrow_forward
- An output of 720 units per shift (7.40 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 26 seconds. What is the required cycle time for such a system? How efficient is your system with the cycle time calculated? Station 3 changes and now requires 50 seconds to complete. What will need to be done to meet demand (assume only 7.40 hours are available)? What is the efficiency of the new system?arrow_forwardThe roller coaster at Treasure Island Amusement Park consists of 20 cars, each of which can carry up to two passengers. According to a time study, each run takes 4.5 minutes, and the time to unload and load riders is 5.5 minutes. What is the theoretical capacity of the system in number of passengers per hour? Round your answer down to the nearest whole number. _________ passengers per hourarrow_forwardThe Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 6 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 2 is whole number). units (enter your response as aarrow_forward
- Students are going through a three-step process to obtain their ID cards. Each student will spend 2 minutes at the registration desk before going to one of three cashiers to pay a fee for the ID card. After that, he/she will visit one of four ID processing stations to have his/her picture taken and ID card printed. Visits to the cashier and ID processing station take 10 and 20 minutes respectively. If the demand rate is 0.5 student per minute, how long does it take to process 20 students, assuming the system is full? Multiple Choice 100 minutes 127 minutesarrow_forwardA car dealership has on average 4.5 cars in its service bays. On aveage each car takes 90 minutes for service. Express the answer as cars / hour. 0.05arrow_forwardI need the answer for part carrow_forward
- Uberya Towing Services repair vehicles that break down at an average 8 vehicles per day. The mechanic crew can service an average of 11 vehicles per day. How many vehicles are likely to be in the system at any one time? The crew cost is approximately Php 900 per day. The cost associated with lost productivity from the breakdown is estimated at Php500 per vehicle per day. if an additional Service crew is added, What is the Expected or Total Cost (Waiting +Service Cost)?arrow_forwardThe manager of a car wash must decide whether to have one or two wash lines. One line will mean a fixed cost of $6,000 a month, and two lines will mean a fixed cost of $10,500 a month. Each line would be able to process 15 cars an hour. Variable costs will be $3 per car, and revenue will be $5.95 per car. The manager projects an average demand of between 14 and 18 cars anhour. Would you recommend one or two lines? The car wash is open 300 hours a month.arrow_forwardPristol, a food retailer, supplies food for vending machines at a university. As the machines are abused by university students, management has to repair them. The machines break down at an average of three per hour and the breakdowns are Poisson distributed. The downtime costs the company $25/hr and each maintenance worker earns $4/hr. One worker can service the machines at a rate of five per hour, exponentially distributed; two workers working together can service at seven per hour, exponentially distributed; and a crew of three can service at eight per hour, exponentially distributed. How large should the crew size be for optimal cost?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY