Concept explainers
A
Interpretation: The cycle time required for output rate needs to be determined.
Concept Introduction: Constraint management is a process helpful to the personnel on focusing the task. As a result, the productivity and the profits also increased.
B
Interpretation: The minimum number of workstations required needs to be determined.
Concept Introduction: Constraint management is a process helpful to the personnel on focusing the task. As a result, the productivity and the profits also increased.
C
Interpretation: The efficiency and the balance delay need to be determined.
Concept Introduction: Constraint management is a process helpful to the personnel on focusing the task. As a result, the productivity and the profit also increased.
D
Interpretation: Increasing cycle time would increase theoretical minimum
Concept Introduction: Constraint management is a process helpful to the personnel on focusing the task. As a result, the productivity and the profits also increased.
Want to see the full answer?
Check out a sample textbook solutionChapter 5 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
- An assembly plant for the Blood Pressure RX, a portable blood pressure device, has 400 minutes available daily in the plant for the device, and the average demand is 80 units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table. Task Performance Time (minutes) Task Must Follow Task Listed Below A 4 - B 1 - C 1 A, B D 3 C E 4 D F 2 E b) Given the demand, what is the cycle time for this operation? The cycle time for this operation is enter your response here minutes/unit (enter your response as a whole number). c) What is the theoretical minimum number of workstations? The theoretical minimum number of workstations is enter your response here stations (enter your response as a whole number and, if your unrounded answer includes decimal values,…arrow_forwardTailwind, Inc., produces high-quality but expensive training shoes for nmners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide morestability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 60. The information for the tasks is as follows: a) Draw the precedence diagram.b) Assign tasks to thl e minimum feasible number of workstations according to the "ranked positioned weight" decision rule.c) What is the efficiency of the process you completed in (b)?d) What is the idle time per cycle?arrow_forwardAlocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 90 toys. Times of the tasks are 2.73, 2.01, 2.13,2.0, 2.61,2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task Dand task E to be completed. Finally, task G can start only once task F is completed.What should be the calculated cycle time in minutes?- O a. None is correct O b. 4.80 Oc 5.33 O d. 6.00 O e. 4.50arrow_forward
- Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task Fneeds both task D and task E to be completed. Finally, task G can start only once task Fis completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are O a. A and B O b. None is the correct answer c. A only O d. A. B, and C О е. Вonlyarrow_forwardAlocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task Fneeds both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the estimated idle time in minutes for FIRST workstation? J. 1 a. 0,09 b. 1.85 C. 0.06 O d. None is the correct answer e. 1.00 Finisarrow_forwardGordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: Workpieces moved per week between work areas are: A C ABCD A A It costs Gordon $1 to move 1 work piece 1 foot. The weekly total material handling cost of the layout= $ (enter your response as a whole number). B T B 900 C 8 7 C 800 400 D 6 11 D 500 400 700 Darrow_forward
- How do bottlenecks increase the work in process inventory of manufacturing plants?arrow_forwardtion A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken out of according to longest task time first, What will the estimated idle time in minutes for THIRD workstation? O a. None is the correct answer O b. 0.06 O C. 1.00 d. 0.09 е. 1.85 NEXT PAGE EVIOUS…arrow_forwardAlocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performied. The daily demand is 150 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires taskA to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once taskFis completed.What is the minimum number of workstations needed?arrow_forward
- Capacity analysis can not be performed without determining bottleneck time and throughput time. Differentiate between these terms with suitable example?arrow_forwardDetermine the resources needed and cost for training of 200 sales agents for launching Project X, which has been decomposed in activities marketing training, ordering process training, and suitable training site. Training classes are eight hours long for activities A and B. The resources required for A and B include the following. One conference room for training, which can hold 10 trainees and one trainer. One marketing trainer and one ordering process trainer for a full day of training (i.e., four hours per day for each trainer). The cost for each trainer is $50 per hour. The cost of the training site is $100 per hour. Choose all the apply: 1. The marketing trainer is required for 20 session each four hours long. 2. The ordering process trainer is required for 20 session each four hours long. 3. The number of sessions required for activity A is 20 sessions. 4. The number of sessions required for ordering process training is 20 sessions. 5. The total cost for the…arrow_forwardThe resources (workers) and processing times (mins per unit) for 3 activities in a production system are shown below. Resources: Processing time: Activity 1 1- 2 worker A 12 min/unit Activity 2 1 worker B 5 min/unit Activity 3 4 worker C 15 min/unit a) What is the capacity (throughput) of each activity and the complete production system? Comment on how Activity A impacts on the entire system. b) What is the average WIP level when the system is at full capacity (apply Littles Law)?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.