Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9781259580093
Author: William J Stevenson
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Question
Chapter 4.S, Problem 22P
Summary Introduction
To determine: The most cost-effective option.
Introduction:
Mean time between failures (MTBF):
The mean time between failures is a term which denotes the time that is elapsed between the first failure of a product and the second failure of a product. It is calculated during the normal system operation.
Mean time to repair (MTTR):
The mean time to repair is the time incurred for a device to fail and also the time elapsed to repair the device. The repair is carried out after the failure of the device.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
In the context of system reliability, explain the difference between Mean Time Between Failures (MTBF) and Mean Time To Recovery (MTTR). How do these metrics impact system design?
The Management Department recently purchased a smallcopier for faculty use. Although the workload of the officestaff has improved somewhat, the secretaries are still making too many trips to the Dean’s office when the departmental copier is out of service. Sylvia, the departmentalsecretary, has been keeping track of failure rates and service times. With a mean time between failures of 100 hoursand a mean time to repair of 24 hours, how much of thetime is the new copier available for faculty use?
The diagram below identifies the elements of service as provided by a soft drink vending machine. Each element has an estimate of its own reliability, independent of the others. What is the reliability of the "system"?
Chapter 4 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Ch. 4.5 - Prob. 1.1RQCh. 4.5 - Prob. 1.2RQCh. 4.8 - LEGO A/S IN THE PINK Lego A/S overcame the recent...Ch. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.S - Prob. 1DRQCh. 4.S - Prob. 2DRQCh. 4.S - Prob. 3DRQCh. 4.S - Consider the following system: Determine the...Ch. 4.S - A product is composed of four parts. In order for...
Ch. 4.S - A system consists of three identical components....Ch. 4.S - A product engineer has developed the following...Ch. 4.S - The guidance system of a ship is controlled by a...Ch. 4.S - One of the industrial robots designed by a leading...Ch. 4.S - A production line has three machines A, B, and C,...Ch. 4.S - Prob. 8PCh. 4.S - A Web server has five major components that must...Ch. 4.S - Repeat Problem 9 under the condition that one of...Ch. 4.S - Hoping to increase the chances of reaching a...Ch. 4.S - An electronic chess game has a useful life that is...Ch. 4.S - A manufacturer of programmable calculators is...Ch. 4.S - Lucky Lumen light bulbs have an expected life that...Ch. 4.S - Prob. 15PCh. 4.S - Prob. 16PCh. 4.S - A major television manufacturer has determined...Ch. 4.S - Prob. 18PCh. 4.S - Determine the availability for each of these...Ch. 4.S - Prob. 20PCh. 4.S - A manager must decide between two machines. The...Ch. 4.S - Prob. 22PCh. 4.S - Auto batteries have an average life of 2.7 years....Ch. 4 - Prob. 1DRQCh. 4 - Prob. 2DRQCh. 4 - Prob. 3DRQCh. 4 - Prob. 4DRQCh. 4 - Prob. 5DRQCh. 4 - Prob. 6DRQCh. 4 - Prob. 7DRQCh. 4 - Prob. 8DRQCh. 4 - a. What is meant by the term life cycle? b. Why...Ch. 4 - Prob. 10DRQCh. 4 - Prob. 11DRQCh. 4 - Prob. 12DRQCh. 4 - Prob. 13DRQCh. 4 - Explain what quality function development is and...Ch. 4 - Prob. 15DRQCh. 4 - Prob. 16DRQCh. 4 - Prob. 17DRQCh. 4 - Prob. 18DRQCh. 4 - Prob. 19DRQCh. 4 - Describe some of the trade-off that are...Ch. 4 - Prob. 2TSCh. 4 - Prob. 3TSCh. 4 - Prob. 1CTECh. 4 - Prob. 2CTECh. 4 - Prob. 3CTECh. 4 - Prob. 4CTECh. 4 - Prob. 5CTECh. 4 - Give two examples of unethical conduct involving...Ch. 4 - Prob. 1PCh. 4 - Prob. 2PCh. 4 - Prepare a service blueprint for each of these...Ch. 4 - Prepare a service blueprint for each of these post...Ch. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prepare a table similar to that shown in Problem...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- What distinguishes six Sigma from traditional continuous improvement?arrow_forwardDiscuss the concept of Mean Time Between Failures (MTBF) and how it is calculated. Explain its limitations and alternatives for measuring system reliability.arrow_forwardFlextronchip, an OEM manufacturer, has a fifth-generation chip for cell phones, with chip specification of 0.2 ± 0.0002 mm for the distance between two adjacent pins. The loss due to a defective chip has been estimated as $28. Required: 1. Compute the value of k, the cost coefficient in the Taguchi quality loss function (QLF), L(x) = k(x − T)2. 2. Assume that the quality control manager takes a sample of 100 chips from the production process. The results are as follows: Measurement Frequency 0.1996 2 0.1997 6 0.1998 14 0.1999 9 0.2000 45 0.2001 9 0.2002 8 0.2003 5 0.2004 2 a. & b. Use the appropriate Taguchi quality loss function, L(x), to calculate the estimated quality loss for each of the observed measurements. Additionally, calculate the expected (i.e., average) loss per unit for the production process as a whole.arrow_forward
- Explain the terms MTTF (Mean Time To Failure) and MTTR (Mean Time To Repair) in the context of reliability.arrow_forwardFlextronchip, an OEM manufacturer, has a fifth-generation chip for cell phones, with chip specification of 0.2 ± 0.0002 mm for the distance between two adjacent pins. The loss due to a defective chip has been estimated as $20. Required: 1. Compute the value of k, the cost coefficient in the Taguchi quality loss function (QLF), L(x) = K(x- T)2. 2. Assume that the quality control manager takes a sample of 100 chips from the production process. The results are as follows: Measurement Frequency 0.1996 4 0.1997 7 0.1998 12 0.1999 11 0.2000 40 0.2001 10 0.2002 8 0.2003 5 0.2004 3 a. & b. Use the appropriate Taguchi quality loss function, L(x), to calculate the estimated quality loss for each of the observed measurements. Additionally, calculate the expected (i.e., average) loss per unit for the production process as a whole. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the value of k, the cost coefficient in the Taguchi quality loss…arrow_forwardEven after taking all appropriate steps to produce a high integrity system, some remaining faults will remain. How would you ensure system safety and reliability in practical approaches?arrow_forward
- 8) The diagram below identifies the elements of service as provided by a soft drink vending machine. Each element has an estimate of its own reliability, independent of the others. What is the reliability of the "system"? Couldht make change Wouldn't take my dollar bill Took my money Dispensed Dispensed Made Power failed Out of stock wong change .90 wrong beverage .95 warm beverage .98 .85 .995 .85 .98 .60arrow_forwardDiscuss the key factors that contribute to system reliability. What are some common challenges in achieving high system reliability?arrow_forwardWhat happens when the mean time between failures (MTTR) approaches zero? Is this a situation that can be adequately described?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY