Question
Chapter 4.S, Problem 20P
Summary Introduction
To determine: The availability of the machine.
Introduction:
Mean time between failures (MTBF):
The mean time between failures is a term which denotes the time that is elapsed between the first failure of a product and the second failure of a product. It is calculated during the normal system operation.
Mean time to repair (MTTR):
The mean time to repair is the time incurred for a device to fail and also the time elapsed to repair the device. The repair is carried out after the failure of the device.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A machine can operate for an average of 10 weeks before it needs to be overhauled, a process which takes two days. The machine is operated five days a week. Compute the availability of this machine. (Hint: All times must be in the same units.)
Answer is complete but not entirely correct.
A campus deli serves 300 customers over its busy lunch period from 11:30 am to
1:30 pm. A quick count of the number of customers waiting in line and being served
by the sandwich makers shows that an average of 7 customers are in process at any
point in time. What is the average amount of time that a customer spends in
process?
Instruction: Round your intermediate and final answer to 1 decimal place.
Average amount of time
(Round to one decimal)
4.9 8 minutes
4
Chapter 4 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 4.5 - Prob. 1.1RQCh. 4.5 - Prob. 1.2RQCh. 4.8 - LEGO A/S IN THE PINK Lego A/S overcame the recent...Ch. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.S - Prob. 1DRQCh. 4.S - Prob. 2DRQCh. 4.S - Prob. 3DRQCh. 4.S - Consider the following system: Determine the...Ch. 4.S - A product is composed of four parts. In order for...
Ch. 4.S - A system consists of three identical components....Ch. 4.S - A product engineer has developed the following...Ch. 4.S - The guidance system of a ship is controlled by a...Ch. 4.S - One of the industrial robots designed by a leading...Ch. 4.S - A production line has three machines A, B, and C,...Ch. 4.S - Prob. 8PCh. 4.S - A Web server has five major components that must...Ch. 4.S - Repeat Problem 9 under the condition that one of...Ch. 4.S - Hoping to increase the chances of reaching a...Ch. 4.S - An electronic chess game has a useful life that is...Ch. 4.S - A manufacturer of programmable calculators is...Ch. 4.S - Lucky Lumen light bulbs have an expected life that...Ch. 4.S - Prob. 15PCh. 4.S - Prob. 16PCh. 4.S - A major television manufacturer has determined...Ch. 4.S - Prob. 18PCh. 4.S - Determine the availability for each of these...Ch. 4.S - Prob. 20PCh. 4.S - A manager must decide between two machines. The...Ch. 4.S - Prob. 22PCh. 4.S - Auto batteries have an average life of 2.7 years....Ch. 4 - Prob. 1DRQCh. 4 - Prob. 2DRQCh. 4 - Prob. 3DRQCh. 4 - Prob. 4DRQCh. 4 - Prob. 5DRQCh. 4 - Prob. 6DRQCh. 4 - Prob. 7DRQCh. 4 - Prob. 8DRQCh. 4 - a. What is meant by the term life cycle? b. Why...Ch. 4 - Prob. 10DRQCh. 4 - Prob. 11DRQCh. 4 - Prob. 12DRQCh. 4 - Prob. 13DRQCh. 4 - Explain what quality function development is and...Ch. 4 - Prob. 15DRQCh. 4 - Prob. 16DRQCh. 4 - Prob. 17DRQCh. 4 - Prob. 18DRQCh. 4 - Prob. 19DRQCh. 4 - Describe some of the trade-off that are...Ch. 4 - Prob. 2TSCh. 4 - Prob. 3TSCh. 4 - Prob. 1CTECh. 4 - Prob. 2CTECh. 4 - Prob. 3CTECh. 4 - Prob. 4CTECh. 4 - Prob. 5CTECh. 4 - Give two examples of unethical conduct involving...Ch. 4 - Prob. 1PCh. 4 - Prob. 2PCh. 4 - Prepare a service blueprint for each of these...Ch. 4 - Prepare a service blueprint for each of these post...Ch. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prepare a table similar to that shown in Problem...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Navern Corporation manufactures and sells custom home elevators. From the time an order is placed until the time the elevator is installed in the customer's home averages 141 days. The 141 days are spent as follows: Wait time Inspection time Process time Move time Queue time What is Navern's manufacturing cycle efficiency (MCE) for its elevators? Multiple Choice O O 41.1% 30.4% 58.9% 29 days 24 days 34 days 31 days 23 days 57.4%arrow_forwardWhat is the bottleneck cycle time of this process (seconds/customer)? What is the raw processing time (T0) of this process?arrow_forwardPlease do not give solution in image format thanku The flow rate through a process is 0.5 flow units per minute. The number waiting for the process is 1. The time to do the activity in the process is 1 minute. This is a stable system. The average amount of time a flow unit spends waiting for the activity and doing the activity = ______. Enter one integer (which can be 0) and ONE decimal, so the answer looks like X.X. Any of the Xs can be a 0.arrow_forward
- Blue Lotus is a bike shop located near a beach resort, which rents its bikes to guests staying in the resort. When a customer requests to rent a bike and no bikes are available (they are either with another customers or being cleaned for rental), customer waits until a bike is available. Once a bike rented out to a customer, the customer keeps it for an average of 1 day. Upon return, the bike is cleaned and tuned-up, which takes half a day (0.5 day). Suppose Blue Lotus has 7 bikes, and demand for bike rental is 4.1 per day. What is the average amount of time a customer waits to receive a bike? (Hint: From the perspective of customer waiting time, 0.5 day of cleaning time would be part of the processing time" so, p = 1+0.5 =1.5 days. Assume CVa = CVp = 1 in your calculations). O 1.197 days O2.134 days O 0.761 days O 5.380 daysarrow_forwardGive typed full explanationarrow_forwardPerformance Evaluation and Risk Aversion Jill Lewis is the office manager of PureBreds Inc.Her office has 30 employees whose collective job is to process applications by dog owners whowant to register their pets with the firm. There is never a shortage of applications waiting to be processed, but random events beyond Lewis’s control (e.g., employees out sick) cause fluctuations inthe number of applications that her office can process. Jill is aware that it is important that the applications be processed quickly and accurately. Alex Zale, the district manager to whom Jill reports,bases his evaluation of Jill on the number of applications that are processed.Required1. If Jill is risk averse, how should Alex compensate her? Why?a. Flat salary.b. Straight commission based on the number of applications processed.c. Flat salary with a bonus based on the number of applications processed.d. Flat salary with a bonus based on the firm’s earnings.2. What is a disadvantage of an evaluation method…arrow_forward
- Please answer only the last two bullet points!!arrow_forward19-33 Waiting times, manufacturing cycle times. The IVplast Corporation uses an injection molding ma- chine to make a plastic product, Z39, after receiving firm orders from its customers. IVplast estimates that it will receive 40 orders for Z39 during the coming year. Each order of Z39 will take 120 hours of machine time. The annual machine capacity is 6,800 hours. 1. Calculate (a) the average amount of time that an order for Z39 will wait in line before it is processed and (b) the average manufacturing cycle time per order for Z39.arrow_forwardHammond Inc. has analyzed the setup time on its computer-controlled lathe. The setup requires changing the type of fixture that holds a part. The average setup time has been 135 minutes, consisting of the following steps: Step Time (in minutes) Turn off machine and remove fixture from lathe 13 Go to tool room with fixture 15 Record replacement of fixture to tool room 18 Return to lathe 20 Clean lathe 17 Return to tool room 20 Record withdrawal of new fixture from tool room 12 Return to lathe 15 Install new fixture and turn on machine 8 Total setup time 138 Why should management be concerned about improving setup time? What do you recommend to Hammond Inc. for improving setup time? How much time would be required for a setup, using your suggestion in (b)?arrow_forward
- A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used 6 workers, who together produced an average of 80 carts per hour. Workers receive $18 per hour, and machine cost was $40 per hour. With the new equipment, it was possible to transfer one of the workers to another department, and equipment cost increased by $10 per hour, while output increased by 5 carts per hour. Comment on the changes in productivity according to the two measures. (Round your intermediate calculations to 3 decimal places and final answers to 2 decimal places.) Labor Productivity increased by ____% Multifactor productivity increased by ___%arrow_forwardMr. K’s is a very popular hair salon. It offers high quality hairstyling andphysical relaxation services at a reasonable price, so it always has unlimiteddemand. The service process includes five activities that are conducted inthe sequence described below ( the time required for each activity is shownin parenthesis):Activity 1: Welcome a guest and offer homemade herb tea (10 minutes)Activity 2: Wash and condition har (10 minutes)Activity 3: Neck, shoulder, and back stress release massage (10 minutes)Activity 4: Design and hair style and do the hair (25 minutes)Activity 5: Ring up the guest bill (5 minutes)Each activity has one employee dedicated to it. For the following questions,assume unlimited demand. Also assume that the employee at activity 1 onlyadmits new guests at the rate of the bottleneck.(a) Which resource is the bottleneck?(b) What is the capacity of the process?(c) What is the flow rate?(d) What is the utilization of the employee at activity 3(e) What is the cycle time?arrow_forwardPlease answer question 2 another image for referencearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.