Concept explainers
a)
To determine: The way to minimize the bus company’s costs over the period of next five years.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
a)
Explanation of Solution
Model:
Solver input:
The solver input is selected from under the “Data” tab in Excel and the input is given as shown below:
Formula:
The total cost is $3,420,000.
b)
To use: The solver table to determine the .change in the total number of hired, fired, total cost change due to the change in unit hiring, firing where each of them increases by the same percentage.
Linear programming:
It is a mathematical modeling procedure where a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
b)
Explanation of Solution
One-way solver table:
The one-way solver table is selected and the input is given as shown below:
Output:
In the given range of percent increases, the total of hired and fired does not change. But, the cost increases.
Want to see more full solutions like this?
Chapter 4 Solutions
EBK PRACTICAL MANAGEMENT SCIENCE
- A political party is planning a ninety-minute television show. The show will have at least 9 minutes of direct requests for money from viewers. Three of the party's politicians will be on the show- a senator, a congresswoman, and a governor. The senator, a party "elder statesman," demands that he be on screen for at least twice as long as the governor. The total time taken by the senator and the governor must be at least twice the time taken by the congresswoman. Based on a pre-show survey, it is believed that 37, 41, and 45 (in thousands) viewers will watch the program for each minute the senator, congresswoman, and governor, respectively, are on the air. Find the time that should be allotted to each politician in order to get the maximum number of viewers. Find the maximum number of viewers. The quantity to be maximized, z, is the number of viewers in thousands. Let x, be the total number of minutes allotted to the senator, × be the total number of minutes allotted to the…arrow_forwardA catering company must have the following number of clean napkins available at the beginning of each of the next four days: day 1: 15, day 2: 12, day 3: 18, and day 4: 6. After being used, a napkin can be cleaned by one of two methods: fast service or slow service. Fast service costs $0.10 per napkin, and a napkin cleaned via fast service is available for use the day after it is last used. Slow service costs $0.06 per napkin, and a napkin cleaned via slow service is available two days after they were last used. New napkins can be purchased for a cost of S0.20 per napkin. Part A: Formulate the problem as a minimum cost transportation problem. Part B: Solve the problem (provide exact values for all variables and the optimal objective function).arrow_forwardA trust officer at the Blacksburg National Bank needs to determine how to invest $150,000 in the following collection of bonds to maximize the annual return. Bond Annual Return Maturity Risk Tax Free A 9.5% Long High Yes B 8.0% Short Low Yes C 9.0% Long Low No D 9.0% Long High Yes E 9.0% Short High No The officer wants to invest at least 40% of the money in short-term issues and no more than 20% in high-risk issues. At least 25% of the funds should go in tax-free investments, and at least 45% of the total annual return should be tax free. Formulate the LP model for this problem. Create the spreadsheet model and use Solver to solve the problem. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- Long-Life Insurance has developed a linear model that it uses to determine the amount of term life Insurance a family of four should have, based on the current age of the head of the household. The equation is: y=150 -0.10x where y= Insurance needed ($000) x = Current age of head of household b. Use the equation to determine the amount of term life Insurance to recommend for a family of four of the head of the household is 40 years old. (Round your answer to 2 decimal places.) Amount of term life insurance thousandsarrow_forwardRaghubhaiarrow_forwardA trust officer at the Blacksburg National Bank needs to determine how to invest $100,000 in the following collection of bonds to maximize the total annual return (before tax). Bond Annual Return Maturity Risk Tax-Free A 9.5% Long High Yes B 8.0% Short Low Yes C 9.0% Long Low No D 9.0% Long High Yes E 9.0% Short High No The officer wants to invest as least 50% of the money in short-term issues and no more than 50% in high-risk issues. At least 30% of the funds should go in tax-free investments, and at least 40% of the total annual return should be tax free. Suppose the decision variable represents the amount of money invested in bond for . Formulate a linear programming (LP) model to solve the optimal strategy. 1. Write down the constraint using the defined decision variables requiring “invest as least 50% of the money in short-term issues”. 2. Write down the constraint using the defined decision…arrow_forward
- A farm consists of 600 acres of land, of which 500 acres will be planted with corn, soybeans, and wheat, according to these conditions: At least half of the planted acreage should be in corn No more than 200 acres should be soybeans The ratio of corn to wheat planted should be 2:1 It costs $20 an acre to plant corn, $15 an acre to plant soybeans, and $12 an acre to plant wheat Formulate this problem as an LP model that will minimize planting cost while achieving the specified conditions.arrow_forwardIn an oil company, its south refinery produces per day 300 barrels of high grade oil, 200 barrels of medium grade oil and 150 barrels of low grade oil. The cost of operation of this refinery amounts to P 600,000 per day. The north refinery of the company produces each day 100 barrels of high grade oil and 100 barrels of medium-grade oil and 150 of low-grade oil. Which has a total of P500,000 operational costs. If the company’s production requirement is at least 900 barrels for high-grade oil, 800 barrels for medium-grade oil, and 750 for low-grade oil, how many days, are required for each refinery to operate to obtain the minimum cost?arrow_forwardA company makes three types of candy and packages them in three assortments. Assortment I contains 4 cherry, 4 lemon, and 12 lime candies, and sells for a profit of $4.00. Assortment Il contains 12 cherry, 4 lemon, and 4 lime candies, and sells for a profit of $3.00. Assortment III contains 8 cherry, 8 lemon, and 8 lime candies, and sells for a profit of $5.00. They can make 5,200 cherry, 4,000 lemon, and 6,000 lime candies weekly. How many boxes of each type should the company produce each week in order to maximize its profit (assuming that all boxes produced can be sold)? What is the maximum profit? Select the correct choice below and fill in any answer boxes within your choice. OA. The maximum profit is $ when boxes of assortment 1. boxes of assortment II and assortment III are produced. OB. There is no way for the company to maximize its profit boxes ofarrow_forward
- A company makes four products that have the following characteristics: Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 of materials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for $135 but needs $105 of materials to produce. The processing requirements for each product on each of the four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardless of how much the worker is used. Answer the following…arrow_forwardA company manufactures two types of products. Each product type needs a turning process at the lathe and a milling process at the milling machine. If the lathe is used for type 1 products only, it can process 500 units in a day. If the lathe is used for type 2 products only, it can process 300 units in a day. If the milling machine is used for type 1 products only, it can proces 900 units in a day. If the milling machine is used for type 2 products only, it can process 450 units in a day. The unit profits for product types 1 and 2 are $50 and $75, respectively. Formulate an LP that will maximize the company's daily profit. (a) Decision variables? (b) Objective and objective function? (c) Constraints?arrow_forwardA political party is planning a half-hour television show. The show will have at least 3 minutos of direct requests for money from viowers Three of the party's politicians will be on the show-a senator, a congresswoman, and a governor The senator, a party "elder statesman," demands that he be on screen for at least twice as long as the governor The total time taken by the senator and the governor must be at least twice the time taken y the congresswoman Based on a pre-show survey, it is believed that 33, 38, and 43 (in thousands) viewers will watch the program for each minute the senator, congresswoman, and governor, respectively, are on the air. Find the time that should be allotted to each politician in order to get the maximum number of viewers Find the maximum number of viewers The quantity to be maximized, z, is the number of viewers in thousands. Let x, be the total number of minutes allotted to the senator, x, be the total number of minutes allottod to the congresswoman, and x,…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,