Practical Management Science
Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
bartleby

Concept explainers

Question
Book Icon
Chapter 3, Problem 38P

a)

Summary Introduction

To determine: The way the company can minimize the cost of meeting the month’s requirement.

Introduction: In linear programming, the unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints, then it is said to be an unfeasible solution.

b)

Summary Introduction

To investigate: The effect on ending inventory during the four-quarter period of systematic changes in the unit holding cost.

Introduction: In linear programming, the unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints, then it is said to be an unfeasible solution.

Blurred answer
Students have asked these similar questions
A company has one machine which can be used to make product Alpha and product Beta. Each unit of product Alpha requires 45 minutes of machine time, while each unit of product Beta requires 37 minutes of machine time. The machine can be used for 8 hours per day and 5 days per week. Next week the company will produce 23 units of product Alpha. After completing the production of Alpha, the company will produce product Beta. How many units of product Beta can be produced next week? Use at least 4 decimals.You must showm your calculation steps and brief explanation on your Excel spreadsheets.
FRUIT COMPUTER COMPANY Fruit Computer Company manufactures memory chips in batches of ten chips. From past experience, Fruit knows that 80% of all batches contain 10% (1 out of 10) defective chips, and 20% of all batches contain 50% (5 out of 10) defective chips. If a good (that is, 10% defective) batch of chips is sent to the next stage of production, processing costs of $4000 are incurred, and if a bad batch (50% defective) is sent on to the next stage of production, processing costs of $16000 are incurred. Fruit also has the alternative of reworking a batch at a cost of $4000. A reworked batch is sure to be a good batch. Alternatively, for a cost of $400, Fruit can test one chip from each batch in an attempt to determine whether the batch is defective.   QUESTIONS 1.Determine a strategy so Fruit can minimize the expected total cost per batch. 2.Compute the EVSI and EVPI.
A roller coaster is being designed for a new theme park. Two "trains" are on the track at any given time. One train is being unloaded/reloaded while the other is moving along the track. The track itself takes 10 minutes to complete. The train being loaded should depart before the arriving train is no closer than one minute away. Each car of a train accommodates four people. Loading a car is estimated to take 6 seconds per passenger. Unloading is estimated to take 6 seconds per passenger. Suppose that (unlike actual roller coasters), only one car can be loaded or unloaded at a time. Unloading can NOT occur at the same time as loading. In order to maximize the number of potential passengers, how many cars should the train be made up of? Round your answer to the nearest whole car.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,