Chapter 3, Problem 38P
a)
Summary Introduction
To determine: The way the company can minimize the cost of meeting the month’s requirement.
Introduction: In linear programming, the unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints, then it is said to be an unfeasible solution.
b)
Summary Introduction
To investigate: The effect on ending inventory during the four-quarter period of systematic changes in the unit holding cost.
Introduction: In linear programming, the unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints, then it is said to be an unfeasible solution.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A company has one machine which can be used to make product Alpha and product Beta.
Each unit of product Alpha requires 45 minutes of machine time, while
each unit of product Beta requires 37 minutes of machine time.
The machine can be used for 8 hours per day and 5 days per week.
Next week the company will produce 23 units of product Alpha.
After completing the production of Alpha, the company will produce product Beta.
How many units of product Beta can be produced next week?
Use at least 4 decimals.You must showm your calculation steps and brief explanation on your Excel spreadsheets.
FRUIT COMPUTER COMPANY
Fruit Computer Company manufactures memory chips in batches of ten chips. From past experience, Fruit knows that 80% of all batches contain 10% (1 out of 10) defective chips, and 20% of all batches contain 50% (5 out of 10) defective chips. If a good (that is, 10% defective) batch of chips is sent to the next stage of production, processing costs of $4000 are incurred, and if a bad batch (50% defective) is sent on to the next stage of production, processing costs of $16000 are incurred. Fruit also has the alternative of reworking a batch at a cost of $4000. A reworked batch is sure to be a good batch. Alternatively, for a cost of $400, Fruit can test one chip from each batch in an attempt to determine whether the batch is defective.
QUESTIONS
1.Determine a strategy so Fruit can minimize the expected total cost per batch.
2.Compute the EVSI and EVPI.
A roller coaster is being designed for a new theme park. Two "trains" are on the track
at any given time. One train is being unloaded/reloaded while the other is moving
along the track. The track itself takes 10 minutes to complete. The train being loaded
should depart before the arriving train is no closer than one minute away.
Each car of a train accommodates four people. Loading a car is estimated to take 6
seconds per passenger. Unloading is estimated to take 6 seconds per passenger.
Suppose that (unlike actual roller coasters), only one car can be loaded or unloaded
at a time. Unloading can NOT occur at the same time as loading.
In order to maximize the number of potential passengers, how many cars should the
train be made up of? Round your answer to the nearest whole car.
Chapter 3 Solutions
Practical Management Science
Ch. 3.6 - Prob. 1PCh. 3.6 - Prob. 2PCh. 3.6 - Prob. 3PCh. 3.6 - Prob. 4PCh. 3.6 - Prob. 5PCh. 3.6 - Prob. 6PCh. 3.6 - Prob. 7PCh. 3.6 - Prob. 8PCh. 3.6 - Prob. 9PCh. 3.7 - Prob. 10P
Ch. 3.7 - Prob. 11PCh. 3.7 - Prob. 12PCh. 3.7 - Prob. 13PCh. 3.7 - Prob. 14PCh. 3.7 - Prob. 15PCh. 3.7 - Prob. 16PCh. 3.7 - Prob. 17PCh. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - Prob. 21PCh. 3.8 - Prob. 22PCh. 3.8 - Prob. 23PCh. 3.8 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 31PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 35PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Prob. 41PCh. 3 - Prob. 42PCh. 3 - Prob. 43PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Prob. 48PCh. 3 - Prob. 49PCh. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - Prob. 52PCh. 3 - Prob. 1C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company makes four products that have the following characteristics: Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 of materials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for $135 but needs $105 of materials to produce. The processing requirements for each product on each of the four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardless of how much the worker is used. Answer the following…arrow_forwardA machine part to be fabricated may be made from alloy of either of two metals. There is an order for 10,000 units. Metal A costs 3 pesos per kg, while Metal B costs 9 pesos per kg. If Metal A is used, the material per unit weighs 110 grams; for metal B, 30 grams. When metal A is used, 50 units can be produced per hour; for metal B, 80 units per hour. Metal B fabrication requires the aid of a tool costing P1,000, which will be useless after the 10,000 units are finished. The machine operator's wage is P50 per hour. If all other costs are identical, determine which material will be more economical to finish the 10,000-unit order. How much is the total cost difference between the use of metal A and metal B?arrow_forwardYou work for a small shipping company and warehouse. The owners have decided to update the software used for tracking, shipping, receiving, and inventory. Fifteen computers need to be updated. Hours of operation are 7 a.m. to 7 p.m. Monday through Saturday. Each computer must be updated manually by one of two trained employees, both of whom must be borrowed from other managers. The update procedure consumes 4 hours of the updater's time and generates an additional 1.5 hours of computer downtime. The work must be performed at a central loading station, away from the current location of the computer. How does the project portfolio management approach lead to enhanced strategic management for an organization and give an example how you woulduse this in a work place?arrow_forward
- According to the XYZ Apartment Rental Company ER diagram, which of the following is true? Each building must have more than one builder Each building must have multiple apartments Each building must have at least 8 apartments Each building must have more than 2 apartments Answer: ____arrow_forwardProducts A,B, and C are sold door-to-door. A costs $ 3 per unit, take 10 minutes to sell (on the average) and costs $0.50 to deliver to customer. B costs $ 5, takes 15 minutes to sell, and is left with the customer at the time of sale. C costs $ 4, takes 12 minutes to sell, and costs $ 1 to deliver. During any week, a salesperson is allowed to draw up to $ 500 worth of A,B,C (at cost) and is allowed delivery expenses not to exceeds $ 75. If a salesperson’s selling time is not expected to exceed 30 hours (1,800 minutes) in a week, and if the salesperson profit (net after all expenses) is $ 1 each on a unit of A and B and $ 2 on a unit of C, what combination of sales of A, B, and C will lead to maximum profit, and what is the maximum profIt?arrow_forwardA company that operated 10 hours a day manufactures two products on three sequential processes. The following table summarizes the data for the problem: Product Process 1 10 Process 2 20 Process 3 8 10 Unit Profit 20 30 Which of the following is the most appropriate representation for variables x and y for the given situation? x is the # of units of Product 1 to be procured; y is the # of units of Product 2 to be procured. x is the # of units of Product 1 to be stored; y is the # of units of Product 2 to be stored x is the # of units of Product 1 to be delivered, y is the # of units of Product 2 to be delivered. x is the # of units of Product 1 to be produced; y is the # of units of Product 2 to be produced. minutesarrow_forward
- A company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the bottleneck method,…arrow_forwardA company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Question: 1. Which Process…arrow_forwardA company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the traditional…arrow_forward
- A company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the bottleneck method,…arrow_forwardA company makes four products that have the following characteristics:Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 ofmaterials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for$135 but needs $105 of materials to produce. The processing requirements for each product on each ofthe four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setuptime when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In thequestions that follow, the traditional method refers to maximizing the contribution margin per unit foreach product, and the bottleneck method refers to maximizing the contribution margin per minute at thebottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardlessof how much the worker is used. Using the bottleneck method,…arrow_forwardThere are two companies manufacturing drones. Company A manufactures mass market drones, while company B manufactures customised drones according to customers’ requirements. In 2020, company A produces 3,200 drones, 3% of which were found to be defective and cannot pass the quality check. Company A employs 5 workers working an average of 8 hours a day in the drone production, and they worked 200 working days in 2020.In contrast, company B produces 900 drones, 10% of which were found to be defective and cannot pass the quality check. Company B employs 3 workers working an average of 6 hours a day in the drone production, and they worked 170 days in 2020. (a) If the drone manufacturing is seen as a process, what is considered as the output of the production processes of companies A and B and why? (b) Measure the single-factor manpower productivity for the two companies. (c) Is it reasonable to compare the manpower productivity of the two companies and reach a conclusion that one company…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,