Question
Chapter 3, Problem 27P
Summary Introduction
To draw: The pattern test to find any type of non-random patterns.
Introduction:
Pattern test is summarized as a study of patterns in the observations. The fundamental objective of this is the recognition of any type of pattern which contain any non-randomness in nature. It concentrates on whole patterns and find out where any change shows any continuity or sustainability.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the diameter is a critical factor
that must be controlled. From sample sizes of 5 pistons produced each day, the mean and the range of this diameter have
been as follows:
Day
Mean (mm)
Range R (mm)
158
4.3
151.2
4.4
155.7
4.2
153.5
4.8
156.6
4.5
What is the UCL using 3-sigma?(round your response to two decimal places).
1.
2.
4.
At Webster Chemical Company, lumps in the caulking compound could cause difficulties in dispensing a smooth bead from the tube. Testing for the presence of lumps destroys the product, so an analyst takes random samples. The following results are obtained:
Tube No.
Lumps
Tube No.
Lumps
Tube No.
Lumps
1
6
5
6
9
0
2
7
6
5
10
5
3
2
7
5
11
2
4
4
8
8
12
3
Determine the c-chart
two-sigma
upper and lower control limits for this process. Is the process in statistical control?
The
UCLc
equals
------
and the
LCLc
equals
------
(Enter
your responses rounded to two decimal
places.)
A production manager at a Contour Manufacturing planthas inspected the number of defective plastic molds in 5 randomsamples of 20 observations each. Following are the number ofdefective molds found in each sample:
Construct a 3-sigma control chart (z = 3) with this information
Chapter 3 Solutions
Operations and Supply Chain Management 9th edition
Ch. 3.S - Prob. 1QCh. 3.S - Prob. 2QCh. 3.S - Prob. 3QCh. 3.S - Prob. 4QCh. 3.S - Prob. 5QCh. 3.S - Prob. 6QCh. 3.S - Prob. 7QCh. 3.S - The Great Lakes Company, a grocery store chain,...Ch. 3.S - Prob. 2PCh. 3.S - Prob. 3P
Ch. 3.S - The Fast Break Computer Company assembles personal...Ch. 3.S - Prob. 5PCh. 3 - Using Sampling and Statistics to Analyze...Ch. 3 - Prob. 2.1ASCCh. 3 - Prob. 3.1ASCCh. 3 - Prob. 4.1ASCCh. 3 - Prob. 5.1ASCCh. 3 - Prob. 1QCh. 3 - Prob. 2QCh. 3 - Prob. 3QCh. 3 - Prob. 4QCh. 3 - Prob. 5QCh. 3 - Prob. 6QCh. 3 - Prob. 7QCh. 3 - Prob. 8QCh. 3 - Prob. 9QCh. 3 - Prob. 10QCh. 3 - Prob. 11QCh. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 5PCh. 3 - Prob. 6PCh. 3 - Prob. 7PCh. 3 - Prob. 8PCh. 3 - Prob. 9PCh. 3 - Prob. 10PCh. 3 - Prob. 11PCh. 3 - Prob. 12PCh. 3 - Prob. 13PCh. 3 - Prob. 14PCh. 3 - Prob. 15PCh. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - Prob. 18PCh. 3 - Prob. 20PCh. 3 - Prob. 21PCh. 3 - Prob. 22PCh. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Elon Corporation manufactures parts for an...Ch. 3 - Prob. 42PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Metropolitan General Hospital is a city-owned...Ch. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - The Shuler Motor Mile is a high-volume discount...Ch. 3 - Prob. 1.1CPCh. 3 - Prob. 2.1CPCh. 3 - Improving Service Time at Daves Burgers Daves...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Road King Tire Company in Birmingham wants to moni-tor the quality of the tires it manufactures. Each day the com-pany quality-control manager takes a sample of 100 tires, tests them, and determines the number of defective tires. The re-sults of 20 samples have been recorded as follows:Construct a p-chart for this process using 2 limits and for each of the last 30 weekdays are shown as follows:describe the variation in the process. Sample Defectives Sample Defectives1 14 11 182 12 12 103 9 13 194 10 14 205 11 15 176 7 16 187 8 17 188 14 18 229 16 19 2410 17 20 23arrow_forwardBoxes of Honey-Nut Oatmeal are produced tocontain 14 ounces, with a standard deviation of .1 ounce. Setup the 3-sigma x-chart for a sample size of 36 boxes.arrow_forwardThe objective of statistical process control (SPC) is to: Determine whether a batch of raw materials should be accepted or rejected. Determine whether a batch of finished goods should be accepted or rejected. Detect assignable cause variations versus normal random variations in the process. Identify variable versus attribute measures.arrow_forward
- mq3arrow_forward4. Organic Grains LLC uses statistical process control to ensure that its health-conscious, low-fat, multigrain sandwich loaves have the proper weight. Based on a previously stable and in-control process, the control limits of the x- and R-charts are: UCLx = 5.35, LCLx = 4.93; UCLR = 0.894, LCLR = 0. Over the past few days, they have taken five random samples of four loaves each and have found the following: Net Weight Sample Loaf # 1 Loaf # 2 Loaf # 3 Loaf # 4 1 4.9 5.2 5.1 5.0 2 5.3 5.1 5.2 5.3 3 4.9 5.2 4.9 5.2 4 5.5 5.5 5.3 5.5 5 5.3 5.2 5.3 5.0 Part 2 Based on the x-chart, is one or more samples beyond the control limits? ▼ No Yes .arrow_forwardTelephone inquiries of 100 IRS "customers" aremonitored daily at random by Xiangling Hu. Incidents of incorrectinformation or other nonconformities (such as impolitenessto customers) are recorded. The data for last week follow: a) Construct a 3-standard deviation c-chart of nonconformities.b) What does the control chart tell you about the IRS telephoneoperators?arrow_forward
- 6 of 11 5 3. The manager of a building-supplies company randomly samples incoming lumber to see whether it meets quality specifications. From each shipment, 100 pieces of 2 x 4 lumber are inspected and judged according to whether they are first (acceptable) or second (defective) grade. The proportions of second-grade 2 x 4s recorded for 30 shipments were as follows: a. Construct a control chart for the proportion of second-grade 2 x 4s in samples of 100 pieces of lumber. b. Explain how the control chart can be of use to the manager of the building supplies company. Shipment No. Proportion of second grade 1 0.14 2 0.22 3 0.21 4 0.15 0.19 0.26 7 0.18 8 0.22 9 0.23 10 0.21 11 0.2 12 0.14 13 0.25 14 0.2 15 0.19 16 0.18 17 0.22 18 0.22 19 0.17 20 0.21 21 0.21 22 0.13 23 0.15 24 0.2 25 0.23 26 0.23 27 0.12 28 0.19 29 0.19 30 0.26arrow_forwarddiscuss how to construct process control chart and use them to determine whether a process is out of statistical control?arrow_forwardThe time to replace vehicle wiper blades at a service center was monitored using a mean and a rangechart. Six samples of n = 20 observations were obtained and the sample means and ranges computed:Sample Mean Range Sample Mean Range1 3.06 .42 4 3.13 .462 3.15 .50 5 3.06 .463 3.11 .41 6 3.09 .45 a. Using the factors in Table 10.3, determine upper and lower limits for mean and range charts.b. Is the process in control?arrow_forward
- A garment manufacturer wants to set up a control chart for irregularities. Each week a random sample of 25 garments is collected from production and the number of irregularities is recorded. The table below gives the results for the past 20 weeks: 1 6 8 10 Sample Number Irregularities 11 2 3 4 5 7 9 8 12 4 16 5 8 17 10 11 16 20 Sample Number | Irregularities 11 12 13 14 15 17 18 19 7 12 13 8 17 11 9 10 (a) Using the data set up an appropriate control chart using a three sigma control limits. (b) Comment on the process. [8 marks] [2 marks] 9,arrow_forwardThe production manager at Sunny Soda, Inc., is interested in tracking the quality of the company's 12-ounce bottle filling line. The bottles must be filled within the tolerances set for this product because the dietary information on the label shows 12 ounces as the serving size. The design standard for the product calls for a fill level of 12±0.10 ounces. The manager collected the accompanying sample data (in fluid ounces per bottle) on the production process. Click the icon to view the sample data. Click the icon to view the table of factors for calculating three-sigma limits for the xachaR-chart. Design an R- and an x-chart for this process. The UCLR equals 0.371 ounces and the LCLR equals 0.000 ounces. (Enter your responses rounded to three decimal places.) The UCL equals 12.115 ounces and the LCL equals 11.878 ounces. (Enter your responses rounded to three decimal places.) a. Are the process average and range in statistical control? The process average is in statistical control…arrow_forwardBreeze Toothpaste Company has been having a problemwith some of the tubes of toothpaste leaking. The tubes are packedin containers with 100 tubes each. Ten containers of toothpastehave been sampled. Th e following number of toothpaste tubeswere found to have leaks: Develop a p-chart with 3-sigma control limits and evaluatewhether the process is in statistical control.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.