Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 3, Problem 19P

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:

Chapter 3, Problem 19P, Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned

a) Determine the expected completion time and variance for each activity.

b) Determine the total project completion time and the critical path for the project.

c) Determine ES, EF, LS, LF, and slack for each activity.

d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?

a)

Expert Solution
Check Mark
Summary Introduction

To determine:The expected completion time and variance of the various activities.

Introduction:

The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:

  • Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
  • Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
  • Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.

Answer to Problem 19P

The expected times and standard deviations for the following six activities are shown in Table 1.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Formula:

The expected time “t” would be calculated by the formula shown below.

t=(a+4m+b)6

where “a” is the optimistic time, “b” is the pessimistic time and “m” is the most realistic time.

The variance denoted by σ2 is calculated by using the formula shown below.

Variance=(b-a6)2

Calculation of expected completion time and variance of the various activities:

Use the above formulas to obtain the expected completion time and the variance for the various activities, as shown below.

Unit=number of days

Activity a m b t Immediate predecessor t SD Variance
A 3 6 8 8 5.83 0.83 0.69
B 2 4 4 4 3.67 0.33 0.11
C 1 2 3 3 2.00 0.33 0.11
D 6 7 8 8 C 7.00 0.33 0.11
E 2 4 6 6 B,D 4.00 0.67 0.44
F 6 10 14 14 A,E 10.00 1.33 1.78
G 1 2 4 4 A,E 2.17 0.50 0.25
H 3 6 9 9 F 6.00 1.00 1.00
I 10 11 12 12 G 11.00 0.33 0.11
J 14 16 20 20 C 16.33 1.00 1.00
K 2 8 10 10 H,I 7.33 0.00

Table 1

Excel worksheet:

Principles Of Operations Management, Chapter 3, Problem 19P , additional homework tip  1

Hence, the expected times and standard deviations for the following six activities are shown in Table 1

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The critical path and the project completion time.

Answer to Problem 19P

The longest path is CàDàEàFàHàK which is the critical path and the project completion time is 36.33 days.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Calculation of critical path and the project completion time:

The AON project network diagram with the precedence relationships of various activities is shown below,

Principles Of Operations Management, Chapter 3, Problem 19P , additional homework tip  2

The various project paths from the above diagram and the path durations are in Table 1.

  • AàFàHàK, path accounting for a duration of 5.83+10+6+7.33=29.16days
  • Path AàGàIàK accounting for a duration of 5.83+2.17+11+7.33=26.33days
  • Project path BàEàFàHàK accounting for a duration of 3.67+4+10+6+7.33=31days
  • Project path BàEàGàIàK accounting for a duration of 3.67+4+2.17+11+7.33=28.17days .
  • Project path CàDàEàGàIàK accounting for a duration of 2+7+4+2.17+11+7.33=33.50days
  • Project path CàDàEàFàHàK accounting for a duration of 2+7+4+2.17+10+6+7.33=36.33days .
  • Project path CàJ accounting for a duration of 2+16.33=18.33days

The longest path is CàDàEàFàHàK and is the critical path. Therefore, the project completion time is 36.33days.

Hence, The critical path is CàDàEàFàHàK and the project completion time is 36.33 days.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: Early start, Early finish, Late start, Late finish and slack for each activity.

Answer to Problem 19P

The Early start, Early finish, Late start, Late finish and slack for each activity is shown in Table 2.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Calculation of Early start, Early finish, Late start, Late finish and slack for each activity:

The AON diagram along with the time duration for each project activity is shown below.

Principles Of Operations Management, Chapter 3, Problem 19P , additional homework tip  3

Slack activity can be calculated by finding the difference LS-ES or LF-EF. ES, EF, LS and LF for the project as shown in the table below.

Principles Of Operations Management, Chapter 3, Problem 19P , additional homework tip  4

Table 2

The slack for each activity is shown in the above table

CàDàEàFàHàK is the critical path and therefore activities C, D, E, F, H and K have no slack.

The slack in activity A is 7.17 days, the slack in activity B is 5.33 days, the slack in activity G is 2.83 days, the slack in activity I is 2.83 days and the slack in activity J is 18 days.

Hence, the Early start, Early finish, Late start, Late finish and slack for each activity is shown in Table 2.

d)

Expert Solution
Check Mark
Summary Introduction

To calculate:The probability that the project will be completed in 40 days or less.

Answer to Problem 19P

The probability that the project will be completed in 40 days or less is 94.63%.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Calculation of probability that the project will be completed in 40 days or less:

Consider the expected project completion time of 36.33 days as the mean and the variance of the distribution σ2, is the sum of the variances of individual activities on the critical path which are C, D, E, F, H, and K (refer table 1)

Consequently,

σ2=0.11+0.11+0.44+1.78+1.00+1.78=5.22

Therefore the standard deviation is the square root of 5.22, which works out to 2.28

Calculate the z value as shown below

z=4036.332.28=1.61

From thez-factor table1.61 corresponds to 0.9463. The probability that the project will be completed in 40 days is 94.63%.

Hence, the probability that the project will be completed in 40 days or less is 94.63%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Al construction has developed tasks duration and predecessor relationships in the following table for building model houses. The manager has been concerned with the amount of time it took to complete several jobs, some of the company workers are very unreliable. A list of activities and their optimistic completion time, the most likely time and the pessimistic completion time (in days) for a new contract are given in the following table. Activity Predecessors Optimistic (a) Most likely  (m) Pessimistic (b)           A -- 1 2 3 B - 2 3 4 C A 4 5 6 D B 8 9 10 E C, D 2 5 8 F D 4 5 6 G E 1 2 3             1.Draw the activity network for this new contract (either AON or AOA).               2. Determine the Expected Time and Variance for each activity.                              3.. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table).…
What's the best way to resolve this problem?   Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion​ time, the most likely completion​ time, and the pessimistic completion time​ (all in​ days) for a new contract are given in the following​ table:   Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s) A 3 5 9 - G 1 2 3 A, E B 4 5 6 - H 4 6 8 F C 1 2 3 - I 10 11 12 G D 7 8 9 C J 15 17 19 C E 1 3 5 B, D K 4 8 12 H, I F 5 10 15 A, E              b) Activities on the critical path for the project are C - D - E - F - H - K c) For the given​ project, the earliest start​ (ES) and earliest finish​ (EF) are: For the given​ project, the latest start​ (LS) and latest finish​ (LF) are: ​(Round your responses to two decimal​ places.)   Referring to the…
Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Activity a A 4 10 11 с 1 7 8 M 2 4 1 7 11 10 11 4 J 13 5 BCDEFGH-X K This exercise contains only part a. a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) Activity Time (days) DEF I - X K m 5 2 2 6 15 9 Immediate b Predecessor(s) 9 12 3963 HZ873 14 12 17 13 1105 Expected Time A B C III G H B, D A, E A, E F G C H, I Variance

Chapter 3 Solutions

Principles Of Operations Management

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY