Concept explainers
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow.
a) What is the expected (estimated) time for activity C?
b) What is the variance for activity C?
c) Based on the calculation of estimated times, what is the critical path?
d) What is the estimated time of the critical path?
e) What is the activity variance along the critical path?
f) What is the probability of completion of the project before week 36?
a)
To determine: The expected time for activity C.
Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.
Answer to Problem 17P
The expected time for activity C is 12 weeks.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time estimates | ||
Optimistic | Most likely | Pessimistic | ||
A | 4 | 8 | 10 | |
B | A | 2 | 8 | 24 |
C | A | 8 | 12 | 16 |
D | A | 4 | 6 | 10 |
E | B | 1 | 2 | 3 |
F | E,C | 6 | 8 | 20 |
G | E,C | 2 | 3 | 4 |
H | F | 2 | 2 | 2 |
I | F | 6 | 6 | 6 |
J | D,G,H | 4 | 6 | 12 |
K | I,J | 2 | 2 | 3 |
Calculation of expected time for activity C:
AON project network diagram shown below, given the precedence relationships of various activities,
Figure 1
With the given predecessor AON diagram is constructed. To Calculate the expected time for activity C given the data that the optimistic time estimate “a” of activity C of 8 weeks, the most likely time estimate “m” of 12 weeks and the pessimistic time estimate “b” of 16 weeks using the formula.
Where ‘a’ is the optimistic time estimate, ‘m’ is the most likely time estimate and ‘b’ is the pessimistic time estimate
Substitute into the equation (1), the values of
Therefore the expected time for activity C is calcualted by adding 8, 48 and16 and dividing the sum with 6 which gives
Hence, the expected time for activity C is 12 weeks.
b)
To calculate: The variance for activity C.
Answer to Problem 17P
The variance for activity C is 1.78 weeks.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time estimates | ||
Optimistic | Most likely | Pessimistic | ||
A | 4 | 8 | 10 | |
B | A | 2 | 8 | 24 |
C | A | 8 | 12 | 16 |
D | A | 4 | 6 | 10 |
E | B | 1 | 2 | 3 |
F | E,C | 6 | 8 | 20 |
G | E,C | 2 | 3 | 4 |
H | F | 2 | 2 | 2 |
I | F | 6 | 6 | 6 |
J | D,G,H | 4 | 6 | 12 |
K | I,J | 2 | 2 | 3 |
Calculation of variance for activity C:
Calculate the variance for activity C using the formula
Substitute in equation (2) the values of
The variance of activity C is calculated by squaring the value obtained by dividing the difference of 16 and 8 with 6 which gives the resultant as 1.28 weeks.
The variance in activity C is 1.78 weeks.
c)
To determine: The critical path.
Answer to Problem 17P
The critical path AàCàFàHàJàK.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time estimates | ||
Optimistic | Most likely | Pessimistic | ||
A | 4 | 8 | 10 | |
B | A | 2 | 8 | 24 |
C | A | 8 | 12 | 16 |
D | A | 4 | 6 | 10 |
E | B | 1 | 2 | 3 |
F | E,C | 6 | 8 | 20 |
G | E,C | 2 | 3 | 4 |
H | F | 2 | 2 | 2 |
I | F | 6 | 6 | 6 |
J | D,G,H | 4 | 6 | 12 |
K | I,J | 2 | 2 | 3 |
Calculation of critical path:
Using equation (1) and (2)calculate the expected times and variances for all the activitiesand obtain the values shown in table.
Figure 1, shows the AON diagram which gives the critical path. The critical path is AàCàFàHàJàK.
Hence, the critical path AàCàFàHàJàK.
d)
To Compute: The estimated time of the critical path.
Answer to Problem 17P
The critical path AàCàFàHàJàK which is 40.18 weeks.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time estimates | ||
Optimistic | Most likely | Pessimistic | ||
A | 4 | 8 | 10 | |
B | A | 2 | 8 | 24 |
C | A | 8 | 12 | 16 |
D | A | 4 | 6 | 10 |
E | B | 1 | 2 | 3 |
F | E,C | 6 | 8 | 20 |
G | E,C | 2 | 3 | 4 |
H | F | 2 | 2 | 2 |
I | F | 6 | 6 | 6 |
J | D,G,H | 4 | 6 | 12 |
K | I,J | 2 | 2 | 3 |
Calculation of estimated time of the critical path:
Figure 1, shows the AON diagram which gives the critical path. The critical path is AàCàFàHàJàK.
The various paths and the expected completion times are listed in the table
Various paths | Completion times |
AàBàEàFàIàK | 37.18 weeks |
AàBàEàGàJàK | 31.18 weeks |
AàCàFàHàJàK | 40.18 weeks |
AàCàGàJàK | 31.51 weeks |
AàDàJàK | 22.84 weeks |
Hence, the estimated time of the critical path AàCàFàHàJàK is 40.18 weeks.
e)
To determine: The variance of the critical path.
Answer to Problem 17P
The variance of the critical path is 10.03 weeks.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time estimates | ||
Optimistic | Most likely | Pessimistic | ||
A | 4 | 8 | 10 | |
B | A | 2 | 8 | 24 |
C | A | 8 | 12 | 16 |
D | A | 4 | 6 | 10 |
E | B | 1 | 2 | 3 |
F | E,C | 6 | 8 | 20 |
G | E,C | 2 | 3 | 4 |
H | F | 2 | 2 | 2 |
I | F | 6 | 6 | 6 |
J | D,G,H | 4 | 6 | 12 |
K | I,J | 2 | 2 | 3 |
Calculation of variance of the critical path:
The activity variance σ2along the critical path AàCàFàHàJàK is the sum of the variances of individual activities A, C, F, H, J and K.
Therefore,
The activity variance along the critical path is the sum of 1, 1.78, 5.44, 0, 1.78, 0.03 is 10.03 weeks.
Hence, the variance of the critical path is 10.03 weeks
f)
To compute: The probability of completion of the project before week 36 weeks.
Answer to Problem 17P
The probability of completion of the project before week 36 weeks is 9.34%.
Explanation of Solution
Given information:
Activity | Immediate predecessor | Time estimates | ||
Optimistic | Most likely | Pessimistic | ||
A | 4 | 8 | 10 | |
B | A | 2 | 8 | 24 |
C | A | 8 | 12 | 16 |
D | A | 4 | 6 | 10 |
E | B | 1 | 2 | 3 |
F | E,C | 6 | 8 | 20 |
G | E,C | 2 | 3 | 4 |
H | F | 2 | 2 | 2 |
I | F | 6 | 6 | 6 |
J | D,G,H | 4 | 6 | 12 |
K | I,J | 2 | 2 | 3 |
Calculation of probability of completion of the project before week 36 weeks:
Use the normal distribution tables given that the estimated mean time is 40.18 weeks and the standard deviation is square root of 10.03 weeks.
First compute the standard deviation σ by computing the square root of 10.03 weeks.
Calculate the z value as shown below
For a z value of -1.32, the probability is 9.34%.
Therefore, there is a probability of 9.34% that the project may be completed on or before 36 weeks.
Hence, the probability of completion of the project before week 36 weeks is 9.34%.
Want to see more full solutions like this?
Chapter 3 Solutions
Principles Of Operations Management
- Consider the following data for a project to install a new server at the Northland Pines High School: NEED HELP Carrow_forwardGiven the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table. Question Viewer Activity Expected Time (weeks) Variance A 4.0 1.00 B 5.5 0.96 C 4.0 0.15 D 11.5 1.52 E 6.5 2.40 F 8.5 2.55 G 5.0 0.69 The probability that this path will take more than 15 weeks to complete is ☐. (Enter your response rounded to four decimal places.)arrow_forwardconduct pest analysis for the data byarrow_forward
- Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity Predecessor Duration in Weeks A - 5 B - 3 C A, B 8 D C 3 E - 4 F E 10 G F 8 H E 18 I D 20 J D, G, I 7 K I 5 L H 10 6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation: the first pic: First: Draw the precedence diagram. Second: Using the notation given identify the duration of the project: you can type it. Third: identify the critical part and explain the critical path. Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found. 6B. Draw the project’s Gantt chart First: The…arrow_forwardRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels Time (weeks) Time (weeks) Immediate Predecessor(s) CE Activity A B C D E F a 4 1 9 5 1 6 m 9 9 14 6 2 9 b 10 24 18 10 4 21 Immediate Predecessor(s) A A A B C, E Activity a 3 2 G H 1 J K a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal places) b) The variance for activity C is weeks. (Round your response to two decimal places) c) Based on the calculation of the estimated times, the critical path is 7 6 3 m 3 2 7 8 3 D 4 2 7 12 4 F F D. G. H 1.J d) The estimated time for the critical path is weeks. (Round your response to two decimal places) e) The activity variance along the critical path is weeks (Round your response to two decimal places) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 40 weeks or less is (Enter as a probability…arrow_forwardAl construction has developed tasks duration and predecessor relationships in the following table for building model houses. The manager has been concerned with the amount of time it took to complete several jobs, some of the company workers are very unreliable. A list of activities and their optimistic completion time, the most likely time and the pessimistic completion time (in days) for a new contract are given in the following table. Activity Predecessors Optimistic (a) Most likely (m) Pessimistic (b) A -- 1 2 3 B - 2 3 4 C A 4 5 6 D B 8 9 10 E C, D 2 5 8 F D 4 5 6 G E 1 2 3 1.Draw the activity network for this new contract (either AON or AOA). 2. Determine the Expected Time and Variance for each activity. 3.. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table).…arrow_forward
- Table contains information about an environmental cleanup project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.arrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Q Activity A B C D E The cost of shortening of project is $ F G H I Normal Time (weeks) 5 7 7 7 1 3 5 4 2 Crash Time (weeks) 4 4 Activity A B C D E 6 4 6 1 3 4 2 2 Cost to Crash ($ per week) . (Enter your response as a whole number.) 300 50 300 250 200 200 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) Immediate Predecessor(s) Activity F G H I None None A A B 3~~ C, D D, E F Garrow_forwardOmar has recently been hired as the HIM director at a large medical center. He realizes that he has a number of employees whose job duties would allow them to work from home. Because his boss has asked him for a space reduction proposal, he recognizes the need to implement a work-at-home program for his employees. What steps should Omar take in developing a security program for the employees who will work from home? Develop a checklist of considerations, along with a list of resources that would facilitate his security program.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.