Operations Management
13th Edition
ISBN: 9780135173626
Author: HEIZER, Jay, RENDER, Barry, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 18DQ
How can we determine the probability that a project will be completed by a certain date? What assumptions are made in this computation?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
How can we determine the probability that a project will be completed by a certain date? What assumptions are made in this computation?
How do we estimate the likelihood of a project being finished by a certain date? In this calculation, what assumptions are made?
The following information has been computed from a project:
Expected total project time = T = 62 weeks
Project variance = 81
1- What is the probability that the project will be completed 18 weeks before its expected
completion date?
2- Draw Normal Curve & Analysis your solution with conclusion
Chapter 3 Solutions
Operations Management
Ch. 3 - Prob. 1EDCh. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...
Ch. 3 - Describe how expected activity times and variances...Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 8PCh. 3 - Prob. 13PCh. 3 - Prob. 15PCh. 3 - Prob. 17PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 33PCh. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- From the following data, calculate BAC, BCWS, BCWP, ACWP, EV, CV and SV when the Status Checking Date is May 5, 2017. Is the project over or under budget? By what percentage? Is the project behind or ahead of schedule? By what percentage? Project Status Status Checking Date 5/5/2017 Actual Effort Estimated Actual Completion Estimated Work Effort by Status Checking Date Completion Date Tasks Date (mm/dd/yy) (mm/dd/yy) (Person Days) (Person Days) 10 2/5/2017 2/5/2017 15 20 3/15/2017 3/25/2017 20 25 4/25/2017 4. 25 25 5/5/2017 4/1/2017 15 10 5/25/2017 10 5 6/10/2017 7 5 6/15/2017 HTML Editor 2. 3. 5.arrow_forwardWhy might a probabilistic estimate of a project’s completion time based solely on the variance of the critical path be misleading? Under what circumstances would it be acceptable?arrow_forwardThe following information has been computed from aproject:Expected total project time = T = 62 weeksProject variance (s2p ) = 81What is the probability that the project will be completed18 weeks before its expected completion date?arrow_forward
- The optimistic, most likely and pessimistic times for the tasks comprising a project are shown below. Use the data to compute the expected completion time and variance for each task. Task to tm tp A 5 10 19 B 2 16 19 C 7 10 14 D 6 22 29 E 20 26 29 Find the expected completion time and variance for each task and fill in the table below (enter your responses rounded to two decimal places). Task to tm tp te s2t A 5 10 19arrow_forwardThe use of probability curves to describe a project estimate helps to deal with: Your answer: The impact of uncertainty on demand. The impact of uncertainty on estimating times. The impact of uncertainty on costs. The impact of uncertainty on satisfaction.arrow_forwardA project is scheduled to complete in six months duration. There are two activities in the project. The actual cost of Activity 1 is SAR 300,000 and that of Activity 2 is SAR 200,000. The planned value of these activities is SAR 280,000 and 150,000 respectively. On reviewing, the current project status is Activity 1 is 100% completed and Activity 2 is only 75% completed. (i) Perform the earned value calculations of the above project scenario and fill the given table. (ii) What do you infer about the project schedule and cost based on your calculations? Earned Value Planned Value Actual Cost Cost Variance Activity Scheduled Variance Cost performance Index Schedule performance Index Month 1arrow_forward
- A project is scheduled to complete in six months duration. There are two activities in the project. The actual cost of Activity 1 is SAR 300,000 and that of Activity 2 is SAR 200,000. The planned value of these activities is SAR 280,000 and 150,000 respectively. On reviewing, the current project status is Activity 1 is 100% completed and Activity 2 is only 75% completed. (i) Perform the earned value calculations of the above project scenario and fill the given table. Activity Month 1 Earned Value Planned Value Actual Cost Cost Variance Scheduled Variance Cost performance Index Schedule performance Index (ii) What do you infer about the project schedule and cost based on your calculations?arrow_forwardConsider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,Garrow_forwardWhy is it important to periodically re-evaluate and adjust software cost estimates during the life of a project?arrow_forward
- How is Project Planning, Scheduling, and Controlling is managed by the OM manager?arrow_forwardFarihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forwardI need solve this question in project managerarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY