Concept explainers
Project Management at Arnold Palmer Hospital
Video Case
The equivalent of a new kindergarten class is born every day at Orlando’s Arnold Palmer Hospital. With more than 13,000 births in the mid-2000s in a hospital that was designed 15 years earlier for a capacity of 6,500 births a year, the newborn intensive care unit was stretched to the limit. Moreover, with continuing strong population growth in central Florida, the hospital was often full. It was clear that new facilities were needed. After much analysis,
The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1,000 planning meetings (lasting from 45 minutes to a whole day). They even created a ‘Supreme Court’ to deal with conflicting views on the multifaceted issues facing the new hospital.
The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1000 planning meetings (lasting from 45 minutes to a whole day). They even created a “Supreme Court” to deal with conflicting views on the multifaceted issues facing the new hospital.
Funding and regulatory issues added substantial complexity to this major expansion, and Hodges was very concerned that the project stay on time and within budget Tom Hyatt, director of facility development, was given the task of onsite manager of the $103 million project, in addition to overseeing ongoing renovations, expansions, and other projects. The activities in the multiyear project for the new building at Arnold Palmer are shown in Table 3.7.
*This list of activities is abbreviated for purposes of this case study. For simplification, assume each week = .25 months (i.e., 2 weeks = .5 month, 6 weeks = 1.5 months, etc.).
1. Develop the network for planning and construction of the new hospital at Arnold Palmer.
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Operations Management
Additional Business Textbook Solutions
Auditing And Assurance Services
Essentials of MIS (13th Edition)
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Fundamentals of Financial Accounting
Financial Accounting, Student Value Edition (5th Edition)
- Milestone Project: Sample Project BriefEstablished in 2010, Jimmy Jonas Famous Sandwiches (JJFS) is a new, yet fast growing, sandwichshop. They established an early reputation for the best bread west of the Mississippi with qualityingredients and friendly, efficient service. Recently, however, efficiency has slipped. JJFS cannotkeep up with the increase in sales, especially in their catering orders. Although new employees havebeen added, the demand for their services is greater than their ability to handle it. As a result, somecustomers have deflected to other sandwich shops and catering orders have greatly declined. At thisrate, JJFS will develop a poor reputation, which could ultimately mean the end of their business.JJFS specializes in exceptional service and delivery. Along with their hundreds of stores, they arealso known for delivering at supersonic speed. JJFS caters all types of business luncheons, birthdayparties and other celebrations. JJFS has a comprehensive training…arrow_forwardWhat is the total cost for this project? (question a)iv.)arrow_forwardDraw a network diagram for the project. Find the minimum project completion time. Identify the critical activities and critical path.arrow_forward
- 46 Question 23 The project manager must be willing to manage within the guidelines, policies, procedures, rules, and directives of the parent company. True Falsearrow_forwardTopic: Managing Hard Rock’s Rockfest 1. Answer the following questions while referring to the Principles of Operations Management (Sustainability and Supply Chain Management) 10th edition. • Identify the critical path and its activities for Rockfest. How long does the project take? • Which activities have a slack time of 8 weeks or more? • Identify five major challenges a project manager faces in events such as this one. • Why is a work breakdown structure useful in a project such as this? Take the 26 activities and break them into what you think should be level-2, level-3, and level-4 tasks.arrow_forwardQ6. Following are the activities of a Project, please consider them for answering the questions below: Duration Activity Predecessor(s) (days) 4 В A B 6 C, D С. D E, F E 5 G D 4 I 6. J Н. I 3 K J 3 a) Draw Gantt chart for the above table b) Draw Labeled Network Diagram and high light critical path. c) Calculate total duration of the project d) Make a list of all Critical Activities e) Make a list of all Non Critical Activities f) Find Float/ Slack for Each Activity.arrow_forward
- QUESTION 2 You are the project manager of a software installation project. You would like to find the minimum-cost schedule for your project. There is a $1000-per-week penalty for each week the project is delayed beyond 25 weeks. In addition, your project team determined that indirect costs are $2,500 per week. Activity A B C D E FC G H Immediate Normal Time Normal Cost Predecessor (weeks) 5 8 10 4 3 9 2 8 9 A A, B B D E, F G C, F ($) 2,000 5,000 10,000 3,000 4,000 8,000 2,000 6,000 7,000 Crash Time (weeks) 3 7 8 3 2 6 2 5 7 a) What is the target completion week? b) How much would you save in total project costs with your schedule? Crash Cost ($) 4,000 8,000 12,000 7,000 5,000 14,000 2,000 9,000 15,000arrow_forward7arrow_forwardConstruct a network diagram for this project? TABLE 1: Activities and duration project Duration in weeks __________________________________ Activity Proceeding activity Optimistic Most likely Pessimistic A - 2 3 3 B - 10 12 15 C A 4 5 8 D B 2 2 2 E A, D 3 3 3 F…arrow_forward
- Use Excel to develop the Network Diagram for the Sample Project (assume project starts on September 1, 2021)arrow_forwardBelow is the first set of activities (Phase I) in constructing a new house, the respective time required to finish each activity, and the precedence relations. Activity A Description Predecessor Duration (in wks) 1 Clear site Bring utilities to the site Excavate 2 A 1 D Pour Foundation Outside Plumbing 2 E B,C 6 Frame House 8 G Do electric wiring Lay Floor Lay Roof Inside Plumbing 3 G 2 F 1 E,H (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying the project? (g) If there will be a delay in doing the outside plumbing without delaying the entire project, how long should it be?arrow_forwarda) Table Q3a. shows the logic for a particular project. (i) Construct a network diagram showing the various logical activity relationships from this information (ii) Perform a forward and backward pass to complete the activity boxes (iii) Highlight the critical path on your diagram and state the earliest project completion time. Activity Precedence Time (days) A - В A C A 4 D В 4 E В F В 4 H D D 6. J Е, F K G 4 L 7 M H, I J, K, L М. N 5 N 8arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.