Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9781259580093
Author: William J Stevenson
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 19, Problem 13P
Summary Introduction
To determine: The number of units of each product on a daily basis to achieve the maximum profit.
Introduction:
Linear programming:
Linear programming is a mathematical modeling method where a linear function is maximized or minimized taking into consideration the various constraints present in the problem. It is useful in making quantitative decisions in business planning.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Because of its labor contract, a company must hire enough labor for 100 units ofproduction per week on one shift or 200 units per week on two shifts. It cannot hire,lay off, or assign overtime. During the fourth week, workers will be available fromanother department to work part or all of an extra shift (up to 100 units). There is aplanned shutdown for maintenance in the second week, which will cut production tohalf. Develop a production plan. The opening inventory is 200 units, and the desiredending inventory is 300 units
Box Electric makes electronic components and has estimated the following for a new design of one of its products.
Fixed cost = $24,975
Material cost per unit = $0.17
Labor cost per unit = $0.12
Revenue per unit = $0.66
Note that fixed cost is incurred regardless of the amount produced. Per-unit material and labor cost together make up the variable cost per unit. Assuming that Box Electric sells all that it produces, profit is calculated by subtracting the fixed cost and total variable cost from total revenue.
Construct an appropriate spreadsheet model to find the profit based on a given production level and use the spreadsheet model to answer these questions.
(a)
Construct a one-way data table with production volume as the column input and profit as the output. Breakeven occurs when profit goes from a negative to a positive value; that is, breakeven is when total revenue = the total cost, yielding a profit of zero. Vary production volume from 0 to 100,000 in increments of 10,000.…
Cox Electric makes electronic components and has estimated the following for a new design of one of its products.
Fixed cost = $23,750
Material cost per unit = $0.17
• Labor cost per unit = $0.12
• Revenue per unit = $0.67
Note that fixed cost is incurred regardless of the amount produced. Per-unit material and labor cost together make up the variable
cost per unit. Assuming that Cox Electric sells all that it produces, profit is calculated by subtracting the fixed cost and total variable
cost from total revenue.
Construct an appropriate spreadsheet model to find the profit based on a given production level and use the spreadsheet model to
answer these questions.
(a) Construct a one-way data table with production volume as the column input and profit as the output. Breakeven occurs when
profit goes from a negative to a positive value; that is, breakeven is when total revenue = the total cost, yielding a profit of
zero. Vary production volume from 0 to 100,000 in increments of 10,000.…
Chapter 19 Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Ch. 19 - For which decision environment is linear...Ch. 19 - What is meant by the term feasible solution space?...Ch. 19 - Explain the term redundant constraint.Ch. 19 - Prob. 4DRQCh. 19 - Prob. 5DRQCh. 19 - Prob. 6DRQCh. 19 - Prob. 1PCh. 19 - Prob. 2PCh. 19 - Prob. 3PCh. 19 - A small candy shop is preparing for the holiday...
Ch. 19 - A retired couple supplement their income by making...Ch. 19 - Solve each of these problems by computer and...Ch. 19 - Prob. 7PCh. 19 - For Problem 6b: a. Find the range of feasibility...Ch. 19 - Prob. 9PCh. 19 - Prob. 10PCh. 19 - Prob. 11PCh. 19 - The manager of the deli section of a grocery...Ch. 19 - Prob. 13PCh. 19 - A chocolate maker has contracted to operate a...Ch. 19 - Prob. 15PCh. 19 - Prob. 16PCh. 19 - Prob. 1.1CQCh. 19 - Prob. 1.2CQCh. 19 - Prob. 1.3CQCh. 19 - Prob. 2.1CQCh. 19 - Prob. 2.2CQCh. 19 - Prob. 2.3CQCh. 19 - Prob. 2.4CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A small consulting firm has an overhead rate of 200% of direct labor charged to each job. The materials cost (including travel and other direct costs) for a particular job is $10,000, and the direct labor is$20,000. What is the total job cost for this job?arrow_forwardInformation on a business is given below.Variable Expenses:Raw material expense: 250 TL / pieceAuxiliary equipment expense: 150 TL / pieceElectricity expenses: 100 TL / pieceSpare parts expense: 75 TL / pieceOther variable expenses: 125 TL / pieceFixed costs:Depreciation, interest and insurance expenses: 75 000 TLLabor and personnel expenses: 250 000 TLOther fixed expenses: 115 000 TLProduction capacity: 2000 pcs / monthSale price: 1600 TL / pieceAccording to the above,a) Find the break-even point as the production quantity?b) Find the amount that the business has to produce in order to make a profit of 500 000 TL / month?arrow_forwardDevelop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition,you have negotiated with the union an option to use the regular workforce on overtime during winter or spring if overtime is necessary to prevent stock-outs at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, $100 for each temp; layoff, $200 for each worker laid off; inventory holding, $5 per unit-quarter; backorder, $10 per unit; straight time, $5 per hour; over time, $8 per hour. Assume that productivity is 0.5 units per worker hour, with eight hours per day and 60 days per season. (Answer in Appendix D)arrow_forward
- A company offers ID theft protection using leads obtained from client banks. Three employees work 40 hours a week on the leads, at a pay rate of $12 per hour per employee. Each employee identifies an average of 3,400 potential leads a week from a list of 4,600. An average of 6 percent of potential leads actually sign up for the service, paying a one-time fee of $80. Material costs are $1,500 per week, and overhead costs are $9,300 per week. Calculate the multifactor productivity for this operation in fees generated per dollar of input.arrow_forwardDevelop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,900; winter, 8,400; spring, 7,100; summer, 12,900. Inventory at the beginning of fall is 545 units. At the beginning of fall, you have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring if overtime is necessary to prevent backorders at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, $800 for each temp; layoff, $1,600 for each worker laid off; inventory holding, $5 per unit-quarter; backorder, $10 per unit; straight time, $25 per hour; overtime, $35 per hour. Assume that the productivity is 0.5 unit per worker hour, with eight hours per day and 60 days per season. In each quarter, produce to the full output of your regular workforce, even if that results…arrow_forwardYou are required to implement the production level method for the following scenario. Four products, each a different colour, are manufactured over one week in a production facility. . You need to manufacture 1500 blue, 750 red, 750 green and 1000 yellow products per week. The plant works 2 shifts per day, 5 days a week. How many of each product should be produced each day? 600 blue, 300 red, 300 green, 400 yellow 300 blue, 150 red, 150 green, 200 yellow 800 per day 150 blue, 75 red, 75 green, 100 yellowarrow_forward
- Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 8,000; spring, 6,000; summer, 13,000. Inventory at the beginning of fall is 500 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring if overtime is necessary to prevent stockouts at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, $100 for each temp; layoff $200 for each worker laid off; inventory holding, $5 per unit-quarter; backorder, $10 per unit; straight time, $5 per hour; overtime, $8 per hour. Assume that the productivity is 0.5 unit per worker hour, with eight hours per day and 60 days per season. a. What is the total cost for this plan?arrow_forwardThe following information relates to a company’s aggregate production planning activities: Quarter Demand Forecast 1 75,000 2 100,000 3 75,000 4 125,000 Beginning Workforce = 35 workers Production per Employee = 1,250 units per quarter Hiring Cost = $500 per worker Firing Cost = $1,000 per worker Inventory Carrying Cost = $20 per unit per quarter If a level production strategy is used then the cost of the level production plan (inventory costs plus hiring and firing costs) is a) $20,000. b) $645,000. c) $1,250,000. d) $1,270,000. Answer: d Pls explain with stepsarrow_forward3-2) The optimal quantity of the three products and resulting revenue for Taco Loco is: A) 28 beef, 80 cheese, and 39.27 beans for $147.27. B) 10.22 beef, 5.33 cheese, and 28.73 beans for $147.27. C) 1.45 Z, 8.36 Y, and 0 Z for $129.09. D) 14 Z, 13 Y, and 17 X for $9.81. 3-3) Taco Loco is unsure whether the amount of beef that their computer thinks is in inventory is correct. What is the range in values for beef inventory that would not affect the optimal product mix? A) 26 to 38.22 pounds B) 27.55 to 28.45 pounds C) 17.78 to 30 pounds D) 12.22 to 28 poundsarrow_forward
- Jack Jones, the materials manager at Precision Enterprises, is beginning to look for ways to reduce inventories. A recent accounting statement shows that the inventory investment for raw materials is $4,100,400, for work-in-process is $6,538,000, and for finished goods is $2.964,000. This year's cost of goods sold will be about $18,148.000. Assume that there are 52 business weeks per year a. Express total inventory as weeks of supply. The weeks of supply is weeks. (Enter your response rounded to one decimal place.) b. Express total inventory as inventory tums. The inventory turnover is turns per year. (Enter your response rounded to one decimal place.)arrow_forwardBetter Products, Inc., manufactures three products on two machines. In a typical week, 40 hours are available on each machine. The profit contribution and production time in hours per unit are as follows: Category Profit/unit Machine 1 time/unit Machine 2 time/unit Product 1 Product 2 $30 0.5 1.0 hr hr $50 2.0 1.0 Product 3 $20 0.75 Two operators are required for machine 1-thus, 2 hours of labor must be scheduled for each hour of machine 1 time. Only one operator is required for machine 2. A maximum of 100 labor-hours is available for assignment to the machines during the coming week. Other production requirements are that product 1 cannot account for more than 50% of the units produced and that product 3 must account for at least 20% of the units produced. (c) What is the value (in $) of an additional hour of labor? 0.5 (a) How many units of each product should be produced to maximize the total profit contribution? What is the projected weekly profit (in $) associated with your…arrow_forwardevelop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 9,700; winter, 8,000; spring, 7,000; summer, 11,700. Inventory at the beginning of fall is 485 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on overtime during winter or spring only if overtime is necessary to prevent stockouts at the end of those quarters. Overtime is not available during the fall. Relevant costs are hiring, $80 for each temp; layoff, $160 for each worker laid off; inventory holding, $5 per unit-quarter; backorder, $10 per unit; straight time, $5 per hour; overtime, $8 per hour. Assume that the productivity is 0.5 unit per worker hour, with eight hours per day and 60 days per season. In each quarter, produce to the full output of your regular workforce, even if that…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,