Textbook Question
Chapter 17, Problem 7DRQ
Identify the term being described for each of the following:
a. A sequence of activities in a project.
b. The longest time sequence of activities in a project.
c. Used when two activities have the same starting and finishing points.
d. The difference in time length of any path and the critical path.
e. The statistical distribution used to describe variability of an activity time.
f. The statistical distribution used to describe path variability.
g. Shortening an activity by allocating additional resources.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Identify the term being described for each of the following: (a). A sequence of activities in a project. (b). The longest time sequence of activities in a project. (c). Used when two activities have the same starting and finishing points. (d). The difference in time length of any path and the critical path. (e). The statistical distribution used to describe variability of an activity time. (f). The statistical distribution used to describe path variability. (g). Shortening an activity by allocating additional resources.
You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track?
Activity
Time
Immediate Predecessor
A
10 Weeks
None
B
6 Weeks
A
C
7 Weeks
A
D
6 Weeks
B
E
8 Weeks
C
F
3 Weeks
D
G
4 Weeks
F
Mangement
Project management is a discipline that involves planning, organizing, and overseeing the execution of a project from initiation to completion. It encompasses defining project goals, outlining tasks, allocating resources, and managing budgets and timelines. A successful project manager must possess strong leadership skills, effective communication, and the ability to mitigate risks and solve problems efficiently. Collaboration among team members is crucial, as is the flexibility to adapt to unexpected challenges that may arise during the project lifecycle. Continuous monitoring and evaluation ensure that the project stays on track, meeting objectives and delivering value to stakeholders.
Question: How can project managers encourage effective collaboration and communication among team members to ensure the successful and timely completion of a project?
Chapter 17 Solutions
Operations Management
Ch. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...
Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.arrow_forwardWhich of the following statements regarding PERT analysis is TRUE? Select one: O a Project variance is the sum of all activity variances. O b. Project standard deviation is the sum of all critical activity standard deviations. O c. Each activity has two estimates of its duration. O d. Only critical activities contribute to the project variancearrow_forwardThe MXN Sdn. Bhd. has identified eight activities that would need to be implemented in order to complete the construction project as listed in the table below. Using the PERT three-estimate approach, the company has obtained the estimated duration and the precedence relationships for each activity. In addition, the company may get penalized if it fails to complete the project within 35 weeks. Activity A B с D E F G H Immediate predecessor(s) None A A None B,C C,D Table 2: Project Description D, F E, G Optimistic 2 7 4 7 3 2 Time estimate (week) SKT AM X Most likely m 6 8 13 7 9 6 Pessimistic b 7 16 13 17 9 9 (a) Construct the activity on the node (AON) network for this project. (b) Compute the expected activity time and the variance for each activity. termine the forward and backward pass, activity slack, and identify the critical path. Estimate the probability that all the activities on the current critical path will be completed within 35 weeks. (e) Estimate the probability that the…arrow_forward
- You are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.arrow_forwardProject Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected processarrow_forwardDo not use chatgptarrow_forward
- Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical) Activity details are in the following table: a) Activity that should be orashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = S (Enter your response as an integer) Normal Activity Time (days) A B C 7 4 11 Crash Normal Time (days) Cost $8,000 $1,200 $4,200 6 2 9 Total Cost with Crashing Immediate Predecessor(s) $6,500 $3,000 $6.200 A Barrow_forwardPlease solve my Problem as Soon as possible. Thank You!arrow_forwardWhat is the definition of the latest completion time (LCT) of a project activity?a. LCT(Ai) = Max{LST(Aj) for which Ajis a successor of Ai}b. LCT(Ai) = Min{LST(Aj) for which Ajis a successor of Ai}c. LCT(Ai) = Max{LST(Aj) for which Ajis a predecessor of Ai}d. LCT(Ai) = Min{LST(Aj) for which Ajis a predecessor of Ai}arrow_forward
- Suppose that you are assigned to a construction project which is planned to be build as early as possible. As a planning engineer you have to find the right sequence of activities in order to complete the project on time. Use Gantt (Bar) Chart and calculate total duration and determine the critical path of the project. Immediate Estimated Activity Predecessors Duration 2 weeks 4 weeks 10 weeks A 6 weeks 4 weeks S weeks 7 weeks 9 weeks 7 weeks 8 weeks G E, G F, 1 4 weeks 5 weeks 2 weeks 6 weeks K M K, L Immediate Predecessor (Finish to Start) Construct Gantt Chart of the project.arrow_forwardFarihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forwardThe project manager of Good Public Relations gathered the data shown in Table 7.15 for a new advertising campaign.a. How long is the project likely to take?b. What is the probability that the project will take more than 38 weeks?c. Consider the path A–E–G–H–J. What is the probability that this path will exceed 38 weeks?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY