Concept explainers
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
a. Construct a network diagram. You can use either AOA or AON (see Example 5).
b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus.
a)
To construct: A network diagram.
Answer to Problem 12P
Answer
Network diagram:
Explanation of Solution
Given information:
Activity | Immediate predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 2 | 4 | 6 | |
D | A | 6 | 8 | 10 |
E | D | 7 | 9 | 12 |
H | E | 2 | 3 | 5 |
F | A | 3 | 4 | 8 |
G | F | 5 | 7 | 9 |
B | 2 | 2 | 3 | |
I | B | 2 | 3 | 6 |
J | I | 3 | 4 | 5 |
K | J | 4 | 5 | 8 |
C | 5 | 8 | 12 | |
M | C | 1 | 1 | 1 |
N | M | 6 | 7 | 11 |
O | N | 8 | 9 | 13 |
End | H, G, K, O |
Formula to calculate expected time and variance:
Calculation of mean and variance:
Activity | Optimistic time | Most likely time | Pessimistic time | Expected time | Standard deviation | Variance |
A | B | C | (A+(4*B)+C)/6 | (C-A)/6 | (C-A)^2/6^2 | |
A | 2 | 4 | 6 | 4 | 0.667 | 0.444 |
D | 6 | 8 | 10 | 8 | 0.667 | 0.444 |
E | 7 | 9 | 12 | 9.17 | 0.833 | 0.694 |
H | 2 | 3 | 5 | 3.17 | 0.500 | 0.250 |
F | 3 | 4 | 8 | 4.5 | 0.833 | 0.694 |
G | 5 | 7 | 9 | 7 | 0.667 | 0.444 |
B | 2 | 2 | 3 | 2.17 | 0.167 | 0.028 |
I | 2 | 3 | 6 | 3.33 | 0.667 | 0.444 |
J | 3 | 4 | 5 | 4 | 0.333 | 0.111 |
K | 4 | 5 | 8 | 5.33 | 0.667 | 0.444 |
C | 5 | 8 | 12 | 8.17 | 1.167 | 1.361 |
M | 1 | 1 | 1 | 1 | 0.000 | 0.000 |
N | 6 | 7 | 11 | 7.5 | 0.833 | 0.694 |
O | 8 | 9 | 13 | 9.5 | 0.833 | 0.694 |
End |
Network diagram:
The activity on arrow diagram is constructed. The activities are mentioned on the arrows. The arrows in the diagram are mentioned in the precedence order. The arrows indicates the successor for each node.
b)
To determine: The probability of each bonus.
Answer to Problem 12P
Explanation of Solution
Given information:
- If the project is finished in 26 weeks the bonus is $1,000.
- If the project is finished in 27 weeks the bonus is $500.
Calculation of expected duration, variance and standard deviation for each path:
Path A-D-E-H:
Path A-F-G:
Path B-I-J-K:
Path C-M-N-O:
Bonus of $1,000 (less than or equal to 26 weeks):
Calculation of probability of completion in less than or equal to 26 weeks:
Calculation of z value for all paths:
Formula:
Path A-D-E-H:
From the standard normal distribution table,
The probability value for (z = 1.23) is 0.8907.
Path A-F-G:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path B-I-J-K:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path C-M-N-O:
From the standard normal distribution table,
The probability value for (z = -0.10) is 0.4602.
Probability of completion in less than or equal to 26 weeks:
The probability of achieving a bonus of $1,000 is 0.4099.
Bonus of $500 (less than or equal to 27 weeks):
Calculation of probability of completion in less than or equal to 27 weeks:
Calculation of z value for all paths:
Formula:
Path A-D-E-H:
From the standard normal distribution table,
The probability value for (z = 1.96) is 0.9750.
Path A-F-G:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path B-I-J-K:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path C-M-N-O:
From the standard normal distribution table,
The probability value for (z = 0.50) is 0.6915.
Probability of completion in less than or equal to 27 weeks:
The probability of achieving a bonus of $500 is 0.6742.
Want to see more full solutions like this?
Chapter 17 Solutions
Operations Management
- a. Develop an AON network for this problem. b. What is the critical path? c. What is the total project completion time? d. What is the slack time for each individual activity? Discussion Question e. Why do you think project management is needed in this scenario?arrow_forwardNote: I don't have time... Please kindly give me all answers otherwise leave it. Help me ? Thank youarrow_forwardThe triple constraints of project management include: O A. Risk, Scope and quality O B. WBS, Scope and deliverables O C. Cost, quality and communication O D. Cost, time and scopearrow_forward
- The following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?arrow_forwardIMPORTANT NOTE: All Project Management Questions are from the same Project. You only need to solve the project one time. The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table. What is the Early Start on Activity G?arrow_forwardProject Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected processarrow_forward
- a. Draw the precedence diagram b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?arrow_forwardThree activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical) Activity details are in the following table: a) Activity that should be orashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = S (Enter your response as an integer) Normal Activity Time (days) A B C 7 4 11 Crash Normal Time (days) Cost $8,000 $1,200 $4,200 6 2 9 Total Cost with Crashing Immediate Predecessor(s) $6,500 $3,000 $6.200 A Barrow_forwardSuppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of 10 months. After tracking the project for six months, you have collected the information in the table below. a. Complete the table. How do Earned Value SPI (based on $) and Earned Schedule SPI differ? b. Calculate the schedule variances for the project for both Earned Value and Earned Schedule. How do the values differ?arrow_forward
- . 1. Project Scope & Constraints The new payroll system project has been approved. The new system will reduce clerical time and errors, improve morale in the payroll department, and avoid possible fines and penalties for noncompliance. The system must be installed by January 1st to meet new federal reporting rules, all expenses must be approved in advance, and the system should have a modular design if possible. The new system is expected to be announced in a year-end report if it is ready by mid-December. 1. Why is it important to define the project scope? How would you describe the scope of the payroll project in this case? 2. Based upon the project scope, identify the constraints, and determine its characteristics: present versus future, internal versus external, and mandatory versus desirable. 3. What questions would you ask to determine the feasibility of this project? 4. Given the project time constraints, could you shorten the typical steps in the preliminary investigation…arrow_forwardPlease answer d, e and f only. Thanksarrow_forwardDraw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and Oarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.