Operations Management
Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 17, Problem 12P

A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.

Chapter 17, Problem 12P, A project manager has compiled a list of major activities that will be required to install a

a. Construct a network diagram. You can use either AOA or AON (see Example 5).

b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus.

a)

Expert Solution
Check Mark
Summary Introduction

To construct: A network diagram.

Answer to Problem 12P

Answer

Network diagram:

Operations Management, Chapter 17, Problem 12P , additional homework tip  1

Explanation of Solution

Given information:

Activity Immediate predecessor Optimistic time Most likely time Pessimistic time
A 2 4 6
D A 6 8 10
E D 7 9 12
H E 2 3 5
F A 3 4 8
G F 5 7 9
B 2 2 3
I B 2 3 6
J I 3 4 5
K J 4 5 8
C 5 8 12
M C 1 1 1
N M 6 7 11
O N 8 9 13
End H, G, K, O

Formula to calculate expected time and variance:

Expected time=Optimistic time+(4×Most likely time)+Pessimistic time6

Standard deviation=Pessimistic timeOptimistic time6

Variance=(Pessimistic timeOptimistic time)262

Calculation of mean and variance:

Activity Optimistic time Most likely time Pessimistic time Expected time Standard deviation Variance
A B C (A+(4*B)+C)/6 (C-A)/6 (C-A)^2/6^2
A 2 4 6 4 0.667 0.444
D 6 8 10 8 0.667 0.444
E 7 9 12 9.17 0.833 0.694
H 2 3 5 3.17 0.500 0.250
F 3 4 8 4.5 0.833 0.694
G 5 7 9 7 0.667 0.444
B 2 2 3 2.17 0.167 0.028
I 2 3 6 3.33 0.667 0.444
J 3 4 5 4 0.333 0.111
K 4 5 8 5.33 0.667 0.444
C 5 8 12 8.17 1.167 1.361
M 1 1 1 1 0.000 0.000
N 6 7 11 7.5 0.833 0.694
O 8 9 13 9.5 0.833 0.694
End

Network diagram:

Operations Management, Chapter 17, Problem 12P , additional homework tip  2

The activity on arrow diagram is constructed. The activities are mentioned on the arrows. The arrows in the diagram are mentioned in the precedence order. The arrows indicates the successor for each node.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability of each bonus.

Answer to Problem 12P

The probability of achieving a bonus of $1,000 is 0.4099. The probability of achieving a bonus of $500 is 0.6742.

Explanation of Solution

Given information:

  • If the project is finished in 26 weeks the bonus is $1,000.
  • If the project is finished in 27 weeks the bonus is $500.

Calculation of expected duration, variance and standard deviation for each path:

Path A-D-E-H:

Expected duration=4+8+9.17+3.17=24.34

Variance=0.444+0.444+0.694+0.250=1.832

Standard deviation=Variance=1.832=1.3535=1.354

Path A-F-G:

Expected duration=4+4.5+7=15.50

Variance=0.444+0.694+0.444=1.582

Standard deviation=Variance=1.582=1.2577=1.258

Path B-I-J-K:

Expected duration=2.17+3.33+4+5.33=14.83

Variance=0.028+0.444+0.111+0.444=1.027

Standard deviation=Variance=1.027=1.014

Path C-M-N-O:

Expected duration=8.17+1+7.50+9.50=26.17

Variance=1.361+0.0+0.694+0.694=2.749

Standard deviation=Variance=2.749=1.658

Bonus of $1,000 (less than or equal to 26 weeks):

Calculation of probability of completion in less than or equal to 26 weeks:

Calculation of z value for all paths:

Formula:

Z=Specified time-Path meanPath standard deviation

Path A-D-E-H:

Z=26-24.341.354=1.23

From the standard normal distribution table,

The probability value for (z = 1.23) is 0.8907.

Path A-F-G:

Z=26-15.501.258=8.35

Since z value is greater than +3.00, probability of completion is 1.0000.

Path B-I-J-K:

Z=26-14.831.014=11.02

Since z value is greater than +3.00, probability of completion is 1.0000.

Path C-M-N-O:

Z=26-26.171.658=0.10

From the standard normal distribution table,

The probability value for (z = -0.10) is 0.4602.

Probability of completion in less than or equal to 26 weeks:

Probability=0.8907×1.0000×1.0000×0.4602=0.4099

The probability of achieving a bonus of $1,000 is 0.4099.

Bonus of $500 (less than or equal to 27 weeks):

Calculation of probability of completion in less than or equal to 27 weeks:

Calculation of z value for all paths:

Formula:

Z=Specified timePath meanPath standard deviation

Path A-D-E-H:

Z=27-24.341.354=1.96

From the standard normal distribution table,

The probability value for (z = 1.96) is 0.9750.

Path A-F-G:

Z=27-15.501.258=9.14

Since z value is greater than +3.00, probability of completion is 1.0000.

Path B-I-J-K:

Z=27-14.831.014=12

Since z value is greater than +3.00, probability of completion is 1.0000.

Path C-M-N-O:

Z=27-26.171.658=0.50

From the standard normal distribution table,

The probability value for (z = 0.50) is 0.6915.

Probability of completion in less than or equal to 27 weeks:

Probability=0.9750×1.0000×1.0000×0.6915=0.6742

The probability of achieving a bonus of $500 is 0.6742.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
working as a program operations manager
12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0
a/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7

Chapter 17 Solutions

Operations Management

Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY