Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 17, Problem 1P
For each of the following network diagrams, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times.
a. AOA diagram
b. AON diagram
c. AOA diagram
d. AON diagram
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the following diagram, why is it used and explain what information does it provide to the Project Manager.
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate
predecessors, and times appear in the accompanying table:
Activity
Immediate Predecessor(s)
Time (days)
B
A, D
C
E, F
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are B - D - E - G.
c) The project length for the leadership training program development project = 28 days.
d) Slack time for each of the activities is:
ABCDEFG
Activity
A
Slack Time
∞ or w w w
10
A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a
network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet
this requirement. She has gathered the activity time estimates and their dependencies shown here.
ID Description
A Survey
B
Soils report
с
Traffic design
D
Lot layout
E Approve design
F
G Drainage
H Landscape
I Signage
J
Illumination
Bid proposal
The project is expected to take
The critical path is:
Early start for Activity E is:
Late finish for Activity F is:
Slack for Activity C is:
Predecessor
None
A
A
A
B, C, D
E
E
E
E
F, G, H, I
Time
(days)
9
22
25
6
76
20
24
24
25
9
days.
day(s).
Chapter 17 Solutions
Operations Management
Ch. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...
Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity A B C D E F G This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are A-E-G c) The project length for the leadership training program development project = 22 days. d) Slack time for each of the activities is: B A, D C E, F Activity A B Slack Time 0 Time (days) 10 6 3 2 4 8arrow_forwardA large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. Description Survey Soils report C Traffic design D Lot layout E Approve design Illumination G Drainage H Landscape I Signage J Bid proposal ID A B The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 13 22 21 a 9 74 20 20 22 17 15 12 days. day(s).arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process a Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Activity Immediate Predecessor(s) ABCDEFG long dash- long dash- ABCDEFG A B C D, E E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) ($) ($) 1 14,000 2 3,000 1 40,000 3 22,000 1 8,000 4 13,000 2 16,000 3234 1 6 63 7,000 3,000 12,000 12,000 8,000 5,000 9,000 a. What is the shortest time duration for this project regardless of cost? (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? C. What is the total time of the minimum cost schedule? (enter your response as whole numbers). The total project's duration according to minimum cost schedule is? The minimum cost schedule…arrow_forward
- choose the correct answer for the following questions 1. When composing a risk management plan, one of the activities is to define: Group of answer choices Methods Work breakdown structure Project charter Project Resource allocationarrow_forwardPlease note that the last digit in the student number is: 0arrow_forwardI need solve this question in project managerarrow_forward
- I'm unable to answer the following question? What is the total cost of crashing the project from its current duration down to 13 weeks?arrow_forwardImage of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.arrow_forwardOmar has recently been hired as the HIM director at a large medical center. He realizes that he has a number of employees whose job duties would allow them to work from home. Because his boss has asked him for a space reduction proposal, he recognizes the need to implement a work-at-home program for his employees. What steps should Omar take in developing a security program for the employees who will work from home? Develop a checklist of considerations, along with a list of resources that would facilitate his security program.arrow_forward
- With the use of a diagram, show the typical levels of uncertainty or project risks associated with the Initiation,Planning,Execution,Monitoring and Controlling and closing phase and throughout a project.arrow_forwardList two outputs for each of the Project Risk Management processes (note that the Implement Risk Responses process is not discussed in this chapter)arrow_forwardIFS233 Donell Consulting recently completed an IT training platform implementation with a public firm. The project concluded after the completion of a testing, piloting and sign-off from the project stakeholders. Though completed, the project manager was reviewing their notes, in which they listed all the important occurrences that were recorded during various project phases: ● The pilot of the training platform is about to begin, and the COO of the firm has informed the project team that they want an additional 1000 staff trained and included, and the firm will be increasing budget accordingly. The new systems analyst replacement just found an issue with the way in which the training platform is recording information inputted from users. Apparently, it does note read or collate all the metadata produced during user inputs, and only considers metadata that leads to a complete sequence of inputs. This is going to cause issues in how we record the users' activities as the client wants to…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY