Textbook Question
Book Icon
Chapter 17, Problem 15P

PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.

A construction project has indirect costs totaling $40,000 per week. Major activities in the project and their expected times in weeks are shown in this precedence diagram.

Chapter 17, Problem 15P, PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No , example  1

Crashing costs for each activity are:

Chapter 17, Problem 15P, PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No , example  2

a. Determine the optimum time–cost crashing plan.

b. Plot the total-cost curve that describes the least expensive crashing schedule that will reduce the project length by six weeks.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The optimum cost-saving plan.

Introduction:

Project crashing:

It is method to shorten the total time taken for a project by reducing the time taken for one or more activities on the critical path. The reduction in the normal time taken is known as crashing.

Answer to Problem 15P

The activities to be crashed are 7-11, 1-2, 6-10, 11-13, and 4-6. The total crashing cost is $1,336,000.

Explanation of Solution

Given information:

  • Indirect cost is $40,000 per week.

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 17, Problem 15P , additional homework tip  1

Activity Crash cost first week ($000) Crash cost second week ($000) Crash cost third week ($000)
1 to 2 18 22
2 to 5 24 25 25
5 to 7 30 30 35
7 to 11 15 20
11 to 13 30 33 36
1 to 3 12 24 26
3 to 8
8 to 11 40 40 40
3 to 9 3 10 12
9 to 12 2 7 10
12 to 13 26
1 to 4 10 15 25
4 to 6 8 13
6 to 10 5 12
10 to 12 14 15

Project crashing:

Calculation of expected duration of each path:

Path 1-2-5-7-11-13:

Expected duration=5+8+7+4+11=35

Path 1-3-8-11-13:

Expected duration=4+12+5+11=32

Path 1-3-9-12-13:

Expected duration=4+6+9+1=20

Path 1-4-6-10-12-13:

Expected duration=3+12+9+8+1=33

Step 1:

Critical path is 1-2-5-7-11-13.

The activities are ranked according to the cost per week to crash.

Activity Cost ($)
7-11 15
1-2 18
2-5 24
5-7 30
11-13 30

Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($15) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.

Step 2:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 34
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33

Critical path is 1-2-5-7-11-13.

The activities are ranked according to the cost per week to crash.

Activity Cost ($)
1-2 $18
7-11 $20
2-5 $24
5-7 $30
11-13 $30

Activity 1-2 will be crashed first by 1 week since it has the lowest crashing cost ($18) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.

Step 3:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 33
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33

Critical path is 1-2-5-7-11-13 and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 7-11 $20
1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-4-6-10-12-13 6-10 $5
4-6 $8
1-4 $10
10-12 $14
12-13 $26

Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($20). Path 1-2-5-7-11-13 will decrease by 1 week.

Activity 6-10 will be crashed first by 1 week since it has the lowest crashing cost ($5). Path 1-4-6-10-12-13 will decrease by 1 week.

The combined crash cost ($25) is ≤ $40.

Step 4:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 32
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 32

Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-3-8-11-13 1-3 $12
11-13 $30
8-11 $40
1-4-6-10-12-13 4-6 $8
1-4 $10
6-10 $12
10-12 $14
12-13 $26

Activity 11-13 will be crashed first by 1 week since it has the lowest crashing cost ($30). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.

Activity 4-6 will be crashed first by 1 week since it has the lowest crashing cost ($8). Path 1-4-6-10-12-13 will decrease by 1 week.

The combined crash cost ($38) is ≤ $40.

Step 5:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 31
1-3-8-11-13 31
1-3-9-12-13 20
1-4-6-10-12-13 31

Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $33
1-3-8-11-13 1-3 $12
11-13 $33
8-11 $40
1-4-6-10-12-13 1-4 $10
6-10 $12
4-6 $13
10-12 $14
12-13 $26

Activity 11-13 could be crashed first by 1 week since it has the lowest crashing cost ($33). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.

Activity 1-4 could be crashed first by 1 week since it has the lowest crashing cost ($10). Path 1-4-6-10-12-13 will decrease by 1 week.

The combined crash cost ($43) is ≥ $40.

Since the marginal cost of crashing is greater than the marginal benefit of crashing, crashing will be stopped at step 4.

The final project duration time is 31 weeks. The activities that are crashed are:

Activity 7-11 (First week)

Activity 7-11 (Second week)

Activity 1-2

Activity 6-10

Activity 11-13

Activity 4-6

Calculation of total crashing cost:

The total crashing cost is calculated by summing the crashing cost involved all the steps and the indirect costs every week.

Total crashing cost=15+18+25+38+(31 weeks×$40)=96+1,240=$1,336

The activities to be crashed are: 7-11, 1-2, 6-10, 11-13, and 4-6. The total crashing cost is $1,336,000.

b)

Expert Solution
Check Mark
Summary Introduction

To Plot: The cost curve with the least expensive crashing which will reduce the project by 6 weeks.

Introduction:

Project crashing:

It is method to shorten the total time taken for a project by reducing the time taken for one or more activities on the critical path. The reduction in the normal time taken is known as crashing.

Answer to Problem 15P

Cost curve:

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 17, Problem 15P , additional homework tip  2

Explanation of Solution

Given information:

  • Indirect cost is $40,000 per week.

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 17, Problem 15P , additional homework tip  3

Activity Crash cost first week ($000) Crash cost second week ($000) Crash cost third week ($000)
1 to 2 18 22
2 to 5 24 25 25
5 to 7 30 30 35
7 to 11 15 20
11 to 13 30 33 36
1 to 3 12 24 26
3 to 8
8 to 11 40 40 40
3 to 9 3 10 12
9 to 12 2 7 10
12 to 13 26
1 to 4 10 15 25
4 to 6 8 13
6 to 10 5 12
10 to 12 14 15

Project crashing:

Calculation of expected duration of each path:

Path 1-2-5-7-11-13:

Expected duration=5+8+7+4+11=35

Path 1-3-8-11-13:

Expected duration=4+12+5+11=32

Path 1-3-9-12-13:

Expected duration=4+6+9+1=20

Path 1-4-6-10-12-13:

Expected duration=3+12+9+8+1=33

Step 1:

Critical path is 1-2-5-7-11-13.

The activities are ranked according to the cost per week to crash.

Activity Cost ($)
7-11 15
1-2 18
2-5 24
5-7 30
11-13 30

Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($15) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.

Step 2:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 34
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33

Critical path is 1-2-5-7-11-13.

The activities are ranked according to the cost per week to crash.

Activity Cost ($)
1-2 $18
7-11 $20
2-5 $24
5-7 $30
11-13 $30

Activity 1-2 will be crashed first by 1 week since it has the lowest crashing cost ($18) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.

Step 3:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 33
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33

Critical path is 1-2-5-7-11-13 and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 7-11 $20
1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-4-6-10-12-13 6-10 $5
4-6 $8
1-4 $10
10-12 $14
12-13 $26

Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($20). Path 1-2-5-7-11-13 will decrease by 1 week.

Activity 6-10 will be crashed first by 1 week since it has the lowest crashing cost ($5). Path 1-4-6-10-12-13 will decrease by 1 week.

The combined crash cost ($25) is ≤ $40.

Step 4:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 32
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 32

Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-3-8-11-13 1-3 $12
11-13 $30
8-11 $40
1-4-6-10-12-13 4-6 $8
1-4 $10
6-10 $12
10-12 $14
12-13 $26

Activity 11-13 will be crashed first by 1 week since it has the lowest crashing cost ($30). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.

Activity 4-6 will be crashed first by 1 week since it has the lowest crashing cost ($8). Path 1-4-6-10-12-13 will decrease by 1 week.

The combined crash cost ($38) is ≤ $40.

Step 5:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 31
1-3-8-11-13 31
1-3-9-12-13 20
1-4-6-10-12-13 31

Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $33
1-3-8-11-13 1-3 $12
11-13 $33
8-11 $40
1-4-6-10-12-13 1-4 $10
6-10 $12
4-6 $13
10-12 $14
12-13 $26

Activity 11-13 will be crashed first by 1 week since it has the lowest crashing cost ($33). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.

Activity 1-4 will be crashed first by 1 week since it has the lowest crashing cost ($10). Path 1-4-6-10-12-13 will decrease by 1 week. The combined crash cost is ($43).

Step 6:

The paths and new expected duration are:

Path Expected Duration
1-2-5-7-11-13 30
1-3-8-11-13 30
1-3-9-12-13 20
1-4-6-10-12-13 30

Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.

The activities are ranked according to the cost per week to crash.

Path Activity Cost ($)
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $36
1-3-8-11-13 1-3 $12
11-13 $36
8-11 $40
1-4-6-10-12-13 6-10 $12
4-6 $13
10-12 $14
1-4 $15
12-13 $26

Activity 1-2 will be crashed first by 1 week since it has the lowest crashing cost ($22). Path 1-2-5-7-11-13 will decrease by 1 week.

Activity 1-3 will be crashed first by 1 week since it has the lowest crashing cost ($12). Path 1-3-8-11-13 will decrease by 1 week.

Activity 6-10 will be crashed first by 1 week since it has the lowest crashing cost ($12). Path 1-4-6-10-12-13 will decrease by 1 week. The combined crash cost is ($436.

The final project duration time is 29 weeks. The activities that are crashed are:

Activity 7-11 (First week)

Activity 7-11 (Second week)

Activity 1-2 (First week)

Activity 1-2 (Second week)

Activity 11-13 (First week)

Activity 11-13 (Second week)

Activity 4-6

Activity 6-10

Activity 1-4

Activity 1-3

Calculation of total crashing cost:

The total crashing cost is calculated by summing the crashing cost involved all the steps and the indirect costs every week.

Total crashing cost=15+18+25+38+(29 weeks×$40)=185+1,160=$1,345

Summarization of total costs for different project lengths:

Project Length Cumulative Weeks shortened Cumulative crash cost ($000) Indirect cost ($000) Total cost ($000)
A B C (D=A×40) E = C+D
35 0  $                              -    $   1,400.00  $ 1,400.00
34 1  $                         15.00  $   1,360.00  $ 1,375.00
33 2  $                         33.00  $   1,320.00  $ 1,353.00
32 3  $                         58.00  $   1,280.00  $ 1,338.00
31 4  $                         96.00  $   1,240.00  $ 1,336.00
30 5  $                       139.00  $   1,200.00  $ 1,339.00
29 6  $                       185.00  $   1,160.00  $ 1,345.00

Cost curve:

The cost curve is plotted by taking the project length on the X-axis and the total cost on the Y-axis.

Operations Management (McGraw-Hill Series in Operations and Decision Sciences), Chapter 17, Problem 15P , additional homework tip  4

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Excel Please. The workload of many areas of banking operations varies considerably based on time of day.  A variable capacity can be achieved effectively by employing part-time personnel.  Because part-timers are not entitled to all the fringe benefits, they are often more economical than full-time employees.  Other considerations, however, may limit the extent to which part-time people can be hired in a given department.  The problem is to find an optimal workforce schedule that would meet personnel requirements at any given time and also be economical.   Some of the factors affecting personnel assignments are listed here:   The bank is open from 9:00am to 7:00pm. Full-time employees work for 8 hours (1 hour for lunch included) per day. They do not necessarily have to start their shift when the bank opens. Part-time employees work for at least 4 hours per day, but less than 8 hours per day and do not get a lunch break. By corporate policy, total part-time personnel hours is limited…
IM.84 An outdoor equipment manufacturer sells a rugged water bottle to complement its product line. They sell this item to a variety of sporting goods stores and other retailers. The manufacturer offers quantity discounts per the following discount schedule: Option Plan Quantity Price A 1 - 2,399 $5.50 B 2,400 - 3,999 $5.20 C 4,000+ $4.50 A large big-box retailer expects to sell 9,700 units this year. This retailer estimates that it incurs an internal administrative cost of $225 each time it places an order with the manufacturer. Holding cost for the retailer is $55 per case per year. (There are 40 units or water bottles per case.) Based on this information, and not taking into account any quantity discount offers, what is the calculated EOQ (in units)? (Display your answer to the nearest whole number.) Number Based on this information, sort each quantity discount plan from left to right by dragging the MOST preferred option plan to the left, and the LEAST preferred…
In less than 150 words, what is an example of what your reflection of core values means to you and your work: Commitment, Perseverance, Community, Service, Pride?

Chapter 17 Solutions

Operations Management (McGraw-Hill Series in Operations and Decision Sciences)

Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY