A construction project has indirect costs totaling $40,000 per week. Major activities in the project and their expected times in weeks are shown in this precedence diagram.
Crashing costs for each activity are:
a. Determine the optimum time–cost crashing plan.
b. Plot the total-cost curve that describes the least expensive crashing
a)
To determine: The optimum cost-saving plan.
Introduction:
Project crashing:
It is method to shorten the total time taken for a project by reducing the time taken for one or more activities on the critical path. The reduction in the normal time taken is known as crashing.
Answer to Problem 15P
Explanation of Solution
Given information:
- Indirect cost is $40,000 per week.
Activity | Crash cost first week ($000) | Crash cost second week ($000) | Crash cost third week ($000) |
1 to 2 | 18 | 22 | |
2 to 5 | 24 | 25 | 25 |
5 to 7 | 30 | 30 | 35 |
7 to 11 | 15 | 20 | |
11 to 13 | 30 | 33 | 36 |
1 to 3 | 12 | 24 | 26 |
3 to 8 | |||
8 to 11 | 40 | 40 | 40 |
3 to 9 | 3 | 10 | 12 |
9 to 12 | 2 | 7 | 10 |
12 to 13 | 26 | ||
1 to 4 | 10 | 15 | 25 |
4 to 6 | 8 | 13 | |
6 to 10 | 5 | 12 | |
10 to 12 | 14 | 15 |
Project crashing:
Calculation of expected duration of each path:
Path 1-2-5-7-11-13:
Path 1-3-8-11-13:
Path 1-3-9-12-13:
Path 1-4-6-10-12-13:
Step 1:
Critical path is 1-2-5-7-11-13.
The activities are ranked according to the cost per week to crash.
Activity | Cost ($) |
7-11 | 15 |
1-2 | 18 |
2-5 | 24 |
5-7 | 30 |
11-13 | 30 |
Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($15) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.
Step 2:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 34 |
1-3-8-11-13 | 32 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 33 |
Critical path is 1-2-5-7-11-13.
The activities are ranked according to the cost per week to crash.
Activity | Cost ($) |
1-2 | $18 |
7-11 | $20 |
2-5 | $24 |
5-7 | $30 |
11-13 | $30 |
Activity 1-2 will be crashed first by 1 week since it has the lowest crashing cost ($18) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.
Step 3:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 33 |
1-3-8-11-13 | 32 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 33 |
Critical path is 1-2-5-7-11-13 and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 7-11 | $20 |
1-2 | $22 | |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $30 | |
1-4-6-10-12-13 | 6-10 | $5 |
4-6 | $8 | |
1-4 | $10 | |
10-12 | $14 | |
12-13 | $26 |
Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($20). Path 1-2-5-7-11-13 will decrease by 1 week.
Activity 6-10 will be crashed first by 1 week since it has the lowest crashing cost ($5). Path 1-4-6-10-12-13 will decrease by 1 week.
The combined crash cost ($25) is ≤ $40.
Step 4:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 32 |
1-3-8-11-13 | 32 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 32 |
Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 1-2 | $22 |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $30 | |
1-3-8-11-13 | 1-3 | $12 |
11-13 | $30 | |
8-11 | $40 | |
1-4-6-10-12-13 | 4-6 | $8 |
1-4 | $10 | |
6-10 | $12 | |
10-12 | $14 | |
12-13 | $26 |
Activity 11-13 will be crashed first by 1 week since it has the lowest crashing cost ($30). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.
Activity 4-6 will be crashed first by 1 week since it has the lowest crashing cost ($8). Path 1-4-6-10-12-13 will decrease by 1 week.
The combined crash cost ($38) is ≤ $40.
Step 5:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 31 |
1-3-8-11-13 | 31 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 31 |
Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 1-2 | $22 |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $33 | |
1-3-8-11-13 | 1-3 | $12 |
11-13 | $33 | |
8-11 | $40 | |
1-4-6-10-12-13 | 1-4 | $10 |
6-10 | $12 | |
4-6 | $13 | |
10-12 | $14 | |
12-13 | $26 |
Activity 11-13 could be crashed first by 1 week since it has the lowest crashing cost ($33). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.
Activity 1-4 could be crashed first by 1 week since it has the lowest crashing cost ($10). Path 1-4-6-10-12-13 will decrease by 1 week.
The combined crash cost ($43) is ≥ $40.
Since the marginal cost of crashing is greater than the marginal benefit of crashing, crashing will be stopped at step 4.
The final project duration time is 31 weeks. The activities that are crashed are:
Activity 7-11 (First week)
Activity 7-11 (Second week)
Activity 1-2
Activity 6-10
Activity 11-13
Activity 4-6
Calculation of total crashing cost:
The total crashing cost is calculated by summing the crashing cost involved all the steps and the indirect costs every week.
The activities to be crashed are: 7-11, 1-2, 6-10, 11-13, and 4-6. The total crashing cost is $1,336,000.
b)
To Plot: The cost curve with the least expensive crashing which will reduce the project by 6 weeks.
Introduction:
Project crashing:
It is method to shorten the total time taken for a project by reducing the time taken for one or more activities on the critical path. The reduction in the normal time taken is known as crashing.
Answer to Problem 15P
Cost curve:
Explanation of Solution
Given information:
- Indirect cost is $40,000 per week.
Activity | Crash cost first week ($000) | Crash cost second week ($000) | Crash cost third week ($000) |
1 to 2 | 18 | 22 | |
2 to 5 | 24 | 25 | 25 |
5 to 7 | 30 | 30 | 35 |
7 to 11 | 15 | 20 | |
11 to 13 | 30 | 33 | 36 |
1 to 3 | 12 | 24 | 26 |
3 to 8 | |||
8 to 11 | 40 | 40 | 40 |
3 to 9 | 3 | 10 | 12 |
9 to 12 | 2 | 7 | 10 |
12 to 13 | 26 | ||
1 to 4 | 10 | 15 | 25 |
4 to 6 | 8 | 13 | |
6 to 10 | 5 | 12 | |
10 to 12 | 14 | 15 |
Project crashing:
Calculation of expected duration of each path:
Path 1-2-5-7-11-13:
Path 1-3-8-11-13:
Path 1-3-9-12-13:
Path 1-4-6-10-12-13:
Step 1:
Critical path is 1-2-5-7-11-13.
The activities are ranked according to the cost per week to crash.
Activity | Cost ($) |
7-11 | 15 |
1-2 | 18 |
2-5 | 24 |
5-7 | 30 |
11-13 | 30 |
Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($15) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.
Step 2:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 34 |
1-3-8-11-13 | 32 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 33 |
Critical path is 1-2-5-7-11-13.
The activities are ranked according to the cost per week to crash.
Activity | Cost ($) |
1-2 | $18 |
7-11 | $20 |
2-5 | $24 |
5-7 | $30 |
11-13 | $30 |
Activity 1-2 will be crashed first by 1 week since it has the lowest crashing cost ($18) and this cost is ≤ 40. Path 1-2-5-7-11-13 will decrease by 1 week.
Step 3:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 33 |
1-3-8-11-13 | 32 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 33 |
Critical path is 1-2-5-7-11-13 and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 7-11 | $20 |
1-2 | $22 | |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $30 | |
1-4-6-10-12-13 | 6-10 | $5 |
4-6 | $8 | |
1-4 | $10 | |
10-12 | $14 | |
12-13 | $26 |
Activity 7-11 will be crashed first by 1 week since it has the lowest crashing cost ($20). Path 1-2-5-7-11-13 will decrease by 1 week.
Activity 6-10 will be crashed first by 1 week since it has the lowest crashing cost ($5). Path 1-4-6-10-12-13 will decrease by 1 week.
The combined crash cost ($25) is ≤ $40.
Step 4:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 32 |
1-3-8-11-13 | 32 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 32 |
Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 1-2 | $22 |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $30 | |
1-3-8-11-13 | 1-3 | $12 |
11-13 | $30 | |
8-11 | $40 | |
1-4-6-10-12-13 | 4-6 | $8 |
1-4 | $10 | |
6-10 | $12 | |
10-12 | $14 | |
12-13 | $26 |
Activity 11-13 will be crashed first by 1 week since it has the lowest crashing cost ($30). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.
Activity 4-6 will be crashed first by 1 week since it has the lowest crashing cost ($8). Path 1-4-6-10-12-13 will decrease by 1 week.
The combined crash cost ($38) is ≤ $40.
Step 5:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 31 |
1-3-8-11-13 | 31 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 31 |
Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 1-2 | $22 |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $33 | |
1-3-8-11-13 | 1-3 | $12 |
11-13 | $33 | |
8-11 | $40 | |
1-4-6-10-12-13 | 1-4 | $10 |
6-10 | $12 | |
4-6 | $13 | |
10-12 | $14 | |
12-13 | $26 |
Activity 11-13 will be crashed first by 1 week since it has the lowest crashing cost ($33). Paths 1-2-5-7-11-13 and 1-3-8-11-13 will decrease by 1 week.
Activity 1-4 will be crashed first by 1 week since it has the lowest crashing cost ($10). Path 1-4-6-10-12-13 will decrease by 1 week. The combined crash cost is ($43).
Step 6:
The paths and new expected duration are:
Path | Expected Duration |
1-2-5-7-11-13 | 30 |
1-3-8-11-13 | 30 |
1-3-9-12-13 | 20 |
1-4-6-10-12-13 | 30 |
Critical path is 1-2-5-7-11-13, 1-3-8-11-13, and 1-4-6-10-12-13.
The activities are ranked according to the cost per week to crash.
Path | Activity | Cost ($) |
1-2-5-7-11-13 | 1-2 | $22 |
2-5 | $24 | |
5-7 | $30 | |
11-13 | $36 | |
1-3-8-11-13 | 1-3 | $12 |
11-13 | $36 | |
8-11 | $40 | |
1-4-6-10-12-13 | 6-10 | $12 |
4-6 | $13 | |
10-12 | $14 | |
1-4 | $15 | |
12-13 | $26 |
Activity 1-2 will be crashed first by 1 week since it has the lowest crashing cost ($22). Path 1-2-5-7-11-13 will decrease by 1 week.
Activity 1-3 will be crashed first by 1 week since it has the lowest crashing cost ($12). Path 1-3-8-11-13 will decrease by 1 week.
Activity 6-10 will be crashed first by 1 week since it has the lowest crashing cost ($12). Path 1-4-6-10-12-13 will decrease by 1 week. The combined crash cost is ($436.
The final project duration time is 29 weeks. The activities that are crashed are:
Activity 7-11 (First week)
Activity 7-11 (Second week)
Activity 1-2 (First week)
Activity 1-2 (Second week)
Activity 11-13 (First week)
Activity 11-13 (Second week)
Activity 4-6
Activity 6-10
Activity 1-4
Activity 1-3
Calculation of total crashing cost:
The total crashing cost is calculated by summing the crashing cost involved all the steps and the indirect costs every week.
Summarization of total costs for different project lengths:
Project Length | Cumulative Weeks shortened | Cumulative crash cost ($000) | Indirect cost ($000) | Total cost ($000) |
A | B | C |
|
E = C+D |
35 | 0 | $ - | $ 1,400.00 | $ 1,400.00 |
34 | 1 | $ 15.00 | $ 1,360.00 | $ 1,375.00 |
33 | 2 | $ 33.00 | $ 1,320.00 | $ 1,353.00 |
32 | 3 | $ 58.00 | $ 1,280.00 | $ 1,338.00 |
31 | 4 | $ 96.00 | $ 1,240.00 | $ 1,336.00 |
30 | 5 | $ 139.00 | $ 1,200.00 | $ 1,339.00 |
29 | 6 | $ 185.00 | $ 1,160.00 | $ 1,345.00 |
Cost curve:
The cost curve is plotted by taking the project length on the X-axis and the total cost on the Y-axis.
Want to see more full solutions like this?
Chapter 17 Solutions
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
- I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to use my forecast numbers to generate a Master Production Schedule (MPS) I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022 April 2023 I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.arrow_forwardSolve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forward
- What are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forwardWhat is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forward
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.