A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
a. Construct a network diagram. You can use either AOA or AON (see Example 5).
b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus.
a)

To construct: A network diagram.
Answer to Problem 12P
Answer
Network diagram:
Explanation of Solution
Given information:
Activity | Immediate predecessor | Optimistic time | Most likely time | Pessimistic time |
A | 2 | 4 | 6 | |
D | A | 6 | 8 | 10 |
E | D | 7 | 9 | 12 |
H | E | 2 | 3 | 5 |
F | A | 3 | 4 | 8 |
G | F | 5 | 7 | 9 |
B | 2 | 2 | 3 | |
I | B | 2 | 3 | 6 |
J | I | 3 | 4 | 5 |
K | J | 4 | 5 | 8 |
C | 5 | 8 | 12 | |
M | C | 1 | 1 | 1 |
N | M | 6 | 7 | 11 |
O | N | 8 | 9 | 13 |
End | H, G, K, O |
Formula to calculate expected time and variance:
Calculation of mean and variance:
Activity | Optimistic time | Most likely time | Pessimistic time | Expected time | Standard deviation | Variance |
A | B | C | (A+(4*B)+C)/6 | (C-A)/6 | (C-A)^2/6^2 | |
A | 2 | 4 | 6 | 4 | 0.667 | 0.444 |
D | 6 | 8 | 10 | 8 | 0.667 | 0.444 |
E | 7 | 9 | 12 | 9.17 | 0.833 | 0.694 |
H | 2 | 3 | 5 | 3.17 | 0.500 | 0.250 |
F | 3 | 4 | 8 | 4.5 | 0.833 | 0.694 |
G | 5 | 7 | 9 | 7 | 0.667 | 0.444 |
B | 2 | 2 | 3 | 2.17 | 0.167 | 0.028 |
I | 2 | 3 | 6 | 3.33 | 0.667 | 0.444 |
J | 3 | 4 | 5 | 4 | 0.333 | 0.111 |
K | 4 | 5 | 8 | 5.33 | 0.667 | 0.444 |
C | 5 | 8 | 12 | 8.17 | 1.167 | 1.361 |
M | 1 | 1 | 1 | 1 | 0.000 | 0.000 |
N | 6 | 7 | 11 | 7.5 | 0.833 | 0.694 |
O | 8 | 9 | 13 | 9.5 | 0.833 | 0.694 |
End |
Network diagram:
The activity on arrow diagram is constructed. The activities are mentioned on the arrows. The arrows in the diagram are mentioned in the precedence order. The arrows indicates the successor for each node.
b)

To determine: The probability of each bonus.
Answer to Problem 12P
Explanation of Solution
Given information:
- If the project is finished in 26 weeks the bonus is $1,000.
- If the project is finished in 27 weeks the bonus is $500.
Calculation of expected duration, variance and standard deviation for each path:
Path A-D-E-H:
Path A-F-G:
Path B-I-J-K:
Path C-M-N-O:
Bonus of $1,000 (less than or equal to 26 weeks):
Calculation of probability of completion in less than or equal to 26 weeks:
Calculation of z value for all paths:
Formula:
Path A-D-E-H:
From the standard normal distribution table,
The probability value for (z = 1.23) is 0.8907.
Path A-F-G:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path B-I-J-K:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path C-M-N-O:
From the standard normal distribution table,
The probability value for (z = -0.10) is 0.4602.
Probability of completion in less than or equal to 26 weeks:
The probability of achieving a bonus of $1,000 is 0.4099.
Bonus of $500 (less than or equal to 27 weeks):
Calculation of probability of completion in less than or equal to 27 weeks:
Calculation of z value for all paths:
Formula:
Path A-D-E-H:
From the standard normal distribution table,
The probability value for (z = 1.96) is 0.9750.
Path A-F-G:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path B-I-J-K:
Since z value is greater than +3.00, probability of completion is 1.0000.
Path C-M-N-O:
From the standard normal distribution table,
The probability value for (z = 0.50) is 0.6915.
Probability of completion in less than or equal to 27 weeks:
The probability of achieving a bonus of $500 is 0.6742.
Want to see more full solutions like this?
Chapter 17 Solutions
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
- by the end of 2013, the IPL port was operational and the naphtha was flowing to the Himachal Fertilizer Corporation (HFC) plant in Central India after being granted the port contract in Summer 2012. The plant was located in an industrial area that had several pipelines in the general geographic area including a crude oil pipeline leading to a refinery, and a pipeline carrying pesticides to be processed and redistributed to local farms in the area. In July 2014, Ajay Patel, the logistics general manager received notification that there were some minor leaks along the pipeline that were being fixed. Workers in the area had experienced sudden headaches and lightheadedness and the company immediately moved to investigate the leak and address faulty seams that had eroded and weakened. The flow of naphtha was temporarily stopped for 72 hours so two portions of the pipeline could be removed, and the eroded portions replaced. Patel put enormous pressure on the repair team to get the repair…arrow_forwardin the MABE: learning to be multinational case report, what is the reccomended course of action?arrow_forwardIn the MABE case report what would be the reccomened course of action?arrow_forward
- Question 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i) Solve this LPP by using graphical analysis ii) What will be the slack at the optimal solution point? Show calculation.arrow_forwardqusestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i. Formulate a linear programming model of the problem for the company. ii Convert the linear programming model formulated in (a) to a standard form.arrow_forwardG ווח >>> Mind Tap Cengage Learning 1- CENGAGE MINDTAP Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 e Submit 自 A ng.cengage.com C Excel Online Student Work G A retail store records customer demand during each sales period. 1. What is the f... Q Search this course ? ✓ Co Excel Online Tutorial Excel Online Activity: Exponential Smoothing A-Z A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. Office Video X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 25.10 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 21.88 Activity Frame ? 3. Choose the correct graph for the single exponential…arrow_forward
- Not use ai pleasearrow_forwardItems removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG SORT STORD KNUJ STUFF FUDGarrow_forwardCould you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?arrow_forward
- Apple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forwardCritical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forwardwhat is an other difination for principle?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,