Textbook Question
Chapter 16, Problem 6P
The following table contains information concerning four jobs that are awaiting processing at a work center.
Sequence the jobs using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. Assume the list is by order of arrival.
b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.
c. Is one method superior to the others? Explain.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What are the advantages and disadvantages of the shortest processing time (SPT) rule?
Consider a workstation that has one maintenance mechanic to repair failed machines. We can think of the mechanic as the processor (scarce resource) and the machines awaiting repair as the jobs. Let us assume that
six machines are down, with estimated repair times given here, and that no new machines fail.
2 3 4
Job (fix
machine #)
Processing time
(hours)
Compute the flow time for each job using both the FCFS rule and the SPT rule, and compare the average flow times. Round your answers for average values to the nearest whole number.
1
NO †
4
5
6
Sequence
-Seled-
Average flow time (FCFS rule):
-Select- Y
-Select-
-Select- V
FCFS Rule
-Select- Y
7 1
Flow Time (hours)
SPT rule
Flow Time (hours)
hours
Average flow time (SPT rule):
hours
-Select- ✔ minimizes flow time and gets the most work done in the least amount of time.
Apply the four popular sequencing rules to the five jobs shown in the table below.
For each sequence determine:
The average completion time (sum of total flow time/number of jobs)
Utilisation measure (Total job work time/Sum of total flow time)
Average number of jobs in system (Sum of total flow time/Total job work time)
Average job lateness (Total late days/Number of jobs)
Job Due
Job Work (Processing)
Time
Date
(Days)
(Days)
8
6
18
15
23
Job
ABCDE
6 W ∞ NO
6
2
8
3
9
Chapter 16 Solutions
OPERATIONS MANAGEMENT -CONNECT
Ch. 16 - Why is scheduling fairly simple for repetitive...Ch. 16 - Prob. 2DRQCh. 16 - What are Gantt charts? How are they used in...Ch. 16 - Prob. 4DRQCh. 16 - Briefly describe each of these priority rules: a....Ch. 16 - Why are priority rules needed?Ch. 16 - What problems not generally found in manufacturing...Ch. 16 - Explain forward and backward schedulings and each...Ch. 16 - Prob. 9DRQCh. 16 - Prob. 10DRQ
Ch. 16 - Prob. 11DRQCh. 16 - What general trade-offs are involved in sequencing...Ch. 16 - Prob. 2TSCh. 16 - Prob. 3TSCh. 16 - One approach that can be effective in reducing the...Ch. 16 - Doctors and dentists offices frequently schedule...Ch. 16 - Prob. 3CTECh. 16 - Use the assignment method to determine the best...Ch. 16 - Rework Problem 1, treating the numbers in the...Ch. 16 - Assign trucks to delivery routes so that total...Ch. 16 - Develop an assignment plan that will minimize...Ch. 16 - Use the assignment method to obtain a plan that...Ch. 16 - The following table contains information...Ch. 16 - Using the information presented in the following...Ch. 16 - The following table shows orders to be processed...Ch. 16 - A wholesale grocery distribution center uses a...Ch. 16 - The times required to complete each of eight jobs...Ch. 16 - Prob. 11PCh. 16 - A shoe repair operation uses a two-step sequence...Ch. 16 - The following schedule was prepared by the...Ch. 16 - The production manager must determine the...Ch. 16 - A foreman has determined processing times at a...Ch. 16 - Given the information in the following table,...Ch. 16 - Given the following information on job times and...Ch. 16 - Prob. 18PCh. 16 - The following table contains order-dependent setup...Ch. 16 - The following table contains order-dependent setup...Ch. 16 - Prob. 21PCh. 16 - Given this information on planned and actual...Ch. 16 - Given the following data on inputs and outputs at...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Determine the minimum number of workers needed,...Ch. 16 - Prob. 1CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival): Job A B с D E F Processing Time (Days) 2 5 7 6 4 10 Due Date: (days from Now) 2 6 15 12 8 3 What is the average flow time for the earliest due date (EDD) rule schedule?arrow_forwardstate whether or not each situation would be considered “compensable time” (and why or why not). An employee of a fast food chain has to arrive at work 15 minutes early to change into the“mascot” costume and it typically takes another 15 minutes at the end of the shift to change outof the costume and properly store it. Due to the cost of the costume, employees are notallowed to take the costume home. The “mascots” typically work from 10am – 2pm, to coverthe lunch rush periods. How much time would be “compensable” for the mascots, assumingthe conditions/schedule listed above?2) George is a Radiology Technician at a local hospital and when on call, is required to be nofurther than 30 minutes away from the facility. Is the “on call” time, compensable?arrow_forwardGiven the projects displayed in Table 18.21, if FCFS is used to sequence the jobs, whatis the average flow time of the projects (in hours)?arrow_forward
- The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.arrow_forwardFive customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates were set based on available technicians; however, one technician had a medical emergency and will be unavailable for at least two weeks so processing times were adjusted. Customer job 1 Processing time (days) Due date (days) 6 Use the EDD rule and compute the start time, flow time, lateness, and tardiness for each job. Use minus sign to enter negative lateness values, if any. If your answer is zero, enter "0". Sequence Start Time, days Flow Time, days Lateness, days Tardiness, days -Select- -Select- -Sclect. -Select- -Select- UI 5 LI TE 10 MAarrow_forwardCourtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. Due date Duration (hours required) Job (hours hence) A 8 16 2 C 24 10 32 16 E 12 6 In what sequence would the jobs be ranked according to the following decision rules: FCFS, EDD, SPT, LPT? According to the FCFS rule, the sequence of jobs should be According to the EDD rule, the sequence of jobs should be According to the SPT rule, the sequence of jobs should be According to the LPT rule, the sequence of jobs should bearrow_forward
- If the jobs displayed in Table 18.23 are processed using the earliest-due-date rule, whatis the average flow time?arrow_forwardCourtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. JOB DUE DATE (HOURS HENCE) 18 36 10 22 14 E a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should be b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What is the average number of jobs in the system? The average number of jobs in the system is place). DURATION (HOURS REQUIRED) 3 19 4 9 5 days (round your response to one decimal place) days (round your response to one decimal place). jobs (round your response to one decimalarrow_forwardCourtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. DURATION (HOURS JOB k A BUD C E DUE DATE (HOURS HENCE) 10 16 14 36 26 REQUIRED) 6 3 7 15 8 a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should be A, C, B, E, D b) What is the average completion (flow) time? The average completion (flow) time is days (round your response to one decimal place).arrow_forward
- Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, which job should be scheduled first in the sequence? O A. V OB. U O C. R OD. S O E. T Job R S T Alpha 20 23 50 26 55 Beta 34 35 20 26 75arrow_forwardFour trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that hasonly a single service bay. The trucks are labeled in the order that they arrived at thedock. Assume the current time is 1:00 P.M. The times required to unload each truck and the times that the goods they contain are due in the plant are given in thefollowing table.Truck Unloading Time (minutes) Time Material Is Due1 20 1:25 P.M.2 14 1:45 P.M.3 35 1:50 P.M.4 10 1:30 P.M.Determine the schedules that result for each of the rules FCFS, SPT, EDD, andCR. In each case compute the mean flow time, average tardiness, and number oftardy jobs.arrow_forwardPlease do not give solution in image format thankuarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY